Whitfield Construction, Co. v. Commercial Development Corp.

392 F. Supp. 982, 11 V.I. 655, 1975 U.S. Dist. LEXIS 12803
CourtDistrict Court, Virgin Islands
DecidedApril 18, 1975
DocketCiv. No. 357-1970
StatusPublished
Cited by3 cases

This text of 392 F. Supp. 982 (Whitfield Construction, Co. v. Commercial Development Corp.) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitfield Construction, Co. v. Commercial Development Corp., 392 F. Supp. 982, 11 V.I. 655, 1975 U.S. Dist. LEXIS 12803 (vid 1975).

Opinion

*659 CHRISTIAN, Chief Judge

MEMORANDUM

This suit was commenced by plaintiff Whitfield Construction Company, Inc. (Whitfield) on a claim against *660 defendants Commercial Development Corporation (hereinafter variously CDC, Commercial or Owner) and Quality Sales Corporation (Quality), for money due and owing on a construction contract and for damages flowing from the alleged breach of the said contract by the defendants. Commercial denied having breached their agreement and in turn counterclaimed against Whitfield for damages stemming allegedly from work left undone, as well as other work done in an unworkmanlike manner. Commercial’s answer stated a multitude of counterclaims. Some involved parties then strangers to the suit. Accordingly, and on motion of CDC, two new defendants on the counterclaims stated were brought in, Fireman’s Insurance Fund (Fireman’s Fund) and American Agencies, Inc. (AA). The former is the bonding company which guaranteed Whitfield’s performance under the contract. The latter is a subcontractor of plaintiff Whitfield which did some of the work provided for under the prime general contract.

Because of issues raised in a further amendment to Commercial’s answer and counterclaims, the joinder of additional parties was found to be necessary. Entering the suit at this point were the architectural firm of Bellante, Clauss, Miller & Nolan (Bellante) which had served Commercial, as well as one John Garfield, an architect and the local agent of Bellante, and finally, an engineer at the time resident in St. Thomas, Roger McCloskey, who performed some of the engineering services entailed in the agreement between Commercial and Bellante. This multitude of parties, as would be expected, spawned a series of cross-claims. As necessary, the substance of them will be detailed in the narrative which follows.

Plaintiff in this suit sought injunctive and declaratory relief also. These aspects of the case came on for hearing on October 5, 1970, at which time plaintiff’s principal effort was to prevent the defendants from taking possession of *661 the building until or unless they accepted it as fully completed. As a matter of actual fact, however, at the time of the hearing, defendants were already in possession and were utilizing the building. The up-shot of it all was a negotiated standoff pending final determination on the merits of the entire case. In halting the court proceedings in progress at that stage, the parties agreed that the sum of $60,000 found to be due plaintiff from defendant CDC, was to be paid. This was done. An additional sum of $5,000 was also handed over to plaintiff as due and owing, but $27,835.44 was placed in the registry of the court. This sum the clerk deposited in an interest bearing account to await the Court’s final decision.

The issues remaining in the case after the above mentioned settlement came on for trial March 18 through 22, 1974. At the conclusion of the taking of testimony, all parties were given time to file post-trial briefs. The matter thereafter having been taken under advisement by the Court, and the Court having now considered the evidence adduced and the contentions of the respective parties, makes its findings of fact and conclusions of law as are set out below.

By written instrument dated October 28, 1967, Howard Rosov acquired a leasehold interest from the Government of the Virgin Islands in certain real estate located in the Sub Base, St. Thomas. This interest was to run initially for a period of twenty-five years, beginning on January 1, 1968, and was subject to two five-year options to renew, after which time it would revert to the Government. Rosov subsequently assigned this lease to Commercial, of which he was President, which in turn leased it to Quality Sales for the purpose of carrying on a food storage and sale business. Rosov is also an officer of Quality Sales, which is owned by International Pood Sales Service.

*662 On September 1, 1968, a contract was entered into between CDC and Bellante, by which the latter was to provide architectural services in the design and construction of the building to be used by Quality in its proposed business. The form of this contract was the standard AIA document between Owner and Architect, setting the ordinary bounds of the Architect’s responsibility and authority. All transactions in behalf of Bellante were accomplished by and through John Garfield, Bellante’s local representative. (Apparently certain aspects of the plans and specifications were submitted to Garfield, already drawn up, by a Dr. Paul Eaton. Although Eaton’s status in this affair was never adequately clarified at trial, it does appear from the testimony that he was an agent of the Owner).

On. June 7, 1969, Commercial signed a contract with Whitfield whereby Whitfield became the general contractor for the construction of the building. Both Ray Whitfield, President of the construction company, and his brother James, superintendent at the job site, testified at the trial. The documents of this integrated contract include, in addition to the written agreement and the AIA General Conditions, the Owner’s Invitation to bid, the drawings, specifications and plans, and three addenda. Whitfield subcontracted the plumbing work to Tropic Plumbing, the electrical work to Rogers Electric and the fabrication and erection of the structural steel frame to American Agencies, Inc. Commercial directly contracted for the construction of the insulated freezer room with Carib Insulation Company of Miami, the millwork in the administrative office area to Amberg and the interior decorating requirements for the office area to Hans Kriek. The original contract price of $575,000 was modified by subsequent agreement to $525,000, removing certain aspects of the construction work from Whitfield and making it either the Owner’s or an independent contractor’s responsibility. This contract *663 stated, that unless otherwise altered by Change Order, the date for the completion of the building was to be 290 days after the issuance of a building permit, and that time was of the essence. As originally planned, the building should have been completed by May 20,1970. 1 Liquidated damages were provided for every day beyond that time that the Owner was deprived of occupancy and use due to delay attributable to the contractor.

In addition to the necessary triumverate of Owner-Architect-Contractor, and the previously mentioned Eaton, there were several other individuals involved in this construction project whose roles are not only ambiguous but whose presence cast the ordinary duties of the others in some confusion.

One Justus Villa, a civil engineer, was retained by Commercial sometime in 1969 as the “Owner’s representative.” Although this appears to be a position anticipated and recognized by the AIA as one apart from the Architect (See ¶2.2 of AIA Agreement between Owner and Architect), Mr. Villa himself appeared uncommonly unsure as to just what his role was supposed to be.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Wingmark Corp.
50 V.I. 431 (Virgin Islands, 2008)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
District Concrete Co. v. Bernstein Concrete Corp.
418 A.2d 1030 (District of Columbia Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
392 F. Supp. 982, 11 V.I. 655, 1975 U.S. Dist. LEXIS 12803, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitfield-construction-co-v-commercial-development-corp-vid-1975.