Classic Custom Homes of Waunakee, Inc. v. Alex Young

CourtCourt of Appeals of Wisconsin
DecidedApril 14, 2022
Docket2021AP001240
StatusUnpublished

This text of Classic Custom Homes of Waunakee, Inc. v. Alex Young (Classic Custom Homes of Waunakee, Inc. v. Alex Young) is published on Counsel Stack Legal Research, covering Court of Appeals of Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Classic Custom Homes of Waunakee, Inc. v. Alex Young, (Wis. Ct. App. 2022).

Opinion

COURT OF APPEALS DECISION NOTICE DATED AND FILED This opinion is subject to further editing. If published, the official version will appear in the bound volume of the Official Reports. April 14, 2022 A party may file with the Supreme Court a Sheila T. Reiff petition to review an adverse decision by the Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10 and RULE 809.62.

Appeal No. 2021AP1240 Cir. Ct. No. 2019CV1949

STATE OF WISCONSIN IN COURT OF APPEALS DISTRICT IV

CLASSIC CUSTOM HOMES OF WAUNAKEE, INC.,

PLAINTIFF-APPELLANT,

V.

ALEX YOUNG AND STACY YOUNG,

DEFENDANTS-RESPONDENTS.

APPEAL from an order of the circuit court for Dane County: FRANK D. REMINGTON, Judge. Affirmed.

Before Fitzpatrick, Graham, and Nashold, JJ.

Per curiam opinions may not be cited in any court of this state as precedent

or authority, except for the limited purposes specified in WIS. STAT. RULE 809.23(3). No. 2021AP1240

¶1 PER CURIAM. Classic Custom Homes of Waunakee, Inc. (CCH) appeals a circuit court order confirming an arbitration award that resolved CCH’s contractual dispute with Alex and Stacy Young. CCH contends that the arbitration award should not be confirmed, and should instead be modified or vacated, because the arbitrator “exceeded his powers,” as that phrase is used in WIS. STAT. § 788.10(1)(d) (2019-20),1 by not imposing the remedies set forth in that contract. We conclude that CCH has not demonstrated by clear and convincing evidence that the arbitrator exceeded his powers, and accordingly, we affirm. Additionally, for reasons set forth below, we deny the Youngs’ motion for an award of costs and attorney fees for a frivolous appeal.

BACKGROUND2

¶2 In December 2018, Alex and Stacy Young entered into a building construction contract with CCH for the construction of a single-family home. The written contract provided that, among other things, the home would be shown in the 2019 Parade of Homes—an important marketing event for CCH—and the Youngs received a discount from CCH in connection with their participation. The contract also provided that any contract dispute would be resolved by arbitration.

1 All references to the Wisconsin Statutes are to the 2019-20 version unless otherwise noted. 2 We do not address a number of assertions set forth in the statement of facts section of CCH’s opening brief, which is replete with arguments about how the arbitrator should have viewed the evidence presented at the arbitration hearing. Such presentation of facts is inconsistent with our scope of review of an arbitration decision, discussed below. See Scherrer Const. Co., Inc. v. Burlington Mem’l Hosp., 64 Wis. 2d 720, 726, 221 N.W.2d 855 (1974) (stating that, when reviewing an arbitration award, “‘[n]o useful purpose will be served by a detailed discussion of the evidence’” (quoted source omitted)). It is also inconsistent with our appellate rules, which provide that the statement of facts section of an appellate brief should be free of argument. Arents v. ANR Pipeline Co., 2005 WI App 61, ¶5 n.2, 281 Wis. 2d 173, 696 N.W.2d 194.

2 No. 2021AP1240

¶3 The Youngs made a down payment, CCH commenced construction, and the Youngs made several progress payments and paid change orders as they came due. However, the Youngs eventually stopped paying in April 2019 after their relationship with CCH deteriorated over disputes about the quality of the construction, billing issues, and time pressures. CCH nevertheless finished construction so that it could participate in the Parade of Homes, and the Youngs moved into the home in August 2019.

¶4 CCH filed a lawsuit in the circuit court to foreclose on its construction lien. The Youngs answered the complaint and alleged as an affirmative defense that CCH had breached the contract in various respects.

