Foeller v. Heintz

118 N.W. 543, 137 Wis. 169, 1908 Wisc. LEXIS 291
CourtWisconsin Supreme Court
DecidedNovember 27, 1908
StatusPublished
Cited by28 cases

This text of 118 N.W. 543 (Foeller v. Heintz) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foeller v. Heintz, 118 N.W. 543, 137 Wis. 169, 1908 Wisc. LEXIS 291 (Wis. 1908).

Opinion

Makshall, :T.

The finding that respondent exceeded his authority by approving of a material departure from the •plans for the building, resulting in appellant failing to get what he bargained for, cannot be disturbed. It is conceded that the structure called for, as to the front thereof, was materially varied, but insisted that there was an inconsistency between the plan therefor and the single detail •drawing, which was adaptable only to the three other sides, all four of which, from a professional standpoint, in view of the form of the building, should be in harmony, in order to be architecturally and structurally correct, fairly indicating [173]*173a mistake in the primary drawing, rather than an omission to make an appropriate subsidiary drawing, which was in the field of respondent’s authority to correct under the provision of the contract that all disputes respecting the true construction or meaning of the drawings should be decided by him and that his decision should be final. That contemplated construction, as the words clearly indicate, not material changes in principal, to fit secondary drawings. There was no question but that the former plainly called for that which respondent assumed authority to change against the protest of the proprietor, upon the ground that in the draught he had made a mistake. That was going outside the field of arbitration laid down in the submission and so not binding on appellant. An • arbitrator, barring inexcusable mistakes and bad faith, is supreme within his jurisdiction, but the moment he passes beyond the boundaries thereof he becomes a usurper and his acts are void, as are all acts of usurpation. Bartlett v. L. Bartlett & Son Co. 116 Wis. 450,. 93 N. W. 473; Consolidated W. P. Co. v. Nash, 109 Wis. 490, 85 U. W. 485; Burnham v. Milwaukee, 100 Wis. 55, 75 N. W. 1014. The result of all the authorities is that the award of an arbitrator so far as not within the lines of the submission is not binding upon any party thereto. 2 Am. & Eng. Ency. of Law (2d ed.) 669, 670. Within that rule we cannot see any justification for a change of the building plan under delegated authority to construe. The principal drawing, as the learned trial court rightly held, formed the basis of the contract. The details were matters of execution. In contemplation of the agreement such principal drawing, as approved by the proprietor, formed the test of what was required for performance.

The learned trial court decided that respondent, without intentional wrong, caused the departure from the plan, but in a particular easily remediable by the expenditure of $400, a small amount as compared with the cost of the structure, [174]*174and as appears -without destruction of any material part thereof erected according to contract, and yet decided that respondent was not entitled to credit for the contract price ■of supervision, though the rule in respect to the matter were the same as in case of the building contractor. We see no good reason why the equity of the law extended to the latter should not include the former. We approve of the conclusion of the trial court in that respect. So the right of appellant to recover depended not upon entire performance as in ordinary contract matters. Substantial performance was sufficient, under a well known exception to the general rule, having perhaps no very logical basis, nevertheless one as well entrenched in the law as any that could well be named.

Tn the light of what constitutes substantial performance of a building contract, it will be seen from the court’s finding and the undisputed evidence, all the calls therefor are fully satisfied. The rule in that regard as recognized by this court is clearly indicated by the following:

“In building contracts, where the contractor constructs something on the land of another which by oversight, but in good-faith effort to perform, fails to entirely satisfy the contract, but is so substantially in compliance therewith that the structure fully accomplishes the purpose of that contracted for,” the test of substantial performance, entitling the builder to recover upon the contract, is satisfied. Manitowoc S. B. Works v. Manitowoc G. Co. 120 Wis. 1, 5, 97 N. W. 515, 517.
“Substantial performance means strict performance in all essentials necessary to the full accomplishment of the purposes for which the thing contracted for was designed. Failure as to any of such features, whether in good faith or bad faith, any departure from the contract, not caused by inadvertence or unavoidable omission, any defect so essential ‘as that the object which the parties intended to accomplish to have a specified amount of work performed in a particular manner is not accomplished,’ is inconsistent with substantial performance of the contract,” within the rule permitting a [175]*175recovery by tbe builder notwithstanding tbe incompleteness. Manning v. School Dist. 124 Wis. 84, 108, 102 N. W. 356, 364.

