Hilltop Construction, Inc. v. Lou Park Apartments

324 N.W.2d 236, 1982 Minn. LEXIS 1762
CourtSupreme Court of Minnesota
DecidedSeptember 10, 1982
Docket81-1142
StatusPublished
Cited by34 cases

This text of 324 N.W.2d 236 (Hilltop Construction, Inc. v. Lou Park Apartments) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hilltop Construction, Inc. v. Lou Park Apartments, 324 N.W.2d 236, 1982 Minn. LEXIS 1762 (Mich. 1982).

Opinion

KELLEY, Justice.

Appellants appeal from an order of the Hennepin County District Court confirming an arbitration award in favor of the respondent general contractor arising out of a dispute in connection with the construction of a low-income apartment complex owned by appellants in St. Louis Park. The trial court held that the arbitrators did not exceed their authority in making the award; that failure of the arbitrators to specifically itemize the award with respect to claims of the respondent did not require the court to submit the award to the arbitrators for clarification; and that respondent was not entitled to attorneys fees. We affirm the court’s ruling that the arbitrators did not exceed their authority and that an order for clarification was not mandated by the statute or the circumstances of this case, but we reverse the trial court’s denial of attorneys fees to respondent, Hilltop Construction, Inc.

Kenneth Peterson, the president of Hilltop Construction, Inc. (Hilltop), and Daniel *238 Otten, the president of Otten Realty, Inc., became interested in building a low-income apartment project on property owned by Otten Realty, Inc. Eventually, the land on which the project was to be erected was conveyed to the Lou Park Apartment Limited Partnership (Lou Park). Architects were hired, city council approval obtained and mortgage financing ’ was approved. Hilltop submitted the low bid for construction of the project, after which the construction contract was signed on September 2, 1977. Simultaneous therewith, a supplemental contract providing for payment of the contractor’s fee was signed. On September 26, 1977, the president of Hilltop was called to the Minnesota Housing and Finance Agency (MHFA), which had arranged the mortgage, to re-execute the contract because MHFA wanted the mortgage to have priority over the construction contract. This latter contract differed in some respects from the September 2, 1977 contract but was generally the same. 1

Shortly after construction started, some problems developed. Some items in the original plans had to be changed — such as fire wall changes ordered by the fire department, a fence around the pool ordered by the building inspector, and other changes —and, in addition, the project was delayed because of labor strikes and bad weather. The question of responsibility for payment for changes made during construction was never resolved by the parties. Hilltop was never paid its “final draw” or its contractor’s fee, and Lou Park paid for none of the changes made during construction.

Hilltop filed a mechanics lien on the property on which it claimed it was owed $253,-871 by Lou Park, and later began an action to foreclose the lien in Hennepin County District Court. Several subcontractors were included as defendants in the foreclosure action. The subcontractors counterclaimed for amounts they alleged were due them. However, Lou Park, instead of interposing an answer, moved to dismiss the action on the grounds that Hilltop had waived its mechanics lien rights in the contract and that the contract required arbitration of the dispute. In response to that motion, the district court, on February 14, 1980, ordered Hilltop’s complaint to be dismissed and further ordered that the dispute be submitted to arbitrators within 30 days. Hilltop appealed that order to this court.

Following further proceedings in this court and in the trial court, hereinafter set forth in Part 3 hereof, the dispute between Hilltop and Lou Park was heard before three arbitrators who issued an award on May 20, 1981. The award indicated that Lou Park was to pay to Hilltop $270,670.83. The award, however, denied Hilltop’s attorneys fees, costs and disbursements “without prejudice to its right to pursue its claim in the pending action in Hennepin County District Court.” Lou Park then applied to the American Arbitration Association for a modification of the award as provided in Minn.Stat. § 572.20 (1980), but the request was denied. Hilltop then requested the Hennepin County District Court to confirm the award under Minn.Stat. § 572.18 (1980). On July 29, 1981, the district court confirmed the award but determined that Hilltop could make no claim against Lou Park for attorneys fees. Lou Park appeals from the order of the court confirming the award. Hilltop has filed a notice of review of that part of the court’s order denying it its attorneys fees and costs.

