United States v. Gleason

175 U.S. 588, 20 S. Ct. 228, 44 L. Ed. 284, 1900 U.S. LEXIS 1708, 35 Ct. Cl. 625
CourtSupreme Court of the United States
DecidedJanuary 8, 1900
Docket59
StatusPublished
Cited by186 cases

This text of 175 U.S. 588 (United States v. Gleason) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Gleason, 175 U.S. 588, 20 S. Ct. 228, 44 L. Ed. 284, 1900 U.S. LEXIS 1708, 35 Ct. Cl. 625 (1900).

Opinion

Mr. Justice Shiras,

after stating the case, delivered the opinion of the court.

Gleason & Gosnell, a firm of contractors, entered into agreements with officers of the Engineer Corps of the United States Army, acting for and on behalf of the United States, whereby the former undertook to perform certain specified work within a certain specified time. The work specified was not completed within tho time fixed, nor at any time. Nevertheless, the contractors claimed in the court below that they were entitled to recover the contract price for the portion of the work which was actually done, and damages for the uncompleted portion, because, as they alleged, they had been prevented, by no fault of their own, but by freshets, ice and other force and violence of the elements from doing the work within the time stipulated, and had been prevented by the officers of the United States, without just cause and contrary to applicable provisions in the contract, from a subsequent completion of the work.

The material questions are determinable by a proper construction of the following clauses contained in the contracts :

“ If, in any event, the party of the second part shall delay or fail to commence with the delivery of the material or the performance of the work on the day specified herein, or shall, *601 in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then in either case the party of the first part, or his successor legally appointed, shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party or parties (or either of them) of the second part, and upon the giving of such notice all money or reserved percentage due or to become due to the party or parties of the second part by reason of this contract shall be and become forfeited to the United States; and the party of the first part shall be thereupon authorized, if an immediate performance of the work or delivery of the materials be in his opinion required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in section 3709 of the Kevised Statutes of the United States; provided, however, that if the party or parties of the second part shall, by freshets, ice or other force or violence of the elements, and by no fault of his or their own, be prevented either from commencing or completing the work or delivering the materials at the time agreed upon in this contract, such additional time may in writing be allowed him or them for such commencement or completion as, in the judgment of the party of the first part or his successor, shall be just and reasonable ; but such allowance and extension shall in no manner affect the rights or obligations of the parties under this contract, but the same shall subsist, take effect and be enforceable precisely as if the new date for such commencement or completion had been the date originally herein agreed upon.
“ The contractor must begin work within twenty days after notification that his bid has been accepted, unless hindered by high water; and within thirty days thereafter his working force must consist of at least 200 men, if working by hand, or the equivalent thereof in case excavating machines are used. If, at any time, the working force be reduced to 150 men or less, the engineer in charge shall have the right to terminate the contract; and in such case the retained percentage shall be forfeited to the United States.
*602 “The contract will expire on the'31st day of December, 1886; but the right is reserved to annul the contract in January, 1886, in case forty per cent of the work covered by the same shall not have been completed on or before the 31st day of December, 1885. The annulment of the contract under the provisions of this’ paragraph will, however, involve no forfeiture of moneys previously earned.”

While we are to determine the legal import of these provisions according to their own terms, it may be well to briefly recall certain well-settled rules in this branch of the law. One is that if a party by his contract charge himself with an obligation possible to be performed, he must make it good, unless his performance is rendered impossible by the act of God, the law, or the other party. Difficulties, even if unfore- . seen, and however great, will not excuse him. If parties have made no provision for a dispensation, the rule of law gives none — nor, in such circumstances, can equity interpose. Dermott v. Jones, 2 Wall. 1; Cutter v. Powell, 2 Smith’s Leading Cases, 1, 7th Amer. ed.

Another rule is, that it is competent for parties to a contract, of the nature of the present one, to make it a term of the contract that the decision of an engineer, or other officer, of all or specified matters of dispute that may arise during the execution of the work shall be final and conclusive, and that, in the absence of fraud or of mistake so gross as to necessarily imply bad faith, such decision will not be subjected to the revisory power of the courts. Martinsburg & Potomac Railroad v. March, 114 U. S. 549; Chicago, Santa Fé &c. Railroad v. Price, 138 U. S. 185.

We do not understand that these principles are now called into question, but their applicability is denied; and we are called upon to consider a very acute and ingenious argument, successfully urged in the court below, aiming to show that, in the present case, the controverted matter, to wit, whether the contractors were entitled to a further and additional extension of time, was not left to the determination of the engineer in charge of the work, but is open, under the language of the agreement and the facts as found, to be inquired into and determined by the court.

*603 The material terms of the contract calling for construction are as follows:

“ The said Gleason & Gosnell shall commence work under this contract on or before the twentieth day of August, 1885, and shall complete the same on or before the thirty-first day of December, 1886. . . . Provided, however, that if the party or parties of the second part shall, by freshets, ice or other force or violence of the elements, and by no fault of his or their own, be prevented either from commencing or completing the work or delivering the materials at the time agreed upon in this contract, such additional time may in writing be allowed him or them for such commencement or completion, as, in the judgment of the party of the first part or his successor shall be just and reasonable.”

Passing by, for the present, the fact that several extensions of time were granted by the engineer, and having regard only for the above language, what does it mean ? The construction put upon it by the court below was thus expressed :

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Perez v. Reider, No. Cv97 34 63 27 S, (May 20, 2002)
2002 Conn. Super. Ct. 6307 (Connecticut Superior Court, 2002)
Darwin Construction Co., Inc. v. United States
811 F.2d 593 (Federal Circuit, 1987)
S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Brownell v. United States
164 Ct. Cl. 406 (Court of Claims, 1964)
Stein Bros. Mfg. Co. v. The United States
337 F.2d 861 (Court of Claims, 1963)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
Nelley v. Mayor of Baltimore
166 A.2d 234 (Court of Appeals of Maryland, 1960)
Eastover Stores, Inc. v. Minnix
150 A.2d 884 (Court of Appeals of Maryland, 1959)
Wagner Whirler & Derrick Corp. v. United States
121 F. Supp. 664 (Court of Claims, 1954)
Knotts v. United States
121 F. Supp. 630 (Court of Claims, 1954)
Warren Bros. Roads Co. v. United States
105 F. Supp. 826 (Court of Claims, 1952)
Wildermuth v. United States
195 F.2d 18 (Seventh Circuit, 1952)
Lindsay v. United States
181 F.2d 582 (Ninth Circuit, 1950)
Penner Installation Corporation v. United States
89 F. Supp. 545 (Court of Claims, 1950)
John H. Mathis Co. v. United States
79 F. Supp. 703 (D. New Jersey, 1948)
Gadsden v. United States
78 F. Supp. 126 (Court of Claims, 1948)
Mitchell Canneries, Inc. v. United States
77 F. Supp. 498 (Court of Claims, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
175 U.S. 588, 20 S. Ct. 228, 44 L. Ed. 284, 1900 U.S. LEXIS 1708, 35 Ct. Cl. 625, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-gleason-scotus-1900.