Benjamin Foster Co. v. Commonwealth

61 N.E.2d 147, 318 Mass. 190, 166 A.L.R. 925, 1945 Mass. LEXIS 552
CourtMassachusetts Supreme Judicial Court
DecidedMay 7, 1945
StatusPublished
Cited by45 cases

This text of 61 N.E.2d 147 (Benjamin Foster Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Benjamin Foster Co. v. Commonwealth, 61 N.E.2d 147, 318 Mass. 190, 166 A.L.R. 925, 1945 Mass. LEXIS 552 (Mass. 1945).

Opinion

Qua, J.

This petition is prosecuted under G. L. (Ter. Ed.) c. 258 to recover for work done and for damages sustained by the petitioner acting as contractor for the metropolitan district water supply commission (St. 1926, c. 375; St. 1927, c. 321) in respect to “Item 8” of “Contract No. 52,” dated August 24, 1936, relating to the construction of the embankment for the main dam of Quabbin Reservoir. The work out of which this litigation arises was performed during the spring, summer and autumn seasons of the years 1937 and 1938.

The petitioner contends' that no express contract ever came into existence between the parties, or that if such contract did come into existence the'petitioner was induced to enter into it by representations made in behalf of the Commonwealth which were substantially false or which were at least only half truths that by reason of concealment of material facts amounted to fraud, and that the Commonwealth broke the contract after it was made. Claim 1 of the petition is a claim to recover $892,581.30 and interest for breach of contract in several respects which, in so far as they are still pressed, will be dealt with later in this opinion. Claim 2 appears to be a claim for damages for deceit, but since damages cannot be recovered against the Commonwealth in tort, Arthur A. Johnson Corp. v. Commonwealth, ante, 88, 92, this claim need not be further considered. Claim 3 is for an undisputed balance most of which has now been paid. An offer of judgment has been made for the remainder. This claim is no longer in controversy. Claim 4 is to recover $892,581.30 and interest on. quantum meruit for work and materials and rests upon the theory that no express contract ever came into existence or upon the theory of rescission of the contract for the alleged fraud. Long v. Athol, 196 Mass. 497, 506. Claims 1 and 4 are in the alternative. No ques[193]*193tian has been raised as to the propriety and sufficiency of the pleadings. We treat claims 1 and 4 as adequate bases for recovery on the grounds contended for by the petitioner, if necessary facts have been established.

The case was heard by an auditor whose findings of fact were to be final. Where cases are referred in this way findings of the auditor which are not inconsistent with each other and which are not shown by the report to be erroneous in law are binding upon the trial court and upon this court, except that the auditor's conclusions of fact reached solely by way of inference from other facts are open to review as matter of fact by the trial court and by this court, and either court may draw additional inferences from facts found. United States Fidelity & Guaranty Co. v. English Construction Co. 303 Mass. 105, 109-112. Galluzzi v. Beverly, 309 Mass. 135. See Arthur A. Johnson Corp. v. Commonwealth, 306 Mass. 347, 350, 351.

In compliance with an order of the court the auditor filed a report on questions of liability only. Thereupon the trial judge ruled that the petitioner was not entitled to recover for work performed and furnished in connection with “Item 8,” except as hereinafter stated. He denied a motion of the petitioner that the court determine that the respondent is liable to the petitioner for work performed and furnished and order further hearings upon the question of damages, and he allowed motions of the respondent for judgment in its favor on claims 2 and 4 and that “a final decision ... be entered” in its favor on claims 1 and 3 in so far as they relate to “Item 8” of “Contract 52,” except as to the balance admittedly due of $12,801.64. He then reported his action upon the motions. G. L. (Ter. Ed.) c. 231, § 111. The action of the judge is a decision in favor of the respondent of all issues argued before us.

The embankment of the main dam, now known as Winsor dam, is about a half mile in length and rises to a height of about one hundred seventy feet above the original valley surface. It crosses, the bed of Swift River. Its ends rest upon hills on each side of the river. It is constructed of [194]*194earthen materials. According to the “Information for Bidders” which accompanied the contract it is about eight hundred feet wide between the upstream and downstream faces at a distance of' one hundred thirty feet from the top, toward which the slopes taper. It creates a lake of an area of about thirty-nine square miles. It was estimated to contain three million five hundred fifty thousand cubic yards of earth. The total bid of the petitioner for all the work contained in “Contract No. 52” was $2,317,445. Of this sum $1,136,000 was for the embankment, calculated at a unit price per cubic yard. The embankment was designated as “Item 8.”