1. Appellants initially contend that the arbitrators exceeded their powers in making the award in this case. 2 Lou Park argues that where there is a dispute concerning whether a contract was executed by mistake, the issue cannot be decided by the *239 arbitrators absent an agreement in the arbitration agreement that such matters were subject to arbitration. See Atcas v. Credit Clearing Corp. of America, 292 Minn. 334, 197 N.W.2d 448 (1972). It argues that since the arbitration award refers to the September 2 contract, the arbitrators must have decided the September 26 contract was executed by mistake. In rejecting this contention, the trial court noted that reference to the September 2 contract was in a preprint-ed preamble referring to the arbitration agreement. 3 Moreover, the demand for arbitration executed by Lou Park also contained a preprinted preamble referring to the September 2 date, as did its claim for relief. 4

The burden rests on Lou Park to demonstrate that the arbitrators exceeded their powers. This it has failed to do. Absent a clear showing that the arbitrators were unfaithful to their obligations, the courts assume that the arbitrators did not exceed their authority. Seppala & Aho-Spear Associates v. Westbrook Gardens, 388 A.2d 88, 90 (Me.1978); Simpson v. Simpson, 194 Neb. 453, 458, 232 N.W.2d 132, 137 (1975). Arbitrators must clearly exceed their powers before an award will be overturned. Children’s Hospital, Inc. v. Minnesota Nurses Association, 265 N.W.2d 649, 652 (Minn.1978); State v. Berthiaume, 259 N.W.2d 904, 910 (Minn.1977). A mere ambiguity in the opinion accompanying an award which permits an inference that the arbitrators may have exceeded their authority is no reason for refusing to enforce the award. United Steelworkers of America v. Enterprise Wheel & Car Corp., 363 U.S. 593, 598, 80 S.Ct. 1358, 1361, 4 L.Ed.2d 1424 (1960). Appellant Lou Park has made no showing that the arbitrators exceeded their authority. It is clear that the reference in the preamble to the arbitrators’ award to the contract date of September 2, 1977 is simply in accord with appellants’ own demand for arbitration. There is no showing that the arbitrators considered the September 26 contract was executed by mistake.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Richfield v. Law Enforcement Labor Servs., Inc.
923 N.W.2d 36 (Supreme Court of Minnesota, 2019)
Mark Herll v. Auto-Owners Insurance Company
879 F.3d 293 (Eighth Circuit, 2018)
Bjorklund Companies, LLC v. Auto-Owners Insurance
Court of Appeals of Minnesota, 2015
Fernow v. Gould
835 N.W.2d 8 (Supreme Court of Minnesota, 2013)
QBE Insurance Corp. v. Twin Homes of French Ridge Homeowners Ass'n
778 N.W.2d 393 (Court of Appeals of Minnesota, 2010)
Health Plan of Nevada, Inc. v. Rainbow Medical, LLC
100 P.3d 172 (Nevada Supreme Court, 2004)
Long-Russell v. Hampe
2002 WY 16 (Wyoming Supreme Court, 2002)
Weaver v. State Farm Insurance Companies
609 N.W.2d 878 (Supreme Court of Minnesota, 2000)
Casias v. Dairyland Insurance
1999 NMCA 046 (New Mexico Court of Appeals, 1999)
EEC Property Co. v. Kaplan
578 N.W.2d 381 (Court of Appeals of Minnesota, 1998)
Menahga Education Ass'n v. Menahga Independent School District No. 821
568 N.W.2d 863 (Court of Appeals of Minnesota, 1997)
Lickteig v. Alderson, Ondov, Leonard & Sween, P.A.
556 N.W.2d 557 (Supreme Court of Minnesota, 1996)
Cruz v. Northwestern Chrysler Plymouth Sales, Inc.
674 N.E.2d 871 (Appellate Court of Illinois, 1996)
County of Hennepin v. Law Enforcement Labor Services, Inc., Local 19
527 N.W.2d 821 (Supreme Court of Minnesota, 1995)
Neal v. State Farm Insurance Co.
509 N.W.2d 173 (Court of Appeals of Minnesota, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
324 N.W.2d 236, 1982 Minn. LEXIS 1762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hilltop-construction-inc-v-lou-park-apartments-minn-1982.