McCloskey ex rel. United States Fidelity & Guaranty Co. v. United States

66 Ct. Cl. 105, 1928 U.S. Ct. Cl. LEXIS 363, 1928 WL 2912
CourtUnited States Court of Claims
DecidedJune 18, 1928
DocketNo. C-975
StatusPublished
Cited by26 cases

This text of 66 Ct. Cl. 105 (McCloskey ex rel. United States Fidelity & Guaranty Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCloskey ex rel. United States Fidelity & Guaranty Co. v. United States, 66 Ct. Cl. 105, 1928 U.S. Ct. Cl. LEXIS 363, 1928 WL 2912 (cc 1928).

Opinion

GeeeN, Judge,

delivered the opinion of the court:

It appears without dispute that plaintiff entered into a contract to construct for the defendant a building at West Point, New York. The plaintiff undertook the work, and with the aid of the surety on its bond completed it, but the delays which were incurred in its completion resulted in a greatly enhanced cost of labor and materials over and above what he had anticipated, and he and the bonding company incurred a large loss. Claiming that the defendant was responsible for these delays and the increased cost, this suit [124]*124has been brought by plaintiff in part for the use of the surety on its bond, to recover the damages alleged to have been sustained.

The plaintiff alleges in the petition that the defendant agreed to have the site for the building cleared by July 1, 1919. The evidence leaves no doubt that defendant failed so to do. In fact, the site was not completely cleared until some eight or ten months later. There is likewise no question but that the delay in clearing the site was the principal cause of the delay in the work upon the building.

The case turns largely on the question of whether the evidence shows that the defendant agreed to have the site for the building cleared by July 1, 1919. On this point the evidence is somewhat conflicting and we think it best to call attention to its most salient features.

Herbert 8. Keffer, estimator for McCloskey, visited West Point and examined the site about a week prior to the submission of the proposal. He was accompanied by David Hoskins. They met the Government superintendent, God-ing, the official in charge of the work. Keffer testifies in substance that he asked Goding how long it would tako to get the excavation completed, and told him that it would make quite a difference in the bid, and says that he explained to Goding that the work would be a lot cheaper if started early in the summer than if it was held over another year. The witness also says that Goding said it looked as if this was quite reasonable and it (the clearing of the site) would be done by July 1, 1919.

After this meeting took place the plaintiff submitted its bid, and when the bids were opened there seems to have been some difficulty about their acceptance on account of the estimate being beyond the requirement. The plaintiff, M. H. McCloskey, jr., saw Mr. Goding and, together with him, went to examine the site, but on account of snow on the ground the plaintiff was not able to determine the extent of the excavation. The plaintiff testifies that he asked Goding when they were going to be out of there,” meaning we conclude, when the excavation upon the site was to be finished. McCloskey says that Goding answered, “ You [125]*125can figure on getting on there on July first,” and that he (McCloskey) said, “ There isn’t any question about that, is there, and he [Goding] assured me there was none.” If this testimony is to be accepted, it follows that the contract subsequently executed was made in reliance upon the agreement to clear the site by July first.

Shortly afterwards the contract was executed; McCloskey returned to West Point about the fifth or sixth of May, and had a conversation with Goding and Col. Timberlake, who, it seems, had succeeded Goding as the Government superintendent of the work and who executed the contract on behalf of the defendant; and plaintiff testifies that he again asked Timberlake whether he would be ready by July first “ so that we can start this job without any interruption,” and that Timberlake said, “ positively.”

Four other witnesses testify to conversations after the execution of the contract with Goding and Timberlake, in which the representatives of the Government gave assurances that the site would be cleared by July first. It is not probable that these statements would have been made if the contract with reference to the clearance of the site had not been made as alleged by the plaintiff. This testimony,, therefore, tends to corroborate the testimony of Keffer and McCloskey.

There is other evidence ‘ that tends to corroborate the plaintiff on this point. The construction contract required the contractor to furnish “ a schedule of progress of construction giving dates of completion of various classes of work.” If, as claimed by the defendant, there was no understanding as to when the site should be cleared, it is obvious that no schedule of progress could be furnished, but the evidence shows that such a schedule was requested before the work was begun.

