New England Structures, Inc. v. Loranger

234 N.E.2d 888, 354 Mass. 62, 1968 Mass. LEXIS 763
CourtMassachusetts Supreme Judicial Court
DecidedMarch 11, 1968
StatusPublished
Cited by20 cases

This text of 234 N.E.2d 888 (New England Structures, Inc. v. Loranger) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
New England Structures, Inc. v. Loranger, 234 N.E.2d 888, 354 Mass. 62, 1968 Mass. LEXIS 763 (Mass. 1968).

Opinion

Cutter, J.

In one case the plaintiffs, doing business as Theodore Loranger & Sons (Loranger), the general contractor on a school project, seek to recover from New England Struc- *63 turcs, Inc., a subcontractor (New England), damages caused by an alleged breach of the subcontract. Loranger avers that the breach made it necessary for Loranger at greater expense to engage another subcontractor to complete work on a roof deck. In a cross action, New England seeks to recover for breach of the subcontract by Loranger alleged to have taken place when Loranger terminated New England’s right to proceed. The actions were consolidated for trial. A jury returned a verdict for New England in the action brought by Loranger, and a verdict for New England in the sum of $16,860.25 in the action brought by New England against Loranger. The cases are before us on Loranger’s exceptions to the judge’s charge.

Loranger, under date of July 11, 1961, entered into a subcontract with New England by which New England undertook to install a gypsum roof deck in a school, then being built by Loranger. New England began work on November 24, 1961. On December 18, 1961, New England received a telegram from Loranger which read, “Because of your . . . repeated refusal ... or inability to provide enough properly skilled workmen to maintain satisfactory progress, we . . . terminate your right to proceed with work at the . . . school as of December 26, 1961, in accordance with Article ... 5 of our contract. We intend to complete the work . . . with other forces and charge its costs and any additional damages resulting from your repeated delays to your account.” New England replied, “Failure on your [Loranger’s] part to provide . . . approved drawings is the cause of the delay.” The telegram also referred to various allegedly inappropriate changes in instructions.

The pertinent portions of art. 5 of the subcontract are set out in the margin. 1 Article 5 stated grounds on which *64 Loranger might terminate New England’s right to proceed with the subcontract.

There was conflicting evidence concerning (a) how New England had done certain work; (b) whether certain metal cross pieces (called bulb tees) had been properly “staggered” and whether joints had been welded on both sides by certified welders, as called for by the specifications; (c) whether New England had supplied an adequate number of certified welders on certain days; (d) whether and to what extent Loranger had waived certain specifications; and (e) whether New England had complied with good trade practices. The' architect testified -that on December 14, 1961, he had made certain complaints to New England’s president. The work was completed by another company at a cost in excess of New England’s bid. There was also testimony (1) that Loraiiger’s job foreman told one of New England’s welders “to do no work at the job site during the five day period following the date of Loranger’s termination telegram,” and (2) that, “if New England had been permitted to continue its work, it could have completed the entire subcontract . . . within five days following the date of the termination telegram.”

The trial judge ruled, as matter of law, that Loranger, by its termination telegram, confined the justification for its, notice of termination to New England’s “repeated refusal . ... or inability to provide enough properly skilled workmen to maintain satisfactory progress.” He then gave the following instructions: “If you should find that New England- . . . did not furnish a sufficient number of men to perform the required work under the contract within a reasonable time . . . then you would be warranted in finding that Loranger was justified in terminating its contract; and it may recover in its suit against New England .... [TJhe *65 termination . . . cannot, as . . . matter of law, be justified for any . . . reason not stated in the telegram of December 18 . . . including failure to stagger the joints of the bulb tees or failure to weld properly ... or any other reason, unless you find that inherent in the reasons stated in the telegram, namely, failure to provide enough skilled workmen to maintain satisfactory progress, are these aspects. Nevertheless, these allegations by Loranger of deficiency of work on the part of New England Structures may be considered by you, if you find that Loranger was justified in terminating the contract for the reason enumerated in the telegram. You may consider it or them as an element of damages sustained by Loranger . . . .” 2 Counsel for Loranger claimed exceptions to the portion of the judge’s charge quoted above in the body of this opinion. 3

