Valentine v. Patrick Warren Construction Co.

56 N.W.2d 860, 263 Wis. 143, 1953 Wisc. LEXIS 336
CourtWisconsin Supreme Court
DecidedFebruary 3, 1953
StatusPublished
Cited by23 cases

This text of 56 N.W.2d 860 (Valentine v. Patrick Warren Construction Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valentine v. Patrick Warren Construction Co., 56 N.W.2d 860, 263 Wis. 143, 1953 Wisc. LEXIS 336 (Wis. 1953).

Opinion

Currie, J.

The crucial issue on this appeal is the right of the defendant Warren to have rescinded its subcontract with Capital which rescission was effected by Warren’s registered-mail letter of July 22, 1947. This is not the ordinary case where the question of right to terminate depends upon whether there has been a material breach by the party against whom cancellation is attempted, but instead involves construction of a particular clause in the written contract itself conferring such right of rescission in the event of certain specified occurrences. •

Article 4 of the contract between the parties conferred the right upon Warren to rescind upon giving three days’ notice:

“If at any time during the prosecution of the work of this contract, the subcontractor [Capital], not being hindered by causes beyond his control, fails to maintain a sufficient working force, or if it shall become evident to the contractor [Warren] that the work is not being prosecuted with proper diligence to complete said work so as not to delay the progress of the building, or if the subcontractor -shows gross carelessness or incompetency, or if the subcontractor fails, refuses, or neglects to comply with the contract . . .”

*156 Abarren in its letter of rescission specified three grounds or reasons for the cancellation of its contract with Capital, the same being, (1) refusal to supply sufficient manpower, (2) refusal to supply sufficient materials and equipment, and (3) refusal to furnish sufficient funds to meet pay roll and prosecuting contract, and stated that in order “not to delay progress of construction, we are forced to invoke clauses in your contract to complete your work with our own forces.”

Before considering separately these three grounds for rescission it is necessary to first point out one very serious error on the part of the referee which becomes apparent from a statement made in his memorandum opinion, in which he states that the contract between the parties provided no time for completion by Capital of the work it undertook under the contract. While in a strict literal sense this may be true, nevertheless, Article 2 of the contract specifically provided that Capital “shall perform all work as directed and at such times and in such manner so as not to delay the completion of the buildings.” We construe the words “as directed” as conferring upon Warren and the architect the right to determine within the bounds of reason the manpower which Capital was required to have on the job in order that the work might progress so as not to delay the building. Furthermore, a deadline of October 1, 1947,*had been set by Warren as to when the painting of the interior of the assembly building had to be completed, as it had definitely committed itself with Ford as to such completion date.

With this in mind we will now examine the evidence bearing on the question of whether Capital did consistently fail and refuse to supply sufficient manpower, thereby breaching Article 2 of the contract. While it is true that the weather conditions during January, February, and the first half of March, 1947, did not allow much construction to be carried on, there was back-priming that was done by the painters. From February 19, 1947, to March 13, 1947, Capital had *157 no painters on the job because of trouble with the painters’ union, and while the testimony is in conflict as to whether such trouble may not have been due to a pay-roll check of Capital’s which “bounced,” we are bound by the referee’s finding that such union trouble was due to causes beyond Capital’s control.

The concrete floor in the first 10 bays had been poured first, and then on April 22, 1947, Warren commenced to pour the remainder of the floor of the assembly building, completing the same, except for one of the 40 bays, by July 19, 1947. Never at any time from April 22, 1947, down to the date of rescission on July 22, 1947, did Capital’s painters keep pace with the floor-pouring operations as repeatedly urged by Warren’s superintendent. Warren’s superintendent repeatedly requested Capital to put on more men so that the ceiling could be painted as the pouring progressed so that the painting would be completed ahead of the electrical, heating, and ventilating subcontractors coming in and doing their work. Mr. Bell, a construction engineer of fifty years’ experience who was the representative of the architect on the job, testified without dispute that it was necessary for him to delay the installation of the electrical fixtures for three months until the ceiling was painted, and then he had to let the electricians go in even though the ceiling was not painted. And he also testified that the installation of the heating and ventilating ducts delayed the painters, but this should not have done so because the painters should have had the ceiling painted ahead of the ducts.

