Sewart v. Silvercryst Ltd.

2010 WI App 141, 792 N.W.2d 608, 329 Wis. 2d 773, 2010 Wisc. App. LEXIS 739
CourtCourt of Appeals of Wisconsin
DecidedSeptember 15, 2010
DocketNo. 2009AP2415
StatusPublished

This text of 2010 WI App 141 (Sewart v. Silvercryst Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sewart v. Silvercryst Ltd., 2010 WI App 141, 792 N.W.2d 608, 329 Wis. 2d 773, 2010 Wisc. App. LEXIS 739 (Wis. Ct. App. 2010).

Opinion

REILLY, J.

¶ 1. Michael and Lynn Sewart appeal from an order denying their motion for confirmation of [776]*776an arbitration award. Silvercryst Limited, Inc. cross-appeals, arguing that the arbitration award should be vacated as the arbitrators were biased and acted outside the scope of their authority. As we find that the parties contracted for an ongoing arbitration process that provided for the continuing jurisdiction of the arbitration board, we hold that the Sewarts' motion for confirmation of the monetary award was timely and therefore reverse. Additionally, we reject Silvercryst's argument that the arbitration board was biased.

FACTS

¶ 2. On February 28, 2003, Michael and Lynn Sewart purchased a newly constructed home from the seller Silvercryst Limited, Inc. Shortly after buying the house, the Sewarts began to experience flooding in their basement and alerted Silvercryst. Silvercryst failed to remedy the situation, and the flooding continued into 2005. The Sewarts invoked the arbitration clause found in their home purchase contract.

Arbitration Agreement

¶ 3. The Sewarts and Silvercryst executed a written arbitration agreement on July 5, 2006. The agreement provided that the controversy would be submitted to the Construction Arbitration Board (CAB) of the Metropolitan Builders Association (MBA) for a hearing and decision utilizing the "procedures" of the CAB. The arbitration agreement expressly provided that "any decision requiring the payment of money may be entered as a judgment by a court of competent jurisdiction if payment is not made pursuant to the ruling of the arbitrators."

¶ 4. The CAB Complaint Processing Procedures set forth the steps of the arbitration process. Initially, [777]*777an inspection team (who serve as the arbitrators) meets with the parties and inspects the items listed in the homeowner's complaint. After a hearing is held, the arbitrators' decision is written down and communicated to the parties. If the decision requires the contractor to make repairs, the CAB retains jurisdiction to issue supplemental decisions if either party fails to comply with the award. The CAB states that all decisions or awards are "final," and that any "[d]ecision requiring the payment of money may be entered as a judgment by a court."

November 15, 2006 Award

¶ 5. On November 7, 2006, a hearing was held before the CAB. The hearing was memorialized in a three-page award dated November 15, 2006. The award found that there was an excessive amount of water flowing into the Sewarts' basement and that Silvercryst knew of this problem during the construction of the home, yet failed to disclose it to the Sewarts when they purchased the property. Instead of awarding monetary damages to the Sewarts, the CAB gave Silvercryst the opportunity to repair the basement. The CAB also ordered Silvercryst to complete all of the necessary repair work within ninety days (barring delays), and to provide the Sewarts with a one-year warranty against water infiltration from the date the work was completed. Finally, the award noted that the CAB retained the "right to assign monetary values to any items of work not completed in a timely fashion," and that monetary awards represent the CAB's "final decision on a particular issue."

¶ 6. Weather delays and disagreements over the quality of the repair work ensued, and the dispute between the Sewarts and Silvercryst dragged on for the [778]*778next year-and-a-half. The CAB sent a letter on March 31, 2008, to Silvercryst stating that all the work was to be performed by June 30, 2008, or the MBA would issue a monetary award to the Sewarts. Silvercryst's attorney responded by asking the CAB to reconsider its November 15, 2006 decision, but the CAB refused to revise its initial determination.