1. Some authority supports the judge’s ruling, in effect, that Loranger, having specified in its telegram one ground for termination of the subcontract, cannot rely in litigation upon other grounds, except to the extent that the other grounds may directly affect the first ground asserted. See Railway Co. v. McCarthy, 96 U. S. 258, 267-268 (“Where a party gives a reason for his conduct and decision touching ... a controversy, he cannot, after litigation has begun, change his ground, and put his conduct upon ... a different consideration. He is not permitted thus to mend his hold. He is estopped from doing it by a settled principle of law” [emphasis supplied]); Luckenbach S.S. Co. Inc. v. W. R. Grace & Co. Inc. 267 Fed. 676, 679 (4th Cir.); Chevrolet *66 Motor Co. v. Gladding, 42 F. 2d 440 (4th Cir.), cert. den. 282 U. S. 872. See also Rode & Brand v. Kamm Games, 181 F. 2d 584, 587 (2d Cir.); Cummings v. Connecticut Gen. Life Ins. Co. 102 Vt. 351, 359-362. In each of these cases, there is reference to estoppel or “waiver” as the legal ground behind the principle.

Our cases somewhat more definitely require reliance or change of position based upon the assertion of the particular reason or defence before treating a person, giving one reason for his action, as estopped later to give a different reason. See Bates v. Cashman, 230 Mass. 167, 168-169. There it was said, “The defendant is not prevented from setting up this defence. Although he wrote respecting other reasons for declining to perform the contract, he expressly reserved different grounds for his refusal. 4 While of course one cannot fail in good faith in presenting his reasons as to his conduct touching a controversy, he is not prevented from relying upon one good defence among others urged simply because he has not always put it forward, when it does not appear that he has acted dishonestly or that the other party has been misled to his harm, or that he is estopped on any other ground.” See Brown v. Henry, 172 Mass. 559, 567; St.John Bros. Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manganella v. Jasmine Co.
23 Mass. L. Rptr. 277 (Massachusetts Superior Court, 2007)
Bavosi v. Harrington
1995 Mass. App. Div. 57 (Mass. Dist. Ct., App. Div., 1995)
Lancaster v. General Accident Insurance Co. of America
587 N.E.2d 246 (Massachusetts Appeals Court, 1992)
Royal-Globe Insurance v. Craven
585 N.E.2d 315 (Massachusetts Supreme Judicial Court, 1992)
Northern Heel Corp. v. Compo Industries, Inc.
851 F.2d 456 (First Circuit, 1988)
Penta v. Concord Auto Auction, Inc.
511 N.E.2d 642 (Massachusetts Appeals Court, 1987)
Accent Builders Co. v. Southwest Concrete Systems, Inc.
679 S.W.2d 106 (Court of Appeals of Texas, 1984)
Harness Tracks Security, Inc. v. Bay State Raceway, Inc.
373 N.E.2d 353 (Massachusetts Supreme Judicial Court, 1978)
Priestley v. Sharaf's, Inc.
344 N.E.2d 905 (Massachusetts Appeals Court, 1976)
Sun Oil Co. v. Greenblatt
314 N.E.2d 462 (Massachusetts Appeals Court, 1974)
Perini Corp. v. Massachusetts Port Authority
308 N.E.2d 562 (Massachusetts Appeals Court, 1974)
Milona Corp. v. Piece O'Pizza of America Corp.
300 N.E.2d 926 (Massachusetts Appeals Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
234 N.E.2d 888, 354 Mass. 62, 1968 Mass. LEXIS 763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/new-england-structures-inc-v-loranger-mass-1968.