Nelley v. Mayor of Baltimore

166 A.2d 234, 224 Md. 1, 1960 Md. LEXIS 584
CourtCourt of Appeals of Maryland
DecidedDecember 15, 1960
Docket[No. 57, September Term, 1960.]
StatusPublished
Cited by25 cases

This text of 166 A.2d 234 (Nelley v. Mayor of Baltimore) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelley v. Mayor of Baltimore, 166 A.2d 234, 224 Md. 1, 1960 Md. LEXIS 584 (Md. 1960).

Opinion

*4 Bruns, C. J.,

delivered the opinion of the Court.

Eugene J. Nelley and James O. Sanders, partners trading as Patapsco Crane & Pile Co., (Patapsco) brought this suit at law against the Mayor and City Council of Baltimore (the City) for damages to compensate them for additional costs incurred by Patapsco in the performance of a contract for the construction of a new sewer line, which costs were due to the concealment of a material fact by the City. The verdict of the jury was in favor of Patapsco. On motion of the City, judgment n. o. v. was entered in its favor on the grounds that the Patapsco’s claim was within the scope of the arbitration clause of the contract, that it had been submitted to the arbitrator specified in the contract and that it had been determined by him adversely to Patapsco prior to the institution of this suit. Patapsco appeals from the judgment.

At issue on this appeal is the correctness of the above holdings of the trial judge. The City filed a motion to dismiss the appeal on the ground that Patapsco had failed to comply with the requirements of Rule 828 (b) as to what shall be included in the appendix or printed record extract. This motion was argued immediately prior to the hearing on the merits and decision thereon was reserved. We think that the appellants’ appendix does contain enough of the evidence, pleadings and other parts of the record to enable us to determine the sufficiency thereof to support the judgment of the trial court, and we therefore deny the motion to dismiss. 1 See Brown v. Fraley, 222 Md. 480, 482-83, 161 A. 2d 128; Reddick v. State, 219 Md. 95, 97, 148 A. 2d 384, cert. den. 360 U. S. 930; cf. Columbian Carbon Co. v. Kight, 207 Md. 203, 205, 114 A. 2d 28 (which arose under a former rule).

*5 The facts in this case are simple and essentially undisputed. Bids were requested by the City for the construction of a sewer line and for the work incidental thereto. In response to this invitation, and after visiting the site of the proposed construction and receiving from the City the specifications and a drawing of the work to be done, Patapsco submitted a bid. Prior to the submission of this bid Mr. Nelley, a partner in Patapsco, called the Bureau of Sewers and asked if there was any other information Patapsco would need to formulate its bid—he was told that Patapsco had all the information requisite to making its bid. Neither Patapsco nor any other bidder was supplied at that time with a drawing of an old sewer line, showing the cracks therein, though the old line was within ten feet of the proposed new line and the City had the drawing in its files prior to its request for bids. On September 29, 1959, Patapsco being the lowest responsible bidder, was awarded the contract, known as Sanitary Contract No. 468.

Soon after Patapsco began excavating a trench for the new line, it was confronted with the seepage of raw sewage from the old line into its excavation. Upon being faced with this problem Mr. Nelley contacted Mr. Arthur P. Shanklin, Field Engineer for the Bureau of Sewers. Mr. Shanklin, in an attempt to be of assistance to appellants, supplied them with the above mentioned drawing of the old sewer line. Though believing that the City had wrongfully concealed this drawing from it, Patapsco elected to “complete the contract and obtain damages for the misrepresented portion of the project later.” After completing the contract Patapsco engaged Mr. Owen W. Turpin, a consulting engineer, who arranged a meeting on Patapsco’s behalf, with Mr. John J. Hunt, the City’s Sewerage Engineer. At this meeting Patapsco sought compensation for the expenses it had incurred in coping with the seepage of sewage from the old sewer line. In order to press its claims, which involved this matter and several others, the appellants and their then counsel attended a meeting with Mr. George A. Carter, then the Director of the City’s Department of Public Works and, as such, the referee named under the arbitration clause of Sanitary Contract No. 468 (the Arbitration Clause). This meeting was evidently in the nature of *6 a hearing, for Mr. Carter testified that he had then heard the same evidence that he had heard in court.

