Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites

CourtCourt of Appeals of Iowa
DecidedMay 1, 2019
Docket18-0622
StatusPublished

This text of Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites (Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites, (iowactapp 2019).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 18-0622 Filed May 1, 2019

REICHER ELECTRIC, INC., Plaintiff-Appellant,

vs.

ATUL PATEL and SHRI GANAPATI & BAJRANGBALI, INC., an Iowa Corporation, d/b/a FAIRFIELD INN & SUITES, Defendants-Appellees. ________________________________________________________________

Appeal from the Iowa District Court for Black Hawk County, John J.

Bauercamper, Judge.

A subcontractor appeals a district court order denying a claim for unjust

enrichment. AFFIRMED.

Dan McClean of McClean & Heavens Law Offices, Dyersville, for appellant.

Max E. Kirk of Ball, Kirk & Holm PC, Waterloo, for appellees.

Considered by Tabor, P.J., and Mullins and Bower, JJ. 2

BOWER, Judge.

Reicher Electric, Inc. (Reicher) appeals the district court’s ruling in favor of

Atul Patel and Shri Ganapati & Bajrangbali, Inc. (SGB). Reicher contends SGB

was unjustly enriched by receiving the benefit of work when Reicher was not paid.

We find Reicher did not establish a direct contract between Reicher and SGB and

cannot support a claim of unjust enrichment.

I. Background Facts & Proceedings

On August 19, 2013, SGB entered into a construction contract with general

contractor Main Street Developers (MSD), a Wisconsin company, to build a

commercial hotel property in Waterloo.1 The contract specified a firm price of

$4,450,000 and required any changes or substitutions be approved by SGB in

writing. Under the agreement, MSD was to “provide all labor, materials, equipment

and services necessary to complete the Work.” The contract had as an exhibit a

list of items to be provided by MSD, including “Interior Lighting Fixtures

(Permanent).”

MSD hired Reicher for the electrical work on the hotel. The contract

provided MSD would pay Reicher $300,000 for the electrical work. After the

project began, MSD approached Reicher and asked for assistance in obtaining the

lighting fixtures; Reicher agreed for a price of ten percent of the cost of the lighting.

1 The parties’ appendix violates the clear requirements in Iowa Rule of Appellate Procedure 6.905(2)(b). In particular, this appendix does not contain the initial pleadings between these parties, a copy of the order in question, a list of relevant docket entries, or relevant portions of the transcript (though a list of relevant transcript portions was included). The briefs refer to documents not included in the appendix. The failure to compile a minimally-adequate appendix forces the court to search a record of over 2000 pages for basic information and impedes the efficiency of this court’s ability to address the issues in a timely manner. 3

Reicher approached Crescent Electric Supply Company (Crescent) to supply the

necessary materials. Following an initial partial estimate from Crescent, MSD

provided $70,000 to Reicher for lighting fixture orders.

After work had already begun, Reicher and Atul Patel, president of SGB,

met with a hotel chain representative who suggested converting to LED lighting

and provided a “spec book” of appropriate fixtures. Reicher informed Patel while

the conversion would save electric costs, it would cost more upfront. Reicher

claims Patel said to change to the LED lighting. Patel testified he never received

a quote for the lighting and did not have a formal meeting with MSD regarding the

LED lighting. No change orders were submitted to SGB or approved for electric

work or light fixtures.

MSD was not present at either LED lighting meeting, but was aware Reicher

was ordering and installing LED lights. The owner of MSD testified the change in

lighting was a separate agreement between Reicher and Patel that MSD was not

part of, and he denied MSD was responsible for paying for the LED lighting.

Numerous other changes to Reicher’s work were requested, including electric car

charging stations, floor boxes in the conference room, rewiring offices, adding

notification lights to sump pumps, and additional outlets. Reicher also had to

rewire for some appliances when fixtures provided by MSD did not match the

electrical requirements on the plans Reicher was working from. Reicher included

costs for all changes in its bill to MSD.

From January 2014 through April 2015, Reicher ordered lighting fixtures

from Crescent. Crescent ordered and Reicher installed the LED lights listed in the

hotel chain’s “spec book.” As the $70,000 was paid over time by MSD, Reicher 4

made payments to Crescent; no other party made payments on the light fixtures

ordered for the hotel. At the end of the project, Reicher still owed $106,209.31 to

Crescent. Reicher provided all the invoices to MSD, and MSD indicated Reicher

probably would not get paid for everything. One week before completion, Reicher

raised the issue of payment with Patel and SGB.

Around the time of opening the hotel, MSD walked off the project without

issuing a statement of substantial completion. After discovering MSD and SGB

would not pay for the LED lighting and extra work performed, Reicher refused to

do additional uncontracted work on the project. Reicher did not complete rebate

forms for the lighting installed and did not complete warranty work in the hotel.2

Some lighting materials were returned to Crescent, but some of the items were

special order or outside the time period for returns and Reicher could not get

refunds for them.

Crescent filed a mechanic’s lien on July 23, 2015, for $104,388.94, naming

Reicher as general contractor for the building owned by SGB. On August 14, 2015,

nearly four months after completing its work on the hotel, Reicher filed a

mechanic’s lien against SGB for items provided between December 2014 and April

2015, claiming a sum of $191,805. It appears Reicher’s mechanic’s lien is still

outstanding.

On November 11, Crescent filed a petition at law against Reicher for breach

of contract, quantum meruit, unjust enrichment, and statement on account.

Crescent requested relief of the principal due plus statutory interest and court

2 According to Reicher, the rebates would have been worth approximately fifteen to twenty thousand dollars. 5

costs. On June 2, 2016, Reicher filed a cross-petition for breach of contract,

quantum meruit, and unjust enrichment against Patel and SGB as third-party

defendants. Reicher did not name MSD in the petition. Reicher claimed to have

entered into an oral contract with Patel and SGB for the installation of electrical

fixtures and lighting at the hotel and to have conferred benefit in the form of

material, services, labor, and time for which the company is entitled to the

reasonable value. Reicher’s requested relief included full contribution and

indemnity, attorney fees, court costs, and interest.

On June 1, 2017, the district court entered a judgment order agreed to by

Crescent and Reicher in favor of Crescent, entering a judgment of $119,207.60

against Reicher.3 On June 8, the cross-petition between Reicher and SGB was

tried to the court.

On February 10, 2018, the court filed its findings of fact, conclusions of law,

judgment and decree. The court found no express contract—written or oral—

existed between Reicher and SGB. The court then noted changes in a contract

between a general contractor and subcontractor do not create a contract between

the subcontractor and the owner. Without contractual privity, the court ruled “no

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henning v. Security Bank
564 N.W.2d 398 (Supreme Court of Iowa, 1997)
Pursell Construction, Inc. v. Hawkeye-Security Insurance Co.
596 N.W.2d 67 (Supreme Court of Iowa, 1999)
Clemens Graf Droste Zu Vischering v. Kading
368 N.W.2d 702 (Supreme Court of Iowa, 1985)
Louie's Floor Covering, Inc. v. DePhillips Interests, Ltd.
378 N.W.2d 923 (Supreme Court of Iowa, 1985)
Ahrendsen v. Iowa Department of Human Services
613 N.W.2d 674 (Supreme Court of Iowa, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Reicher Electric, Inc. v. Atul Patel and Shri Ganapati & Bajrangbali, Inc., and Iowa Corporation, d/b/a Fairfield Inn & Suites, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reicher-electric-inc-v-atul-patel-and-shri-ganapati-bajrangbali-inc-iowactapp-2019.