Carroll v. United States

76 Ct. Cl. 103, 1932 U.S. Ct. Cl. LEXIS 454, 1932 WL 2230
CourtUnited States Court of Claims
DecidedMay 2, 1932
DocketNo. C-1236
StatusPublished
Cited by15 cases

This text of 76 Ct. Cl. 103 (Carroll v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carroll v. United States, 76 Ct. Cl. 103, 1932 U.S. Ct. Cl. LEXIS 454, 1932 WL 2230 (cc 1932).

Opinions

Booth, Chief Justice,

delivered the opinion:

The plaintiffs are Harry B,. Carroll and Louis D. Carroll, copartners doing business under the firm name of Carroll Electric Company. This suit arises out of a written contract executed by the plaintiffs and the Chief of the Bureau of Yards and Docks of the Navy Department on October 4, [115]*1151917. The contract obligated the plaintiffs to furnish,* deliver, and install the outside tunnels, tunnel piping, and the outside pipe distributing systems at the Navy Yard, Norfolk, Virginia, in accord with the written contract and specifications. The contract was what is known as a lump-sum one, i. e., for the work to be done thereunder the plaintiffs were to receive $264,700. The work to be done under this contract embraced the laying of a concrete tunnel approximately 3,000 feet in length leading from a power house to three other buildings, inside of which were to be installed heating pipes and other pipes, subject to expansion and contraction, so as to prevent loss of heat and provide easy access in cases of needed repairs thereto. It also included a distributing system involving the laying of piping for the transportation of salt water throughout the navy-yard grounds — a fire precaution — another piping system for the distribution of fresh water to the various buildings on the grounds, and still another known as the compressed-air distributing system. The distribution of salt and fresh water required the use of cast-iron piping, whereas the compressed-air system exacted the use of wrought-steel piping properly welded and buried in the ground. The contract work was of such a character as to exact a minimum of skilled labor, and was to be completed within 120 days from the date of the delivery of the contract to the plaintiffs. The date of the contract is of importance, for on that date the war activities of the Government were acute, and at the Norfolk Navy Yard the Government was engaged in an extensive program of enlargement and improvement, involving the construction of various buildings and drydocks, and it was intended by the contract to supply these various units, as well as fire prevention, by means of the distributing system provided for in the contract.

The first item in suit is predicated upon a breach of the contract with respect to the failure upon the part of the Government to definitely fix the lines and situs of the work to be done, and to remove from the site the various obstructions which precluded the plaintiffs from proceeding with the work.

[116]*116Paragraph 5 of specification 2504 provided that—

“ LocatioN. — The work included under this contract shall be located at the navy yard, Norfolk, Va., approximately in the position indicated on the drawings. The exact location will be determined by the officer in charge.”

Paragraph 6 of the general specifications provided that — ■

“ Unless otherwise specifically stated, the contractor shall be allowed reasonable space at the site of the work and access to the same for receiving, handling, storing, and working material. * * * ”

It is not denied that, with the exception of anticipated requirements of sand, gravel, cement, and specified reinforcing steel, the plaintiffs immediately ordered and procured the essential materials to promptly commence the contract work. Keeping in mind the war-time period and as a consequence thereof, the Navy Department informed the plaintiffs that the necessary quantities of sand, gravel, and cement would be furnished by the department and the cost thereof credited to the Government upon the sum to be paid the contractor for the contract work. This was all done by the department in pursuance of a governmental policy by which the latter had taken over the distribution and sale of these materials to conserve the same for governmental purposes, and the public-works officer at the yard was in charge thereof. The same situation in most respects applied to the procurement of reinforcing steel. The plaintiffs were compelled to procure governmental priority orders to obtain shipment and were finally instructed to place orders for steel with the Cambria Steel Co., Philadelphia.

What has been said above is in no way contradicted, and the facts are set forth in connection with other facts as disclosing plaintiffs’ readiness and ability to perform the contract work. The record shows that plaintiffs promptly notified the Government officials in detailed schedules of the quantity of the above materials needed and the dates upon which the same should be supplied. The plaintiffs were never given complete and definite locations for the work to be done. No comprehensive plan or sketch of the locations was ever furnished the plaintiffs. On the contrary, a sketch [117]*117of tbe locations furnished by the plaintiffs to the public-works officer on October 10,1917, prior to the delivery of the contract in suit, indicating plaintiffs’ understanding of locations, was not approved. Instead, approval of locations was given by the public-works officer in “ piecemeal,” intermittently as to designated parts of the work, rendering it impossible for the plaintiffs to proceed in an orderly fashion in the performance of the contract. The record shows that on February 7,1919, within two days of a year subsequent to the contract date for the completion of the work, the plaintiffs were without information as to the location of certain fuel lines to be laid under the terms of the contract. The justification for this delay upon the part of the Government officials is found in the record. It is clearly an administrative one. The officials did not themselves know the precise limits of location, due to inability upon their part to definitely fix the locations to be allotted to the various buildings to be constructed upon the yard and with which the distributing system was to be connected. In the meantime, however, the contractor was not only retarded in the completion of its work, but was put to additional expense and costs aggregating a considerable sum of money. Labor could not be economically employed and sometimes not at all; materials could not be utilized, and the added expense of handling the same is proven in the record.

The record establishes, as shown in finding VI, that the site of the contract work in suit was at no time cleared to a sufficient extent to enable the plaintiffs to carry on performance of the contract, either economically or expeditiously. In fact, the record indisputably establishes that the site of the work and the location for its performance were occupied with railroad tracks of other contractors, heaped high in some locations with excavated materials from the dry dock excavation, and so circumscribed in limits and obstructions that the contractor was precluded from keeping in continuous operation a new steam shovel purchased for excavating purposes, and otherwise employing labor and materials except at greatly enhanced cost and expense, and also prolonging the period of performance at the expense of the contractor. The record is most convincing that definite and [118]*118comprehensive locations for the work were never given and that the Government officials signally failed to afford the contractor an unobstructed site within which to perform the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Metropolitan Paving Company v. The United States
325 F.2d 241 (Court of Claims, 1963)
Leeds & Northrup Co. v. United States
101 F. Supp. 999 (E.D. Pennsylvania, 1951)
James Graham Mfg. Co. v. United States
91 F. Supp. 715 (N.D. California, 1950)
Mitchell Canneries, Inc. v. United States
77 F. Supp. 498 (Court of Claims, 1948)
Penker Construction Co. v. United States
96 Ct. Cl. 1 (Court of Claims, 1942)
Rice v. United States
95 Ct. Cl. 84 (Court of Claims, 1941)
Hirsch v. United States
94 Ct. Cl. 602 (Court of Claims, 1941)
Navytone Co. v. United States
91 Ct. Cl. 220 (Court of Claims, 1940)
MacDonald Engineering Co. v. United States
88 Ct. Cl. 473 (Court of Claims, 1939)
Edward E. Gillen Co. v. United States
88 Ct. Cl. 347 (Court of Claims, 1939)
H. B. Nelson Construction Co. v. United States
87 Ct. Cl. 375 (Court of Claims, 1938)
McShain Co. v. United States
83 Ct. Cl. 405 (Court of Claims, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
76 Ct. Cl. 103, 1932 U.S. Ct. Cl. LEXIS 454, 1932 WL 2230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carroll-v-united-states-cc-1932.