As of the week ending April 23, 1947, Capital had but 12 painters and 1 foreman on the job, and this number continued until the week ending June 11, 1947, although both Warren and the architect were pressing Capital during such period to put more painters on the job; and the week ending June 18, 1947, the number of Capital’s employees on the job was increased to 17, and was still further increased until *158 it got up to 26 on July 9, 1947, and stayed at such number until July 22, 1947, when the notice of rescission was given. The architect’s report to Ford of June 28, 1947, stated that Capital had but 25 painters on the job and that 25 more were needed. The architect’s report of July 5, 1947, stated that Capital was still short of painters, and the architect’s further report of July 12, 1947, made at a time when Capital had attained its maximum force of 26 painters, stated that the contractor had a few more painters “but is still short.”

The referee in his opinion placed great stress upon a statement made by Bell in the architect’s report to Ford of July 19, 1947, to the effect that Capital was “making better progress and expects to have more painters next week.” However, Bell, who, as the architect’s representative on the job was a disinterested witness, testified that the need for 50 painters still existed on July 22, 1947. After July 22d, when Warren itself hired the painters, it increased the number of painting employees to 47 by the week ending July 30, 1947; and from August 6, 1947, to August 19, 1947, had from 55 to 57 painters on the job. It does not appear from the record how many painters Busch & Latta had on the job after August 19, 1947, but the reason Warren engaged them at a contract price of approximately $25,000 over the lowest bid submitted for completing the painting subcontract was because of their large size in an attempt to insure completion of the assembly building by October 1st, so it is reasonable to assume that they did not cut down the number of painters which Warren had on the job when they took over. Even then the painting of the assembly building was not completed until October 8, 1947. (The office building was not completed until the summer of 1948, but such delay was approved by Ford.) This establishes that the architect’s estimate' of 50 painters which Capital should have had on the job was not an excessive estimate. In any event, under the contract it was for Warren to determine the manpower required, and Capi

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hedtcke v. Sentry Insurance
326 N.W.2d 727 (Wisconsin Supreme Court, 1982)
Hartford Elevator, Inc. v. Lauer
289 N.W.2d 280 (Wisconsin Supreme Court, 1980)
Tri-State Home Improvement Co. v. Mansavage
253 N.W.2d 474 (Wisconsin Supreme Court, 1977)
Hawkins v. Teeples and Thatcher, Inc.
515 P.2d 927 (Oregon Supreme Court, 1973)
Menard v. Jiffy Self-Service Dry Cleaning, Inc.
174 N.W.2d 493 (Wisconsin Supreme Court, 1970)
Kreyer v. Driscoll
159 N.W.2d 680 (Wisconsin Supreme Court, 1968)
New England Structures, Inc. v. Loranger
234 N.E.2d 888 (Massachusetts Supreme Judicial Court, 1968)
Bornemann v. City of New Berlin
133 N.W.2d 328 (Wisconsin Supreme Court, 1965)
Miles Homes, Inc. v. Starrett
127 N.W.2d 243 (Wisconsin Supreme Court, 1964)
Hernke v. Northern Insurance Co.
120 N.W.2d 123 (Wisconsin Supreme Court, 1963)
Sonotone Corp. v. Ladd
117 N.W.2d 591 (Wisconsin Supreme Court, 1962)
Millis v. Raye
113 N.W.2d 820 (Wisconsin Supreme Court, 1962)
Jolitz v. Graff
106 N.W.2d 340 (Wisconsin Supreme Court, 1960)
Plante v. Jacobs
103 N.W.2d 296 (Wisconsin Supreme Court, 1960)
Wm. G. Tannhaeuser Co. v. Holiday House, Inc.
83 N.W.2d 880 (Wisconsin Supreme Court, 1957)
Georgiades v. Glickman
75 N.W.2d 573 (Wisconsin Supreme Court, 1956)

Cite This Page — Counsel Stack

Bluebook (online)
56 N.W.2d 860, 263 Wis. 143, 1953 Wisc. LEXIS 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valentine-v-patrick-warren-construction-co-wis-1953.