Edward E. Gillen Co. v. United States

88 Ct. Cl. 347, 1939 U.S. Ct. Cl. LEXIS 240, 1939 WL 4233
CourtUnited States Court of Claims
DecidedMarch 6, 1939
DocketNo. 43519
StatusPublished
Cited by2 cases

This text of 88 Ct. Cl. 347 (Edward E. Gillen Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward E. Gillen Co. v. United States, 88 Ct. Cl. 347, 1939 U.S. Ct. Cl. LEXIS 240, 1939 WL 4233 (cc 1939).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

The Edward E. Gillen Company is a Wisconsin corporation engaged in contracting for the construction of marine works of improvement, foundations, and other similar heavy structures. On October 27, 1932, the defendant by advertisement solicited bids for the construction of Lock 5 on and adjoining the west bank of the Mississippi Biver near Minneiska, Minnesota.

[363]*363Plaintiff’s bid was accepted and on December 19, 1932, plaintiff and defendant executed the contract involved in this case. The pertinent facts upon which the issues in the case are to be determined are not in dispute. The suit is for the recovery of damages suffered by the plaintiff because of the failure of the defendant to obtain title to certain parcels of shore lands essential for the construction of the lock.

The plaintiff as agreed received $783,528.17 for furnishing all the material and labor for the performance of the contract. When the advertisement for bids was published the plaintiff was not advised and the advertisement did not state that the defendant had on October 25, 1932, instituted in the United States District Court for the District of Minnesota a suit to condemn the lands needed at the site of the work.

Plaintiff first became aware of the condemnation suit on December 6, 1932. Its bid for the contract having been accepted and bond filed, and having qualified under the terms of the advertisement prior to November 29,1932, plaintiff proceeded to execute the contract at the time being requested by the defendant to secure from the Chicago, Milwaukee, St. Paul and Pacific Railroad, the owners of the lands, permission to enter upon and use the same. The railroad company, defendant in the condemnation suit, at first indicated a qualified consent to plaintiff’s request; subsequently it absolutely declined to permit the plaintiff or defendant to enter upon or use the lands.

The particular features of contract construction which exacted the use of the railroad lands provided for in the specifications were, first, the construction of a cofferdam; second, the construction of an esplanade, i. e., an earth fill of approximately 15,000 cubic yards between the inner guide wall and the bank of the river, the fill to extend to an elevation of 665.

The cofferdam was the first thing to be constructed. This was specified as a “three-sided temporary cofferdam on the western shore of the Mississippi River * * *. The fourth arm * * * was to be the shore of the river.” The fact is not traversed that according to the specifications the plaintiff could not construct the fourth arm of the cofferdam [364]*364without entering upon and utilizing one of the parcels of land to which the defendant did not have title. Finding 6. The esplanade was situate upon railroad land, and the defendant did not acquire title to either parcel until August 1,1933.

The plaintiff was to complete the work within 365 days after notice to proceed, and notwithstanding the defendant’s lack of title to land involved, and the delay in the determination of its condemnation suit, the defendant on January 6, 1933, notified the plaintiff in writing to proceed with the work.

The plaintiff, in view of the situation confronting both parties to the contract, endeavored to have the defendant gain access to the lands for the location of the wings of the cofferdam and the esplanade; to postpone the date for the commencement of the work until access to the lands could be acquired, and finally to change the specifications for the cofferdam so as to avoid the necessity of entering upon the railroad’s lands. All requests were officially denied by the District Engineer.

The District Engineer placed his refusal to grant the plaintiff any relief upon specification 18, and plaintiff was therefore under the necessity of proceeding as best it could. Finding 16 itemizes plaintiff’s loss. Each item is supported by the record and no testimony appears of record to challenge their accuracy. The plaintiff, however, persisted in its efforts to obtain from the railroad company right to enter upon and use its lands and finally on March 17, 1933, sixty-nine days after the receipt of the order to proceed with the work, obtained a license from the railroad company to use its lands, and approximately 355 days later finished the contract work.

Specification 18 reads as follows:

Geounds. — All land at the site below the elevation of ordinary high water (estimated to be Elev. 653.2) is held subservient to the control of the United States for navigation and may be utilized by the contractor as an agent of the United States. The contractor will be solely responsible for obtaining any additional land which he considers necessary for construction purposes and/or the delivery and storage of materials. The con[365]*365tractor shall, without expense to the United States and at any time during the progress of work when needed for other purposes, promptly vacate and clean up any part of the Government grounds that have been allotted to or have been in use by him, when directed to do so by the contracting officer. The contractor shall keep the buildings and grounds in use by him at the site of the work in a sanitary condition. Suitable extinguishers or fire fighting apparatus shall be provided for ready use in all buildings erected or in use by the contractor on Government ground.

We think the construction adopted by the District Engineer of specification 18 is definitely erroneous, and the mistaken application he made of the same is clearly demonstrable. Manifestly, all land at the site of the work below the high-water mark of the river was subservient to the control of the United States. The river was a navigable stream, and the site of the lock indispensably exacted the utilization of the land described.

In order to construct the lock according to the adopted plans and specifications the defendant required more land than it laAvfully controlled, and was seeking through the court to obtain title to the same. We are speaking now of land the defendant needed so the lock could be constructed the way it wanted it done. The plaintiff did not possess the right of eminent domain and obviously did not require in its own name titl& to additional lands. The only land the plaintiff needed was storage space for its equipment and transportation of its materials, etc., to the site of the work. The right the plaintiff wanted to acquire was a permissive one, nothing additional.

What space the plaintiff needed, as noted above, was we think the extent and meaning of so much of the provisions of specification 18 as imposed upon it the obligation for obtaining “any additional land * * * necessary for construction purposes and/or the delivery and storage of materials.” The plaintiff’s contract provided expressly for furnishing all the materials, equipment, and labor necessary to construct the lock. No provision of the contract obligated it to acquire the fee simple title to any land essential to the construction of the permanent work.

[366]*366On January 6, 1933, the defendant was not in a position to order the plaintiff to proceed with the work. Defendant relied upon securing title to the lands involved in the condemnation suit before they would actually be needed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blinderman Construction Co., Inc. v. The United States
695 F.2d 552 (Federal Circuit, 1982)
Ouilmette Construction & Engineering Co. v. United States
89 Ct. Cl. 334 (Court of Claims, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
88 Ct. Cl. 347, 1939 U.S. Ct. Cl. LEXIS 240, 1939 WL 4233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-e-gillen-co-v-united-states-cc-1939.