McKenzie v. Warmka

260 N.W.2d 752, 81 Wis. 2d 591, 1978 Wisc. LEXIS 1222
CourtWisconsin Supreme Court
DecidedJanuary 3, 1978
Docket75-829
StatusPublished
Cited by15 cases

This text of 260 N.W.2d 752 (McKenzie v. Warmka) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKenzie v. Warmka, 260 N.W.2d 752, 81 Wis. 2d 591, 1978 Wisc. LEXIS 1222 (Wis. 1978).

Opinion

CONNOR T. HANSEN, J.

Warmka entered into a contract with McKenzie whereby Warmka agreed to install a seamless floor covering in a kitchen at St. Joseph’s Memorial Hospital in Hillsboro. The floor covering was to meet certain specifications, and the contract price was to be $3,092.

The flooring subsequently installed by Warmka was rejected by McKenzie because the materials used did not conform to the specifications of the contract and because of alleged, but unspecified, defects of workmanship in the surface of the flooring.

Warmka’s efforts to remedy the defects were unacceptable to McKenzie. McKenzie contracted with a third *594 party to remove the flooring, apparently by grinding it away, and to install new flooring. The cost of removing the unsatisfactory flooring was $744.71, and the cost of the new replacement flooring was $4,100.

McKenzie commenced this action to recover damages in the amount of $1,902.71. This figure represents the difference between the $4,844.71 cost of removing and replacing the flooring, and Warmka’s original contract price of $3,092, minus $150 for work which was allegedly not performed. 1 Warmka counterclaimed for the original contract price of $3,092.

The parties stipulated that the matter be submitted to arbitration. The stipulation provided that all matters at issue in the pending action were to be determined by the arbitrator, Sante DeMarco of Rockford, Illinois. The issues were to be submitted to DeMarco “to the end that a determination of the facts and findings made [sic] and filed with the court herein.” The arbitrator was to “make a determination of the facts and decided [sic] the issues” after a hearing, and to file a report which could be supplemented “by further findings or determinations by the [trial] court, in the event, in the interests of fairness and justice, the court shall determine need for same.” Chapter 298, Stats., was to govern the arbitration, except as otherwise provided in the stipulation. Judgment was to be entered “[u]pon final determination of the matter by the arbitrator and approval or modification of same by the court. . . .”

The arbitrator’s “report” consisted of a letter to the trial court. The arbitrator found that Warmka knew that *595 the architect specified one of three franchised products for the job; that Warmka was not a franchised applicator and “went ahead on his own and used an unspecified product.” He also found that the floor had not been accepted by McKenzie, the architect or the owner, and that all three said the floor was not satisfactorily installed. Although the arbitrator found that Warmka did not use the type of flooring material specified in the contract, it was the arbitrator’s belief that the floor would have been accepted if it had been properly installed.

The arbitrator found that McKenzie was claiming $744.71 for the removal of the flooring installed by Warmka and $1,158 as the difference between the original contract price and the price of the replacement flooring. The arbitrator concluded:

“I do not feel that Mr. McKenzie should have to pay to correct problems created by Mr. Warmka and therefor should be reimbursed the $744.71. I do not believe Mr. McKenzie is entitled to the $1,158.00 as it is a general contractor’s responsibility to know the subs and their capabilities prior to signing a contract with them. . . .”

He also stated:

“The above decision is based on my personal judgment of the case. It is my understanding that Your Honor will review this decision and make whatever corrective stipulations he deems to be proper.”

Upon receiving the arbitrator’s report, the trial court advised the parties that their stipulation for arbitration provided for a hearing before the court would make its findings of fact and conclusions of law. Neither party requested such a hearing within the time specified by the trial court, and the court proceeded to render its decision. In its decision, the court stated:

“A reading of the [arbitrator’s] letter shows the following award was made to plaintiff:
“(1) $744.71 for repairs to the floor surface;
*596 “ (2) $1158 for completion of the floor by another contractor.”