Tbe foregoing is in harmony with the general trend of •authority where departure from the general rule as to the right of one to recover upon the contract and tbe correlative •departure from the ordinary rule of damages as to the other, is recognized as in this jurisdiction, as witness the following:

“Where the contractor in good faith intended to comply with the terms of tbe contract, and has substantially done so, but there are some slight omissions or defects caused by inadvertence or mistake, which are not so essential as to defeat the object of the parties, or, as it has sometimes been expressed, do not go to the root of the subject matter of the ■contract, but are easily susceptible of remedy, so that an •allowance out of the contract price will give the other party full indemnity and give him in effect just what he bargained for, the contractor may recover the contract price, less the ■damages on account of such defects or omissions. . . .” Leeds v. Little, 42 Minn. 414, 419, 44 N. W. 309, 310.
“Where a builder has in good faith intended to comply with the contract, and has substantially complied with it, although there may be slight defects caused by inadvertence or unintentional omissions, he may recover the contract price, less the damage on account of such defects. . . . The defects must not run through the whole, nor be so essential as that the object of the parties, to have a specified amount •of work done in a particular way, is not accomplished.” Woodward v. Fuller, 80 N. Y. 312, 315.

So, as there was no bad faith indicated in this ease and appellant got, in general, a structure for the contract price •satisfactory in all essentials necessary to the thing bargained for, there was substantial performance.

It follows that respondent had a right to recover on his -contract subject to such compensation as appellant was entitled to for breach thereof.

What has been said leads us to a consideration of the [176]*176proper rule of damages in such, a case as this. On that, branch appellant complains serious error was committed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Wall and Paver, LLC v. Pamela E. Gacek and Mark R. Gacek.
73 So. 3d 714 (Court of Civil Appeals of Alabama, 2011)
State v. City of Oak Creek
2000 WI 9 (Wisconsin Supreme Court, 2000)
W. G. Slugg Seed & Fertilizer, Inc. v. Paulsen Lumber, Inc.
214 N.W.2d 413 (Wisconsin Supreme Court, 1974)
Tabet Lumber Company v. Baughman
439 P.2d 706 (New Mexico Supreme Court, 1968)
Shimek v. Vogel
105 N.W.2d 677 (North Dakota Supreme Court, 1960)
Cross v. Robinson
281 S.W.2d 22 (Missouri Court of Appeals, 1955)
Montgomery v. Karavas
114 P.2d 776 (New Mexico Supreme Court, 1941)
Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)
J. G. Jansen, Inc. v. Rilling
232 N.W. 887 (Wisconsin Supreme Court, 1931)
City of Earlington v. Powell
10 S.W.2d 1060 (Court of Appeals of Kentucky (pre-1976), 1928)
Schneider v. Allis-Chalmers Manufacturing Co.
219 N.W. 370 (Wisconsin Supreme Court, 1928)
Cardell v. City of Perry
207 N.W. 775 (Supreme Court of Iowa, 1926)
Atkinson v. Jackson Bros.
270 S.W. 848 (Texas Commission of Appeals, 1925)
F. E. Marsh & Co. v. Light & Power Co.
196 Iowa 926 (Supreme Court of Iowa, 1923)
Morris v. Fox
135 N.E. 663 (Indiana Court of Appeals, 1922)
Jacob & Youngs, Inc. v. Kent
129 N.E. 889 (New York Court of Appeals, 1921)
Harrild v. Spokane School District
192 P. 1 (Washington Supreme Court, 1920)
Bayfield County v. Ogren
177 N.W. 591 (Wisconsin Supreme Court, 1920)
Kingman Colony Irr. Co. v. Payne
152 P. 891 (Oregon Supreme Court, 1915)
First Savings & Trust Co. v. Milwaukee County
148 N.W. 22 (Wisconsin Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
118 N.W. 543, 137 Wis. 169, 1908 Wisc. LEXIS 291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foeller-v-heintz-wis-1908.