Perini Corp. v. Massachusetts Port Authority

308 N.E.2d 562, 2 Mass. App. Ct. 34, 1974 Mass. App. LEXIS 600
CourtMassachusetts Appeals Court
DecidedMarch 14, 1974
StatusPublished
Cited by5 cases

This text of 308 N.E.2d 562 (Perini Corp. v. Massachusetts Port Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Perini Corp. v. Massachusetts Port Authority, 308 N.E.2d 562, 2 Mass. App. Ct. 34, 1974 Mass. App. LEXIS 600 (Mass. Ct. App. 1974).

Opinion

Armstrong, J.

This is an action brought by Perini Corporation (Perini) to recover damages under a contract to construct the foundation of the Southwest Air Terminal at Logan International Airport. The declaration contains four counts. Counts one and two are a claim for payment at a unit price fixed by the contract for certain “preexcavation” or predrilling of locations where piles were to be driven, which predrilling Perini [35]*35contends is required by the contract, but the defendant Massachusetts Port Authority (Authority) contends is in excess of contract requirements. Counts three and four are an extra work claim by Perini, which maintains that its subcontractor was required by the Authority’s engineer to drive certain piles in excess of contract requirements.

The case was referred to an auditor whose findings of fact were to be final, and who found for Perini on the predrilling claim, and for the Authority on the over-driving claim. The objections of both parties to the auditor’s report were overruled, and the report was confirmed, all subject to exceptions duly saved; and judgment was ordered to enter for Perini on counts one and two in the amount of $35,994.00, plus $8,458.59 interest, and for the Authority on counts three and four. The case is here on the Authority’s appeal and bill of exceptions which raise the propriety of the judge’s overruling of the objections to the report, his denial of motions relative to the report, and his order that judgment enter for Perini on counts one and two.

From the auditor’s uncontested findings it appears that Perini and the Authority executed a written contract on June 13, 1966, and that Perini subcontracted with Carter Pile Driving, Inc. (Carter), a firm specializing exclusively in driving piles, to do that part of the work. The specifications called for the placement of 1,009 precast, “prestressed” concrete piles, of an average weight of 20,000 pounds each, driven to rock or hardpan, the “bearing stratum on which the pile rests.” Section 4-10 of the specifications, entitled “PreExcavation,” provided:

“Immediately before each pile is driven, a hole shall be pre-drilled at the pile location to a minimum of 60 ft. depth below the cut off elevation of the piles or within 5 feet of the top of the rock or hardpan. The hole shall be 18 inches in diameter. Drilling shall be by the wet rotary method; augering will not be permitted.
[36]*36“It is of utmost import?nee that the hole be completely drilled and be kept full of heavy slurry until the pile is placed therein in order to insure holding the sides of the hole in place. The pile shall be lowered into the hole under its own weight.”

Other sections of the specifications required that when each pile stopped descending under its own weight, driving was to begin and to continue without interruption until a certain resistance was met, indicating that the pile had reached the supporting rock or hardpan. Most piles were to be driven in clusters. Each cluster was to be covered with a single, specially designed pile cap.

Perini’s accepted bid proposal was based on an estimate of 61,000 feet of predrilling, or approximately 60 feet per pile. Predrilling was, however, made a unit-price item, to be paid for at the rate of $2.10 per foot “to required depths”. The auditor found that on June 23, 1966, there was a preconstruction meeting, attended by representatives of Perini, Carter, the Authority, Eastern Airlines (which was to occupy the terminal building when completed), Desmond & Lord, the architect and engineer for the project (Desmond), and Sepp Firnkas Engineering, Inc., the structural engineer engaged by Desmond (Firnkas). At that meeting it appears to have been agreed or understood that predrilling would be to a depth of 60 feet below the specified cut-off elevation of the piles, unless construction difficulties made further predrilling advisable.

Carter began driving piles in August. No problems arose in locations where piles were to be driven singly or in small clusters; but on and after August 30, when Carter commenced driving piles for the main building, where piles were to be clustered in groups of nine to twenty-nine piles, it encountered problems of pile tolerance and excessive deviation in placement. On September 2, at a job site conference, Firnkas’ inspector ex[37]*37pressed concern lest the deviations in certain clusters be so great as to require redesign of pile caps. Carter’s representatives suggested that the problems could be eliminated if they were to predrill to a greater depth, and they made a proposal to predrill a pile to a greater depth as a test. The problem was also discussed in letters from Firnkas to Desmond and from Desmond to Perini; and at a job site meeting on September 9 Firnkas’ inspector authorized Carter to predrill one pile to a depth of 80 feet to test the effect on deviation and tolerance. Later the same day, at the location of the 75th pile, Carter predrilled to 80 feet, and encountered no tolerance problem.

On September 16 Perini’s superintendent wrote to Desmond that he had directed Carter to start predrilling to within five feet of rock or hardpan, and to test this procedure immediately on all the piles in one cluster of eighteen or more. The letter stated, “If you feel that a meeting is necessary before we start the deeper pre-drilling, or if you are in disagreement with this procedure, please notify us immediately.” On September 22 Carter began predrilling to 80 feet, starting with pile number 137.

On September 29 Perini received a copy of a letter written September 23 from Firnkas’ project engineer to Desmond, expressing the view that predrilling beyond 60 feet was unnecessary and might well create a problem of uplift “by reducing the soil friction tending to hold the pile down.” He instead recommended certain corrective techniques which the auditor found Carter was already applying.

On September 30 Desmond sent Perini a letter requesting a proposal from Perini to increase the rate of placement of piles so as to meet the contract schedule. At a meeting on October 7, attended by representatives of Firnkas, the Authority, Perini and Carter, numerous measures to accelerate progress were discussed, and mention was made that the deeper predrilling recently [38]*38begun had contributed and would continue to contribute to the acceleration desired.

On October 10 Carter by letter gave Perini a report on its progress in implementing several measures agreed upon, and in the letter stated:

“As you know, the increased depth of drilling which we started on September 22 has cut our redrives from a high of 80 % to an average of 25 %; naturally this is a definite time saver and therefore will increase our production, so we hereby notify you that we will continue to drill up to a maximum depth of within 5/of rock or till.”

On October 13 Perini sent a copy of Carter’s October 10 letter to Desmond and stated:

“Your comments on . . . [Carter’s] observations regarding drilling to depths of eighty (80) feet will be appreciated.”

On October 18 Firnkas sent a letter to Desmond stating:

“We are in receipt of a letter from Carter Pile Driving, Inc., dated October 10, 1966, noting that predrilling operations were now being carried on beyond the required 60 feet. Carter is welcome to do so, but it should be clear that the distance beyond 60 feet will be at his own expense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

H.Q. v. K.Q.
Massachusetts Appeals Court, 2023
Maccurtain v. Nason
107 N.E.3d 1256 (Massachusetts Appeals Court, 2018)
Ostrow Electrical Co. v. J.L. Marshall & Sons, Inc.
798 N.E.2d 310 (Massachusetts Appeals Court, 2003)
J. A. Sullivan Corp. v. Commonwealth
494 N.E.2d 374 (Massachusetts Supreme Judicial Court, 1986)
Hess Oil & Chemical Corp. v. Ristuccia
331 N.E.2d 823 (Massachusetts Appeals Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
308 N.E.2d 562, 2 Mass. App. Ct. 34, 1974 Mass. App. LEXIS 600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/perini-corp-v-massachusetts-port-authority-massappct-1974.