However, the arbitrator had said in his letter, “I do not believe Mr. McKenzie is entitled to the $1,158.00 . . .” The trial court reversed the arbitrator’s award with regard to the $1,158 amount. This action was based on the trial court’s determination that the arbitrator was appointed to find facts, and not to apply the law. The trial court held the arbitrator had overstepped his authority by “inject[ing] his view of the law of contract into the award of $1158.00.” Judgment was entered in favor of McKenzie in the amount of $1,902.71.

Additional facts will be discussed in considering the issues, which are:

1. Was the arbitrator authorized to decide questions of both law and fact, or only to make findings of fact?

2. Should the trial court have vacated the award on the ground that it was not final and complete?

3. Did the trial court err in changing the award with regard to McKenzie’s claim for $1,158?

I.

The trial court, in its decision, stated that the arbitrator:

“. . . was appointed to find facts, as is abundantly clear from a reading of the arbitration stipulation. He was not appointed to apply the law.”

We do not believe this conclusion is supported by the arbitration stipulation. The stipulation provided:

“. . . that in lieu of a trial all matters at issue set forth in the Complaint of the plaintiff herein shall be submitted to arbitration. . . .
“That all further proceedings of this action be stayed until such time as the issues now -pending between the *597 parties shall have been determined by a single arbitrator, . . . ifi
“The arbitrator shall make a determination of the facts and decided [sic] the issues herein within a reasonable time. . . .” (Emphasis added.)

McKenzie argues that the arbitrator was authorized only to make findings of fact, and points out that the stipulation provides:

“The parties mutually agree to submit all issues now the subject of this action to said arbitrator to the end that a determination of the facts and findings made and filed with the Court herein.” [sic] (Emphasis added.)

In isolation, this passage might tend to support the view that the arbitrator was merely to prepare findings of fact. However, the stipulation further provides that the arbitrator was to determine what was variously stated as “all matters at issue set forth in the Complaint. . “. . . the issues now pending between the parties. . “. . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herbal Aspect LLC v. Alexander Gish
Court of Appeals of Wisconsin, 2026
Classic Custom Homes of Waunakee, Inc. v. Alex Young
Court of Appeals of Wisconsin, 2022
Loren Imhoff Homebuilder, Inc. v. Lisa Taylor
2022 WI App 14 (Court of Appeals of Wisconsin, 2022)
Sewart v. Silvercryst Ltd.
2010 WI App 141 (Court of Appeals of Wisconsin, 2010)
In RE MARRIAGE OF FRANKE v. Franke
2004 WI 8 (Wisconsin Supreme Court, 2004)
Lane v. Williams
2000 WI App 263 (Court of Appeals of Wisconsin, 2000)
Briggs v. Farmers Insurance Exchange
2000 WI App 40 (Court of Appeals of Wisconsin, 2000)
Finkenbinder v. State Farm Mutual Auto Insurance
572 N.W.2d 501 (Court of Appeals of Wisconsin, 1997)
Employers Ins. of Wausau v. Certain Underwriters at Lloyd's London
552 N.W.2d 420 (Court of Appeals of Wisconsin, 1996)
State v. P.G. Miron Construction Co.
512 N.W.2d 499 (Wisconsin Supreme Court, 1994)
Manu-Tronics, Inc. v. Effective Management Systems, Inc.
471 N.W.2d 263 (Court of Appeals of Wisconsin, 1991)
Fillnow v. City of Madison
435 N.W.2d 296 (Court of Appeals of Wisconsin, 1988)
Milwaukee Teacher's Education Ass'n v. Milwaukee Board of School Directors
433 N.W.2d 669 (Court of Appeals of Wisconsin, 1988)
Hilltop Construction, Inc. v. Lou Park Apartments
324 N.W.2d 236 (Supreme Court of Minnesota, 1982)
Milwaukee Police Ass'n v. City of Milwaukee
285 N.W.2d 133 (Wisconsin Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
260 N.W.2d 752, 81 Wis. 2d 591, 1978 Wisc. LEXIS 1222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckenzie-v-warmka-wis-1978.