Reith v. Wynhoff

137 N.W.2d 33, 28 Wis. 2d 336, 1965 Wisc. LEXIS 838
CourtWisconsin Supreme Court
DecidedOctober 5, 1965
StatusPublished
Cited by9 cases

This text of 137 N.W.2d 33 (Reith v. Wynhoff) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reith v. Wynhoff, 137 N.W.2d 33, 28 Wis. 2d 336, 1965 Wisc. LEXIS 838 (Wis. 1965).

Opinion

Hallows, J.

There is some confusion in the record whether the stipulation entered into by the parties constituted a reference, a common-law or statutory arbitration, or some other arrangement. The court in its order and in its findings, no doubt prepared by counsel, refers to referees; however, we do not consider this stipulation as calling forth and being governed by a statutory reference under sec. 270.34, Stats. That section provides for a trial by a referee upon the written consent of the parties. Such trials are conducted in the same manner as a trial by the court. Sec. 270.35. No such trial was contemplated or held pursuant to the stipulation.

Nor can the stipulation be treated as a common-law arbitration since at common law the entire proceeding of arbitration and award merely constituted a contract between the parties and the successful party could only enforce the award as he could an ordinary contract. Such an arbitration made during a lawsuit ousted the court of jurisdiction and operated ipso jacto as a discontinuance of the pending action. Pick Industries, Inc., v. Gebhard-Berghammer, Inc. (1952), 262 Wis. 498, 56 N. W. (2d) 97, 57 N. W. (2d) 519; Decker v. Ladish-Stoppenback Co. (1931), 203 Wis. 285, 234 N. W. 355. Here, the parties contemplated the award would be returned to the court in the form of a report. The stipulation provided the court would settle certain matters of difference between the two experts. The stipulation required a judgment to be entered upon the award and the jurisdiction of the court was expressly retained.

We consider the stipulation should be treated as a statutory arbitration under ch. 298, Stats., and that chapter *340 should apply where not inconsistent with the agreement. The stipulation is silent as to its nature and since the statutory-arbitration provisions are not negated and the parties have acted thereunder not inconsistently with the statutory-arbitration procedure, the arbitration ch. 298 applies. Madison v. Frank Lloyd Wright Foundation (1963), 20 Wis. (2d) 361, 122 N. W. (2d) 409.

The defendant contends it makes no difference whether the stipulation is treated as a statutory arbitration or just as a contract because in either event the court had power and erred in not setting aside the report or award. Under sec. 298.10 (1) (d), Stats., a court may vacate an award “Where the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.” The court under a statutory arbitration may also modify or correct an award in the three situations set forth in sec. 298.11 (1). One of the grounds for correcting an award is “Where the arbitrators have awarded upon a matter not submitted to them unless it is a matter not affecting the merits of the decision upon the matters submitted.” Sec. 298.11 (1) (b).

The main thrust of the appellant’s argument is the court-appointed experts failed to understand the instructions, to follow them and to use the correct measure of damages. The stipulation entered into required the court-appointed appraiser to have, with other qualifications, at least fifteen-years’ experience in the appraisal of residential property in the Wauwatosa area and the building contractor to have, with other qualifications, at least fifteen-years’ experience in general construction with emphasis on residential construction, particularly multifamily units. Such men were appointed by the court and were to determine the extent of the plaintiffs’ damages, if any, caused by the defendant. The *341 stipulation was somewhat unusual for an arbitration contract. It required the real-estate appraiser to examine the building and to determine whether, because of any failure on the part of the defendant to perform the contract, the plaintiffs received a building of diminished value. In determining the diminished value he was to use the standard of “the difference between the value of the building as it now stands with faulty and incomplete construction and the value of the building as it would stand if it had been constructed in strict compliance with the contract.” But, in making this determination the real-estate appraiser was not to include any defects which could be “remedied by reasonable expense without great sacrifice of work or material already wrought into the building and which could be effected without tearing down or destroying a great deal of work or creating substantial destruction and economic waste.” The defects which could be so repaired were to be compensated for by the contractor’s determining a reasonable sum for the cost of repair. This standard of diminished value and cost of repair is taken almost verbatim from Plante v. Jacobs (1960), 10 Wis. (2d) 567, 103 N. W. (2d) 296.

The contractor was required to examine the building to determine whether there were defects attributable to the defendant, which could be repaired at a reasonable expense and without economic waste, and the cost of repairing such defects. The contractor was to inform the appraiser of those defects which he believed would not be subject to the cost-of-repair rule and thus fall under the diminished-value rule. In the event a conflict arose as to whether an item was properly a cost-of-repair or a diminished-value item, the conflict was to be resolved by the court. In this respect the parties departed from Plante v. Jacobs, wherein it was pointed out the normal rule for damages due to faulty construction amounting to incomplete but substantial perform- *342 anee was the diminished-value rule and that the cost-of-repair applied to small items of defect or omission which could be remedied without the reconstruction of a substantial part of the building or a great sacrifice of work or material already wrought in the building. However, where the separation of defects would lead to confusion, the rule of diminished value would apply to all defects. No dispute arose between the two experts concerning which items came under the cost-of-repair rule and which under the diminished-value rule. Thus the report was not to be a joint award of two experts of the entire subject matter but rather a determination by each expert of a part thereof.

The report consisted of two parts, the part prepared by the building contractor which set forth the cost of repair of all the defects whether they were economically feasible to repair or not. The real-estate appraiser then took this report and classified certain defects as those to which the rule of diminished value should apply. These defects consisted primarily of exterior defects, such as cracks in the brick wall, sills, and outside basement wall. The cost of repairing these items was $1,151.07. By adding an inconvenience factor of $499, the appraiser assigned damages under the diminished-value rule of $1,650. The items to which the cost-of-repair rule applied as determined by the contractor amounted to $1,857.95. All of these defects excepting the driveway were in the interior of the building. The appraiser added to this figure an inconvenience factor of $642.05, resulting in a cost of repair of $2,500.

The real-estate appraiser had no authority to include an inconvenience factor of $642.05 in the cost of repair of those items falling within the cost-of-repair rule.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Teaching Assistants Ass'n v. University of Wisconsin-Madison
292 N.W.2d 657 (Court of Appeals of Wisconsin, 1980)
St. Ex Rel. Teach. Assts. v. Wis.-Madison Univ.
292 N.W.2d 657 (Court of Appeals of Wisconsin, 1980)
Stradinger v. City of Whitewater
277 N.W.2d 827 (Wisconsin Supreme Court, 1979)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
Joint School District No. 10 v. Jefferson Education Ass'n
253 N.W.2d 536 (Wisconsin Supreme Court, 1977)
Wisconsin Employment Relations Commission v. Teamsters Local No. 563
250 N.W.2d 696 (Wisconsin Supreme Court, 1977)
Scherrer Construction Co. v. Burlington Memorial Hospital
221 N.W.2d 855 (Wisconsin Supreme Court, 1974)
Strudell Asphalt, Inc. v. Bernstein
138 N.W.2d 209 (Wisconsin Supreme Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
137 N.W.2d 33, 28 Wis. 2d 336, 1965 Wisc. LEXIS 838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reith-v-wynhoff-wis-1965.