Shimek v. Vogel

105 N.W.2d 677, 1960 N.D. LEXIS 91
CourtNorth Dakota Supreme Court
DecidedNovember 1, 1960
Docket7872
StatusPublished
Cited by27 cases

This text of 105 N.W.2d 677 (Shimek v. Vogel) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shimek v. Vogel, 105 N.W.2d 677, 1960 N.D. LEXIS 91 (N.D. 1960).

Opinion

HARRY E. RITTGERS, District Judge.

This is a trial de novo in an action brought to determine the amount due plaintiff under a contract with defendants for the construction of a building, and to foreclose a mechanic’s lien. Plaintiff recovered judgment awarding him $7,001.52, with interest from September 26, 1956, and for costs, and for the foreclosure of the lien. Defendants have appealed from that judgment.

Plaintiff’s complaint alleges that the original contract price was $48,430.60; that plaintiff has been paid thereon the sum of $41,312; leaving a balance due thereon in the sum of $7,118.60. The complaint further alleges that various changes were made during the course of construction at the request or with the consent of defendants, and that pursuant thereto plaintiff has furnished the necessary labor and materials required for such extra work amounting to the further sum of $4,650.98, making a total amount now due plaintiff in the sum of $11,769.58.

Defendants’ answer consists of a general denial and a counterclaim, to which there was a reply. The answer admits that on or about May 7, 1956, defendants made an agreement with plaintiff for the construction of the building in question. The counterclaim was for the sum of $20,000, and as the basis thereof defendants alleged numerous defects and unauthorized changes in the work of construction.

The trial court allowed plaintiff on the “extras”, $1,593.52, and allowed defendants on their counterclaim the sum of $1,710 leaving a difference on those items in favor of defendants in the sum of $116.48. The trial court stated said amounts as follows:

Due on contract-$48,430.00

Less amount paid by defendants - 41,312.00

Balance- 7,118.00

Less difference owing defendants - 116.48

Total amount due plaintiff-$ 7,001.52

In support of their counterclaim defendants on the trial offered evidence tending to show that if the building had been constructed according to the contract its value would be much more than the value of the present building.

Whether such evidence is admissible depends upon the facts. The transcript of the proceedings in the lower court comprises a total of 660 pages. We have carefully read and analyzed the full record. For reasons which will appear from our later discussions, we hold that there was a substantial completion of the building by plaintiff under the terms of the contract and an acceptance thereof by defendants, reserving to defendants the right to oppose plaintiff’s claims for “extras” and to counterclaim for damages on account of defects in the work. The changes made by plaintiff were consented to or waived by defendants who accepted and took possession of the building. Evidence as to the value of the building was therefore not relevant to the issues.

The contract in question is Exhibit 3 and was signed by the parties on May 7, 1956. It was composed by plaintiff after several conferences had been held concerning the building defendants desired. Plaintiff is an experienced builder of commercial buildings in the Bismarck area. Defendant Anton Vogel, has for several years operated a general plumbing and heating business in the same city. He testified that he had the experience of building about a dozen dwelling houses in the Bismarck area. The defendant Ruth Vogel, is Anton Vogel’s wife and partner in the business, and is the bookkeeper and office manager. Defendants *680 own the site on which this building was placed. It was mutually agreed by the parties that no architect should be hired to prepare plans and specifications or to supervise and direct the work of construction, and that plaintiff should prepare all necessary plans. Exhibit C is an estimate prepared by plaintiff of the cost of materials and labor required, and upon which his bid was based. Exhibit 5 was the plan of the proposed building prepared by plaintiff. These exhibits were frequently referred to by the parties in connection with their operations under the contract, Exhibit 3, and are properly treated as parts of the contract.