In our opinion the testimony of the witnesses1 for the defendant is not sufficient to overcome this evidence; in fact, Goding makes only a qualified denial of the testimony of Keffer and McCloskey, and what he does say is only after repeated questions by counsel for the defendant. His testimony is not consistent with the testimony given on behalf [126]*126of the plaintiff, but we think the latter is, under all the circumstances, much more worthy of credit.

It is hardly conceivable that an experienced contractor like the plaintiff would enter into a contract of this nature without having a definite understanding as to when he could begin the work. It is quite obvious, as Keffer stated in his testimony, that the work could be done cheaper in the summer than it could be done in the winter. Moreover, there were all Irinds of contingencies that might affect the contractor in his performance of the work if it was indefinitely postponed.. All of these matters are set out in the findings of fact which are supported by the preponderance of the evidence. There is much conflict in the evidence also as to the facts stated in Finding IX, which is in effect that the site could and should have been completely cleared and ready by July 1st, 1919. The evidence on this point is quite voluminous, but the preponderance is clearly in favor of the plaintiff.

Six witnesses gave testimony which, if correct, could only justify the conclusion that the site could, with the exercise of reasonable diligence and modern methods, have been cleared in from thirty to sixty days from the date of the execution of the contract; and the testimony of Timberlake, instead of rebutting this testimony, tends to confirm it when taken in connection with the evidence as to the amount of work done from March 31 to May 1, 1919. The witnesses who testified on behalf of plaintiff were all experienced in blasting work, and several of them had done a large amount of work in cities, where the difficulties to be encountered were at least as great as at the site in question. So far as one inexperienced in such work can acquire knowledge from photographs, the photographs taken of the progress of the work tend to sustain the contentions of the plaintiff. We see no good reason why the site could not have been cleared by July 1, 1919, if experienced parties with sufficient help had taken charge of the work.-

Counsel for defendant call attention to delays on the part of the plaintiff in furnishing some of the structural iron work, artificial stone, and other materials, but it was useless [127]*127for the plaintiff to arrange to have the material on the ground before it could be used; in fact, to do so would simply have further encumbered the work. To state the situation briefly, one delay was the cause of another, and so on all through the work. Subcontractors abandoned their contracts, freight embargoes were encountered, and material became difficult to obtain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jmr Construction Corp. v. United States
117 Fed. Cl. 436 (Federal Claims, 2014)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
System Fuels, Inc. v. United States
78 Fed. Cl. 769 (Federal Claims, 2007)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Harbert/Lummus v. United States
41 Cont. Cas. Fed. 77,020 (Federal Claims, 1996)
Hazeltine Corp. v. United States
10 Cl. Ct. 417 (Court of Claims, 1986)
Prestex, Inc. v. United States
31 Cont. Cas. Fed. 71,508 (Court of Claims, 1983)
Houston Ready-Cut House Co. v. United States
96 F. Supp. 629 (Court of Claims, 1951)
Brand Inv. Co. v. United States
58 F. Supp. 749 (Court of Claims, 1944)
Rice v. United States
95 Ct. Cl. 84 (Court of Claims, 1941)
Hirsch v. United States
94 Ct. Cl. 602 (Court of Claims, 1941)
Grand Trunk Western R. Co. v. HW Nelson Co.
116 F.2d 823 (Sixth Circuit, 1941)
Schmoll v. United States
91 Ct. Cl. 1 (Court of Claims, 1940)
Ouilmette Construction & Engineering Co. v. United States
89 Ct. Cl. 334 (Court of Claims, 1939)
MacDonald Engineering Co. v. United States
88 Ct. Cl. 473 (Court of Claims, 1939)
Edward E. Gillen Co. v. United States
88 Ct. Cl. 347 (Court of Claims, 1939)
Carden v. United States
87 Ct. Cl. 189 (Court of Claims, 1938)
Phoenix Bridge Co. v. United States
85 Ct. Cl. 603 (Court of Claims, 1937)
Donnell-Zane Co. v. United States
75 Ct. Cl. 368 (Court of Claims, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
66 Ct. Cl. 105, 1928 U.S. Ct. Cl. LEXIS 363, 1928 WL 2912, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccloskey-ex-rel-united-states-fidelity-guaranty-co-v-united-states-cc-1928.