¶5 CCH also commenced an arbitration to resolve its breach of contract claim, and the Youngs again alleged breaches by CCH. The parties entered into an “arbitration rules” agreement in which they selected their arbitrator and agreed to certain ground rules for the arbitration. Pursuant to these rules, the parties would be entitled to pretrial discovery, and the arbitration hearing would consist of written position statements, the presentation of exhibits and witness testimony, and closing briefs.

¶6 Following a three-day arbitration hearing, the arbitrator issued a written decision determining that both sides had breached the contract.

¶7 The arbitrator determined that the Youngs breached the contract by not making timely payments on the last two progress payments and a final change

3 No. 2021AP1240

order,3 by not giving CCH the opportunity to cure some of the problems that arose during the construction, and by failing to timely make decisions to keep the construction on schedule, which was important for participation in the Parade of Homes. The arbitrator determined that the total contract price was $1,168,983, and that the Youngs had paid $1,068,067, resulting in an unpaid principal balance of $100,916.

¶8 However, the arbitrator also determined that, for its part, CCH had breached the contract in a number of ways. Although the arbitrator determined that some of the billing and quality issues that the Youngs had complained about were relatively minor, he determined that other quality issues were more serious, including the following. First, CCH failed to properly repair trusses that had been damaged during construction, and one truss was entirely missing, resulting in “a clear and distinct danger” that the roof would develop load issues and soft spots, requiring considerable repair work in the future. Second, the interior dimensions of a prominent feature of the house were smaller than called for in the design specifications, and CCH had refused to halt construction to resolve the discrepancy when it was discovered. Third, CCH installed outside stonework that its own expert deemed to be “unacceptable,” at least in part, and that would lead to future drainage and leaking issues. Fourth, a footing was missing from a load bearing wall. Finally, the bathroom shower ceiling CCH installed was visibly sloping. The arbitrator found that “[a] million dollar house should not have this degree of issues,” and further, that many items would need to be repaired or

3 Despite this conclusion, the arbitrator also determined that CCH had made some billing errors that, although insufficient by themselves to create a ground for the Youngs to breach or terminate the contract, arguably justified their decision to withhold payment until the billing errors could be sorted out and explained, as they were during the arbitration hearing.

4 No. 2021AP1240

replaced and would have to be disclosed in any future sale of the home. The arbitrator found that the “cost to remedy the problems may be substantial.”

¶9 The arbitrator resolved the matter by ordering the Youngs to pay $35,000 to CCH. The arbitrator appears to have arrived at that amount based on the unpaid amounts due to CCH, minus a setoff to compensate the Youngs for the devaluation of their home and their costs to remedy the defects caused by CCH’s breaches.4 The arbitrator then considered CCH’s argument that it was entitled to interest, costs, and attorney fees under the contract, but he declined to award interest, costs, or fees. He found that “[n]either party is the prevailing party,” and that, “[u]nder the circumstances, it would not be fair to award interest or attorney fees and costs to either party.” At bottom, the arbitrator explained, “CCH is not getting all the money it claims and the Youngs are not getting the house they contracted for.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howell v. Denomie
2005 WI 81 (Wisconsin Supreme Court, 2005)
Juneau County v. Courthouse Employees
585 N.W.2d 587 (Wisconsin Supreme Court, 1998)
Arents v. ANR Pipeline Co.
2005 WI App 61 (Court of Appeals of Wisconsin, 2005)
Scherrer Construction Co. v. Burlington Memorial Hospital
221 N.W.2d 855 (Wisconsin Supreme Court, 1974)
A.O. Smith Corp. v. Allstate Insurance
588 N.W.2d 285 (Court of Appeals of Wisconsin, 1998)
Entzminger v. Ford Motor Co.
177 N.W.2d 899 (Wisconsin Supreme Court, 1970)
Sommer v. Carr
299 N.W.2d 856 (Wisconsin Supreme Court, 1981)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
Lukowski v. Dankert
515 N.W.2d 883 (Wisconsin Supreme Court, 1994)
In THE MATTER OF ARBITRATION OF NICOLET HS DIST. v. Nicolet Ed. Ass'n
348 N.W.2d 175 (Wisconsin Supreme Court, 1984)
State Ex Rel. Robinson v. Town of Bristol
2003 WI App 97 (Court of Appeals of Wisconsin, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Classic Custom Homes of Waunakee, Inc. v. Alex Young, Counsel Stack Legal Research, https://law.counselstack.com/opinion/classic-custom-homes-of-waunakee-inc-v-alex-young-wisctapp-2022.