Plante v. Jacobs

103 N.W.2d 296, 10 Wis. 2d 567, 1960 Wisc. LEXIS 401
CourtWisconsin Supreme Court
DecidedJune 7, 1960
StatusPublished
Cited by22 cases

This text of 103 N.W.2d 296 (Plante v. Jacobs) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plante v. Jacobs, 103 N.W.2d 296, 10 Wis. 2d 567, 1960 Wisc. LEXIS 401 (Wis. 1960).

Opinion

Hallows, J.

The defendants argue that the plaintiff cannot recover any amount because he has failed to substantially perform the contract. The plaintiff conceded he failed to furnish the kitchen cabinets, gutters and downspouts, sidewalk, closet clothes poles, and entrance' seat amounting to $1,601.95. This amount was allowed to the defendants. The defendants claim some 20 other items of incomplete or faulty performance by the plaintiff and no substantial performance because the cost of completing the house in strict compliance with the plans and specifications would amount to 25 or 30 per cent of the contract price. The defendants especially stress the misplacing of the wall between the living room and the kitchen, which narrowed the living room in excess of one foot. The cost of tearing down this wall and rebuilding it would be approximately $4,000. The record is not clear why and when this wall was misplaced, but the wall is completely built and the house decorated and the defendants are living therein. Real-estate experts testified that the smaller width of the living room would not affect the market price of the house.

The defendants rely on Manitowoc Steam Boiler Works v. Manitowoc Glue Co. (1903), 120 Wis. 1, 97 N. W. 515, for the proposition that there can be no recovery on the contract as distinguished from quantum meruit unless there is substantial performance. This is undoubtedly the correct rule at common law. For recovery on quantum meruit, see Valentine v. Patrick Warren Construction Co. (1953), 263 Wis. 143, 56 N. W. (2d) 860. The question here is whether there has been substantial performance. The test of what amounts to substantial performance seems to be whether the performance meets the essential purpose of the contract. In the Manitowoc Case the contract called for a boiler having *571 a capacity of 150 per cent of the existing boiler. The court held there was no substantial performance because the boiler furnished had a capacity of only 82 per cent of the old boiler and only approximately one half of the boiler capacity contemplated by the contract. In Houlahan v. Clark (1901), 110 Wis. 43, 85 N. W. 676, the contract provided that the plaintiff was to drive pilings in the lake and place a boathouse thereon parallel and in line with a neighbor’s dock. This was not done and the contractor so positioned the boathouse that it was practically useless to the owner. Manthey v. Stock (1907), 133 Wis. 107, 113 N. W. 443, involved a contract to paint a house and to do a good job, including the removal of the old paint where necessary. The plaintiff did not remove the old paint, and blistering and roughness of the new paint resulted. The court held that the plaintiff failed to show substantial performance. The defendants also cite Manning v. School Dist. (1905), 124 Wis. 84, 102 N. W. 356. However, this case involved a contract to install a heating and ventilating plant in the school building which would meet certain tests which the heating apparatus failed to do. The heating plant was practically a total failure to accomplish the purposes of the contract. See also Nees v. Weaver (1936), 222 Wis. 492, 269 N. W. 266 (roof on a garage).

Substantial performance as applied to construction of a house does not mean that every detail must be in strict compliance with the specifications and the plans. Something less than perfection is the test of specific performance unless all details are made the essence of the contract. This was not done here. There may be situations in which features or details of construction of special or of great personal importance, if not performed, would prevent a finding of substantial performance of the contract. In this case the plan was a stock floor plan. No detailed construction of the house was shown on the plan. There were no blueprints. *572 The specifications were standard printed forms with some modifications and additions written in by the parties. Many of the problems that arose during the construction had to be solved on the basis of practical experience. No mathematical rule relating to the percentage of the price, of cost of completion, or of completeness can be laid down to determine substantial performance of a building contract. Although the defendants received a house with which they are dissatisfied in many respects, the trial court was not in error in finding the contract was substantially performed.