July 15, 2008 Ruling

¶ 7. On July 7, 2008, the CAB performed a site inspection at the Sewart residence. In a written report dated July 15, 2008, the CAB ruled that Silvercryst had thirty days to disconnect the downspouts and install bentonite at the Sewarts1 house. Additionally, Silvercryst was ordered to extend its warranty by two years, and if flooding occurred during the warranty period, the Sewarts were to "obtain an estimate of the total costs" of repairs and the CAB would "issue a written decision awarding [the Sewarts] the approved costs for completing the [repair] work."

¶ 8. While Silvercryst performed repair work, it was not to the satisfaction of the Sewarts and on December 28, 2008, the Sewarts' basement flooded again. The Sewarts informed the CAB of the flooding and provided a cost estimate for installing a drainage system. On February 16, 2009, Silvercryst wrote to the CAB/MBA and stated that the December 28, 2008 flooding was due to "severe and unusual weather," that the CAB/MBA did not have jurisdiction over the matter because the Sewarts failed to reduce the original arbitration award to a judgment, and that Silvercryst was no longer a member of the MBA and therefore the CAB/MBA did not have legal authority over Silvercryst.

¶ 9. The CAB responded to the parties on March 10, 2009, and indicated it would review all of the [779]*779information and issue a final written decision following its review. Silvercryst was invited to submit any information it wanted the CAB to review. Silvercryst did not submit any information.

May 13, 2009 Decision

¶ 10. On May 13, 2009, the CAB issued another written decision. The decision rejected Silvercryst's claim that the CAB lost jurisdiction, finding that Silvercryst's departure from the MBA was irrelevant given that both parties signed an arbitration agreement. The arbitrators also found that the flooding in the Sewarts' home on December 28, 2008 was not caused by extraordinary weather. Finally, the CAB awarded $92,030.93 in damages to the Sewarts.

¶ 11. On May 21, 2009, the Sewarts filed a petition in circuit court to confirm the arbitration award pursuant to Wis. Stat. § 788.09 (2007-08).1 Section 788.09 provides that:

At any time within one year after the award is made any party to the arbitration may apply to the court in and for the county within which such award was made for an order confirming the award, and thereupon the court must grant such an order unless the award is vacated, modified or corrected under s. 788.10 or 788.11. Notice in writing of the application shall be served upon the adverse party or the adverse party's attorney 5 days before the hearing thereof.

The circuit court denied the petition for confirmation finding that § 788.09 required the Sewarts to confirm the November 15, 2006 arbitration award within one [780]*780year, and the failure to do so resulted in the CAB losing jurisdiction over the subsequent arbitration proceedings. The Sewarts appealed.

¶ 12. Two issues are presented to us on appeal: (1) did the CAB lose "jurisdiction" when the Sewarts did not confirm the November 15, 2006 arbitration award within a year?; and (2) is Silvercryst estopped from asserting the defense of untimely confirmation? In the event that this court reverses the circuit court, Silvercryst cross-appeals and argues that the award should be vacated as the arbitrators were biased.

STANDARD OF REVIEW

¶ 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pilgrim Investment Corp. v. Reed
457 N.W.2d 544 (Court of Appeals of Wisconsin, 1990)
Garstka v. Russo
154 N.W.2d 286 (Wisconsin Supreme Court, 1967)
City of Madison v. Madison Professional Police Officers Ass'n
425 N.W.2d 8 (Wisconsin Supreme Court, 1988)
Borst v. Allstate Insurance Co.
2006 WI 70 (Wisconsin Supreme Court, 2006)
Joint School District No. 10 v. Jefferson Education Ass'n
253 N.W.2d 536 (Wisconsin Supreme Court, 1977)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
City of Madison v. Frank Lloyd Wright Foundation
122 N.W.2d 409 (Wisconsin Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
2010 WI App 141, 792 N.W.2d 608, 329 Wis. 2d 773, 2010 Wisc. App. LEXIS 739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sewart-v-silvercryst-ltd-wisctapp-2010.