W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc.

214 N.W.2d 413, 62 Wis. 2d 220, 1974 Wisc. LEXIS 1536
CourtWisconsin Supreme Court
DecidedFebruary 5, 1974
Docket163
StatusPublished
Cited by14 cases

This text of 214 N.W.2d 413 (W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc., 214 N.W.2d 413, 62 Wis. 2d 220, 1974 Wisc. LEXIS 1536 (Wis. 1974).

Opinion

Hallows, C. J.

The issues on appeal involve the proper measure of damages and the correctness of the instructions given to the jury. Slugg operated an agricultural and garden-supply business out of a warehouse in the city of Milwaukee. In September, 1967, it decided to build a new warehouse on the same location and entered into a contract with Paulsen to construct a cinder-block combination warehouse and office building for $119,500 in a workmanlike manner, according to plans, accepted trade-practices, and code restrictions. Slugg paid Paulsen $102,461, which when various extra costs *223 were figured in, left a balance due under the contract of $18,417.46. Construction commenced in November, 1967, and by September, 1968, Slugg substantially occupied the warehouse and by March, 1969, it had taken over the building.

However, Slugg claimed defects existed in the building and so notified Paulsen in a letter, dated May 28, 1969, wherein some 20 defects were listed caused by poor workmanship or disregard of the plans. Three important defects consisted in the failure to install a fifth truss in the roof, failure to construct a five-inch concrete floor over a layer of woven-wire mesh over six inches of gravel as called for by the contract, and failure to build the roof to specifications. After negotiations between Slugg and Paulsen, Computerized Structural Design (CSD) was engaged to make a report of the defects in the building and to draw plans for their correction. Paulsen agreed Slugg should make these corrections at Paulsen’s expense and Dahlman Construction Company was a low bidder at $15,500. This bid did not include remedying the missing fifth roof truss or conforming the roof and the floors to contract specifications. During the course of the repair work, the warehouse was completely destroyed by fire. The warehouse had been insured for the contract price of $119,500. At the time of the fire, Dahlman had performed services amounting to $9,125.69 and the bill of CSD for engineering services for the corrective work was $2,527.28.

This case presents the typical situation where a building contract is substantially performed but the building contains defects which constitute a breach of the contract. In such cases many defects can be repaired at no economic waste and while it might cost slightly more to repair the defects than it would have cost to construct the building properly in the first place, the cost of the repair normally is a proper measure of damages. Here, *224 it is stipulated that certain defects could be repaired at the cost of $15,500 plus the engineering fees, and it was agreed between the parties that this should be done; however, there were three important defects concerning which the evidence of the cost of repair in relation to the increased value was in dispute. There was evidence by Slugg to the effect that the missing truss and the defective roof and floor would cost more to remedy so as to achieve strict compliance with the contract than the economic value of the building would increase as a result thereof. Paulsen introduced evidence at the trial that two of these defects, the roof and the floor, could economically be remedied. Slugg’s expert witness testified that the value of the building as constructed was $45,000 less than if the building had conformed to the plans and specifications and if the repairs of the items, which the parties agreed should be repaired at a cost of $15,500, were made the building would be worth $40,000 less than the contract price. This witness did not allocate any portion of the $40,000 diminished value to the three separate major defects.

On this state of evidence, Slugg asked for a special verdict including an instruction on what sum of money represented the reasonable cost of remedying the defects which could be repaired or replaced without economic waste. This was to be answered by the court at $18,027.28, which sum represented the stipulated cost of the repairs plus the engineering fees. Another inquiry asked what sum of money represented the diminished value of the building as built compared to the value the building would have had if built in accordance with the contract. The giving of both of these instructions would have resulted in duplication with the possibility of overlap. No argument is made that the $15,500 cost of repairs based on the testimony of Slugg’s witness would only increase the value of the building by $5,000. *225 This fact may have been in the court’s mind in giving only the instruction of diminished value. The court rejected the instructions and gave only an instruction on diminished value as the measure of damages. Paulsen argues the giving of only an instruction on the diminished value rule was error because (1) Slugg had failed to lay a foundation for the instruction, and (2) allowed recovery for items which had been shown were repairable at a small cost. The basis of Paulsen’s argument is that, when repairs can economically be made, those repairs must fall under the cost of repair rule and cannot be included in the diminished value rule. Under this view, only those repairs or corrections which are economically unfeasible to make can be included in the diminished value rule.

It would have been preferable if the question of damages had been submitted to the jury on a special verdict which applied the cost of repair rule to those items the parties had agreed could be repaired at a reasonable cost and applied the diminished value rule to the three defects which were not so repairable. This view, of course, assumes the jury would disregard the evidence of Paulsen that two of these defects were economically repairable. The pinpoint issue is whether the trial court must give instructions on both rules when they are applicable to the facts or whether the court can apply only the diminished value rule to avoid confusing the jury. Whether or not both rules should be submitted to the jury is a question for the court to decide.

The general rules respecting the measure of damages for defects in the performance of building contracts have been stated many times and are not in dispute. Where there is a breach of the contract, the law attempts to give the parties to the contract exactly what they contracted for or if this is not possible or feasible, then its equivalent in money. Generally, the measure of damages *226 is the cost of correcting the defect or completing the omission and with this money, the aggrieved parly can specifically correct the defects and supply the omissions. This measure of damages is practical and attains the desired result only when the correction or completion does not involve unreasonable destruction of the work done so that the cost of corrections is not materially disproportionate to the value of the corrections. If reconstruction and completion in accordance with the contract involves unreasonable economic waste, then the rule as to those defects at least is the difference between the value the building would have had if properly constructed and the value that the building does have as constructed. 13 Am. Jur. 2d, Building and Construction Contracts, pp. 79, 80, sec. 79; Restatement, Contracts, pp. 672, 573, sec. 346; Anno., Construction Contract — Breach—Damages, 76 A. L. R. 2d 805, 810, 815, secs. 3 and 4; Calamari and Perillo, The Law of Contracts, pp. 362, 364, sec.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Champion Companies of Wisconsin, Inc. v. Stafford Development, LLC
2011 WI App 8 (Court of Appeals of Wisconsin, 2010)
Schrubbe v. Peninsula Veterinary Service, Inc.
552 N.W.2d 634 (Court of Appeals of Wisconsin, 1996)
Jacob v. West Bend Mutual Insurance
553 N.W.2d 800 (Court of Appeals of Wisconsin, 1996)
State v. Lyon
744 P.2d 231 (Oregon Supreme Court, 1987)
Town of Fifield v. State Farm Mutual Automobile Insurance
339 N.W.2d 348 (Court of Appeals of Wisconsin, 1983)
American Standard, Inc. v. Schectman
80 A.D.2d 318 (Appellate Division of the Supreme Court of New York, 1981)
Klug & Smith Co. v. Sommer
265 N.W.2d 269 (Wisconsin Supreme Court, 1978)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
State Ex Rel. Schilling & Klingler v. Baird
222 N.W.2d 666 (Wisconsin Supreme Court, 1974)
Stevens Construction Corp. v. Carolina Corp.
217 N.W.2d 291 (Wisconsin Supreme Court, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
214 N.W.2d 413, 62 Wis. 2d 220, 1974 Wisc. LEXIS 1536, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-g-slugg-seed-fertilizer-inc-v-paulsen-lumber-inc-wis-1974.