The embankment was required to be built by the so called full hydraulic method. The dominating characteristics of this method may be described as follows. The embankment is- built upon a foundation which is in the form of a very broad shallow trough, the lowest part of which is along the center line of the dam. The materials of which the dam is to be composed, such as earth, sand, gravel, and small stones, are mixed with water and sluiced through pipes upon the sides of the trough at their outer edges. The coarsest and heaviest materials come to rest-near what are to be the outside faces of the dam. Finer materials are deposited farther down along the slopes of the trough, called the beaches, while the finest materials of all, called fines, are held in suspension in the water, which gathers in a long, narrow pool running lengthwise of the dam along its center line. The fines are slowly precipitated in the form of thin mud in the center of the dam. The edges of the pool on either side at any given time are determined by the extent to which solid material has been allowed to run down the beaches into the water, that is to say, by the sluicing limits. The pool gradually rises as the dam is built but does not necessarily become deeper, since the deposit of fine material constantly raises the level of its bottom. The coarse materials near the outside of the dam constitute the shoulders and give the dam strength and resisting power but are pervious to water, while the fines precipitated in the pool along the center of the dam be[195]*195come gradually consolidated and form the core, which is fairly impervious to water and prevents undue loss by percolation through the embankment.

. It is readily apparent that the safety and usefulness of a structure of the kind described, with its appurtenances, are dependent upon the constant supervision by skilled engineers of the details of the work during the process of erection, and also that much depends upon the sluicing of proper proportions of coarse materials and fines at the different stages of the work. Accordingly, it is not surprising that the contract throughout contains provisions worded in various ways requiring, in effect, that practically all of the work under "Item 8” shall be performed according to the orders and to the satisfaction of the chief engineer or his assistants. These provisions are detailed, explicit, and emphatic. To a large extent the case hinges upon them. To many of them reference will be made later in this opinion. Whenever in this opinion the word engineer is used in quotations from the contract or otherwise, whether in the singular or in the plural, it refers, unless otherwise indicated, to the chief engineer in the service of the Commonwealth and his assistants acting under his authority.

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frank Realty, Inc. v. Handelsman
17 Mass. L. Rptr. 433 (Massachusetts Superior Court, 2004)
Burlington Landmark Associates, LLC v. RHI Holdings, Inc.
27 F. Supp. 2d 95 (D. Massachusetts, 1998)
John J. Petruzzi-William E. Forrester, Inc. v. Massachusetts Turnpike Authority
9 Mass. L. Rptr. 184 (Massachusetts Superior Court, 1998)
CCM Corp. v. Massachusetts Turnpike Authority
5 Mass. L. Rptr. 58 (Massachusetts Superior Court, 1996)
Northern Heel Corp. v. Compo Industries, Inc.
851 F.2d 456 (First Circuit, 1988)
Samuels v. Brooks
519 N.E.2d 605 (Massachusetts Appeals Court, 1988)
Eastern Air Lines v. Air Line Pilots Ass'n, Intern.
670 F. Supp. 947 (S.D. Florida, 1987)
J. A. Sullivan Corp. v. Commonwealth
494 N.E.2d 374 (Massachusetts Supreme Judicial Court, 1986)
Smith v. Allmon
461 N.E.2d 1237 (Massachusetts Appeals Court, 1984)
Bucciero v. Drinkwater
434 N.E.2d 1315 (Massachusetts Appeals Court, 1982)
J.J. Finn Electrical Service, Inc. v. P & H General Contractors, Inc.
432 N.E.2d 116 (Massachusetts Appeals Court, 1982)
D. Federico Co., Inc. v. Commonwealth
415 N.E.2d 855 (Massachusetts Appeals Court, 1981)
Marrapese v. Rhode Island
500 F. Supp. 1207 (D. Rhode Island, 1980)
Perini Corp. v. Massachusetts Port Authority
308 N.E.2d 562 (Massachusetts Appeals Court, 1974)
Newell v. Mosley
469 S.W.2d 481 (Court of Appeals of Texas, 1971)
Alpert v. Commonwealth
258 N.E.2d 755 (Massachusetts Supreme Judicial Court, 1970)
Farina Bros. v. Commonwealth
257 N.E.2d 450 (Massachusetts Supreme Judicial Court, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
61 N.E.2d 147, 318 Mass. 190, 166 A.L.R. 925, 1945 Mass. LEXIS 552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/benjamin-foster-co-v-commonwealth-mass-1945.