As we view the evidence we find no proof of intention on the part of the defendants to refuse to accept the building. In fact, while defendants protested at various times concerning various changes in the work, such protests appear to have been merely expressions of some dissatisfaction. Defendants in no instance insisted that any work be torn out or replaced. Some of the changes in the course of construction were made on the direction of the defendants, some were on plaintiff’s initiative, and some were openly agreed to by both parties in advance. Where objections were made by defendants and no further action was taken, defendants must be held to have acquiesced in the changes made by plaintiff. A good instance on this point is presented in the change in the construction of the ceiling. The contract described the material to be used and the method of constructing the ceiling in detail. The defendants undertook the construction of this building in the first instance for the purpose of renting it to Mr. Zahn as a bowling alley. The contract stated that the building should be completed by September IS, 1956, but time of completion was not made of the essence of this agreement.' Both Mr. Vogel and Mr. Zahn were anxious to have the building ready for use as soon as possible. Both were urging an early completion of the work. When plaintiff reached the point of constructing the ceiling he was not able to secure the materials required by the contract. Plaintiff substituted other material without consulting defendants. When the ceiling was partly built defendant Anton Vogel informed plaintiff, “It is not the ceiling I want.” Plaintiff testified the ceiling cost him considerably more money than the cost of the ceiling contracted for would have been, and he asserts the change was made to enable Mr. Zahn to commence business much earlier than would otherwise have been possible. In this instance plaintiff testified that when he informed Mr. Vogel it would be necessary to make the change, Mr. Vogel said, “Go ahead, anything to get the job done.” Vogel in his testimony denies making this statement. The witness Harney, who is in the flooring and acoustics business testified, and this testimony is not disputed, that there was very little difference between the ceiling built and the one specified, and that Mr. Shimek did some extra work on the ceiling at the request of Mr. Zahn. Mrs. Vogel testified that she asked Mr. Shimek, “How come we are getting that kind of a ceiling?” and that Shimek replied, “That is the only way I can get the building done so Zahn can occupy it.” Mrs. Vogel testified that she then told Shimek, “That isn’t the. ceiling I want.” No other protest was made or other action taken at any time regarding the ceiling by either of the defendants. Testimony of other witnesses was that the ceiling as built was as good as that contracted for.

The objections of the defendants and the differences between the parties in regard to the ceiling may fairly be said to be representative of the objections and differences in regard to the other changes and to the attitude and conduct of both parties in regard thereto. We therefore are constrained to hold that the changes in the work of construction made by plaintiff were consented to by the defendants.

As will appear from our later consideration of the claims of defendants under their counterclaim, the defects were remediable or compensable and do not invalidate the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Texaco, Inc. v. Mercury Exploration Company
994 F.2d 463 (Eighth Circuit, 1993)
Swain v. Harvest States Cooperatives
469 N.W.2d 571 (North Dakota Supreme Court, 1991)
Biteler's Tower Service, Inc. v. Guderian
466 N.W.2d 141 (North Dakota Supreme Court, 1991)
All Seasons Water Users Ass'n v. Northern Improvement Co.
417 N.W.2d 831 (North Dakota Supreme Court, 1988)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Myers v. Western Realty & Construction, Inc.
635 P.2d 867 (Court of Appeals of Arizona, 1981)
North County School District R-1 v. Fidelity & Deposit Co. of Maryland
539 S.W.2d 469 (Missouri Court of Appeals, 1976)
Farmers Union Grain Terminal Ass'n v. Nelson
223 N.W.2d 494 (North Dakota Supreme Court, 1974)
Gajewski v. Bratcher
221 N.W.2d 614 (North Dakota Supreme Court, 1974)
Dobler v. Malloy
214 N.W.2d 510 (North Dakota Supreme Court, 1973)
Nordin Construction Company v. City of Nome
489 P.2d 455 (Alaska Supreme Court, 1971)
Stewart Equipment Co. v. Hilling Construction Co.
175 N.W.2d 692 (North Dakota Supreme Court, 1970)
Minette v. Associated Chinchilla Breeders, Inc.
173 N.W.2d 485 (North Dakota Supreme Court, 1970)
Scott v. National Travelers Life Insurance Co.
171 N.W.2d 749 (North Dakota Supreme Court, 1969)
Stuart v. Secrest
170 N.W.2d 878 (North Dakota Supreme Court, 1969)
Denice v. Spotswood I. Quinby, Inc.
237 A.2d 4 (Court of Appeals of Maryland, 1968)
Lillethun v. Tri-County Electric Cooperative, Inc.
152 N.W.2d 147 (North Dakota Supreme Court, 1967)
501 DeMers, Inc. v. Fink
148 N.W.2d 820 (North Dakota Supreme Court, 1967)
Ireland's Lumber Yard v. Progressive Contractors, Inc.
122 N.W.2d 554 (North Dakota Supreme Court, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
105 N.W.2d 677, 1960 N.D. LEXIS 91, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shimek-v-vogel-nd-1960.