The next question is, What is the amount of recovery when the plaintiff has substantially, but incompletely, performed? For substantial performance, the plaintiff should recover the contract price less the damages caused the defendant by the incomplete performance. Both parties agree Venzke v. Magdanz (1943), 243 Wis. 155, 9 N. W. (2d) 604, states the correct rule for damages due to faulty construction amounting to such incomplete performance, which is the difference between the value of the house as it stands with faulty and incomplete construction and the value of the house if it had been constructed in strict accordance with the plans and specifications. This is the diminished-value rule. The cost of replacement or repair is not the measure of such damage, but is an element to take into consideration in arriving at value under some circumstances. The cost of replacement or the cost to make whole the omissions may equal or be less than the difference in value in some cases and, likewise, the cost to rectify a defect may greatly exceed the added value to the structure as corrected. The defendants argue that under the Venzke rule their damages are $10,000. The plaintiff on review argues that the defendants’ damages are only $650. Both parties agree the trial court applied the wrong rule to the facts.

The trial court applied the cost-of-repair or replacement rule as to several items, relying on Stern v. Schlafer (1943), *573 244 Wis. 183, 11 N. W. (2d) 640, 12 N. W. (2d) 678, wherein it was stated that when there are a number of small items of defect or omission which can be remedied without the reconstruction of a substantial part of the building or a great sacrifice of work or material already wrought in the building, the reasonable cost of correcting the defect should be allowed. However, in Mohs v. Quarton (1950), 257 Wis. 544, 44 N. W. (2d) 580, the court held when the separation of defects would lead to confusion, the rule of diminished value could apply to all defects.

In this case no such confusion arises in separating the defects. The trial court disallowed certain claimed defects because they were not proven. This finding was not against the great weight and clear preponderance of the evidence and will not be disturbed on appeal. Of the remaining defects claimed by the defendants, the court allowed the cost of replacement or repair except as to the misplacement of the living-room wall. Whether a defect should fall under the cost-of-replacement rule or be considered under the diminished-value rule depends upon the nature and magnitude of the defect. This court has not allowed items of such magnitude under the cost-of-repair rule as the trial court did.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flynn Builders, L.C. v. Matthew P. Lande and Chris Lande
814 N.W.2d 542 (Supreme Court of Iowa, 2012)
Pinckney v. United States
85 Fed. Cl. 392 (Federal Claims, 2009)
WISCONSIN AVIATION FOUR LAKES, INC. v. Berryman
2004 WI App 167 (Court of Appeals of Wisconsin, 2004)
Monus v. Colorado Baseball 1993, Inc.
103 F.3d 145 (Tenth Circuit, 1996)
Jacob v. West Bend Mutual Insurance
553 N.W.2d 800 (Court of Appeals of Wisconsin, 1996)
T.O. Haas Tire Co. v. Futura Coatings, Inc.
507 N.W.2d 297 (Nebraska Court of Appeals, 1993)
Micro-Managers, Inc. v. Gregory
434 N.W.2d 97 (Court of Appeals of Wisconsin, 1988)
National Chain Co. v. Campbell
487 A.2d 132 (Supreme Court of Rhode Island, 1985)
Klug & Smith Co. v. Sommer
265 N.W.2d 269 (Wisconsin Supreme Court, 1978)
Johnson v. Taylor Bldg. Corp.
371 N.E.2d 404 (Indiana Court of Appeals, 1978)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
Johnson v. Taylor Building Corp.
371 N.E.2d 404 (Indiana Court of Appeals, 1977)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)
W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc.
214 N.W.2d 413 (Wisconsin Supreme Court, 1974)
Salem Towne Apartments, Inc. v. McDaniel & Sons Roofing Co.
330 F. Supp. 906 (E.D. North Carolina, 1970)
Kreyer v. Driscoll
159 N.W.2d 680 (Wisconsin Supreme Court, 1968)
Reith v. Wynhoff
137 N.W.2d 33 (Wisconsin Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
103 N.W.2d 296, 10 Wis. 2d 567, 1960 Wisc. LEXIS 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plante-v-jacobs-wis-1960.