The Arbitration Clause reads as follows:

“Authority of Sewerage Engineer and Director of Public Works.
58. Subject to the power and authority of the Director of Public Works as provided by law and in these contract documents, the Sewerage Engineer shall in all cases, determine the amount or quantity, quality and acceptability of the work and materials which are to be paid for under this contract; shall decide all questions in relation to said work and the performance thereof; and shall, in all cases, decide questions which may arise relative to the fulfillment of the contract or to the obligations of the Contractor thereunder.
To prevent disputes and litigations, the Director of Public Works will be the referee in case any question shall arise between the Contractor and the City touching the Contract, and his determination, decision and/or estimate shall be final and conclusive upon the Contractor and shall also be a condition precedent to the right of the Contractor to receive any moneys under the contract.”

Two days after the meeting with Mr. Carter, the appellants were informed by him by letter (copies of which are stated to have been furnished to their then counsel and to the Sewerage Engineer) that “[ajcting in pursuance * * * [of his] power and authority as referee under the contract,” their “claim for * * * pumping and time lost [was] denied,” and they were also advised of his action as referee upon their other five claims, three of which appear to have been allowed in part and one in whole. Patapsco then brought this suit in the Superior Court of Baltimore City, with the result above stated.

In essence Patapsco contends that the trial judge erred in holding that the Arbitration Clause was broad enough to bar suit for the damages caused by the City’s concealment or mis *7 representation in the inducement of the substantive portions of the contract. In urging this contention, it asserts that the case of Soviero Bros. Contracting Corp. v. City of New York, 142 N.Y.S. 2d 508, 510, cited and relied upon by the trial court as authority for restricting them to their rights under the Arbitration Clause, does not support the trial court’s holding.

It is clear, assuming the correctness of Patapsco’s claim that it was a defrauded party, that Patapsco, upon discovering the fraud perpetrated upon it by the City, had an election of remedies which are mutually exclusive. It could, by appropriate action, promptly rescind the contract and be restored to its former position (which here would have included obtaining reimbursement for work done prior to discovery of the fraud and rescission), or it could affirm by performing the contract and claim damages due to the concealment or misrepresentation. The latter remedy was the one actually and clearly chosen, and it is, of course, an affirmance of the contract. Wolin v. Zenith Homes, Inc., 219 Md. 242, 250-51, 146 A. 2d 197;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baltimore Contractors, LLC v. Mayor & City Council of Baltimore
869 A.2d 396 (Court of Special Appeals of Maryland, 2005)
Port East Transfer, Inc. v. Liberty Mutual Insurance
624 A.2d 520 (Court of Appeals of Maryland, 1993)
Baltimore County v. Mayor of Baltimore
621 A.2d 864 (Court of Appeals of Maryland, 1993)
Meyer v. State Farm Fire & Casualty Co.
582 A.2d 275 (Court of Special Appeals of Maryland, 1990)
Regina Construction Corp. v. Envirmech Contracting Corp.
565 A.2d 693 (Court of Special Appeals of Maryland, 1989)
Board of Education v. Prince George's County Educators' Ass'n
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Bd. of Educ. v. PG CO. EDUCATORS'ASS'N
522 A.2d 931 (Court of Appeals of Maryland, 1987)
Barclay Townhouse Associates v. Stephen L. Messersmith, Inc.
508 A.2d 507 (Court of Special Appeals of Maryland, 1986)
Kalb v. Vega
468 A.2d 676 (Court of Special Appeals of Maryland, 1983)
Gold Coast Mall, Inc. v. Larmar Corp.
468 A.2d 91 (Court of Appeals of Maryland, 1983)
Mayor of Baltimore v. Ohio Casualty Insurance
438 A.2d 933 (Court of Special Appeals of Maryland, 1982)
Thrifty Diversified, Inc. v. Searles
429 A.2d 270 (Court of Special Appeals of Maryland, 1981)
Southern Maryland Hospital Center v. Edward M. Crough, Inc.
427 A.2d 1051 (Court of Special Appeals of Maryland, 1981)
Joseph F. Trionfo & Sons, Inc. v. Ernest B. Larosa & Sons, Inc.
381 A.2d 727 (Court of Special Appeals of Maryland, 1978)
American Structures, Inc. v. Mayor of Baltimore
364 A.2d 55 (Court of Appeals of Maryland, 1976)
Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
320 A.2d 558 (Court of Special Appeals of Maryland, 1974)
In Re the Arbitration Between Weinrott & Carp
298 N.E.2d 42 (New York Court of Appeals, 1973)
Maietta v. Greenfield
297 A.2d 244 (Court of Appeals of Maryland, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
166 A.2d 234, 224 Md. 1, 1960 Md. LEXIS 584, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelley-v-mayor-of-baltimore-md-1960.