Maietta v. Greenfield

297 A.2d 244, 267 Md. 287, 1972 Md. LEXIS 670
CourtCourt of Appeals of Maryland
DecidedDecember 7, 1972
Docket[No. 75, September Term, 1972.]
StatusPublished
Cited by30 cases

This text of 297 A.2d 244 (Maietta v. Greenfield) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maietta v. Greenfield, 297 A.2d 244, 267 Md. 287, 1972 Md. LEXIS 670 (Md. 1972).

Opinion

Scanlan, J.,

delivered the opinion of the Court.

In this case, we are asked to consider an appeal (a) prematurely taken, (b) which proves in fact to have been unnecessary, and (c) which asks that this Court advise the court below concerning matters upon which the opposing parties are now in agreement. Such a meritless resort to the appellate process must be dismissed under Rule 835 a 2. This we do, for the reasons now stated.

Appellants, Dennis Maietta and Frank Maietta, d/b/a Maietta Trucking Co. and Maietta Trucking Contractors (hereinafter referred to as “Maietta”) are a Pennsylvania partnership. Maietta is a subcontractor working on a low rent public housing project being constructed in Hagerstown known as the Noland Gardens Project. The general contractor for the project is Security Construction Company (hereinafter referred to as “Security.”) In addition to Security, the other appellees are Urban *289 Development Company and Associates, owner of the land on which the project is being constructed, the Equitable Trust Company, and the Hagerstown Housing Authority.

Maietta performed certain work on Noland Gardens. A dispute arose between Maietta and Security. Maietta then filed a mechanic’s lien and thereafter filed a petition to foreclose and enforce the mechanic’s lien against all the appellees in the Circuit Court for Washington County. Security disputed the petition to enforce the lien, claiming that there was a genuine dispute between the parties as to the amount of work, labor and materials performed or furnished by Maietta. Security also alleged that Maietta had breached the contract it had with Security. On its part, Maietta claimed that Security had breached that contract.

In the court below, Security contended that the dispute between the parties was subject to arbitration. Maietta took the position that the chancellor had exclusive jurisdiction to determine all the issues and facts involved in the dispute. After hearing argument and reviewing the contract between the parties, the chancellor entered an order, dated February 1, 1972, directing the parties to proceed by arbitration. On April 6, 1972, the chancellor filed an opinion and entered an order approving the substitution of a surety bond in the amount of $230,000.00 in place of the mechanic’s lien claimed by the appellants in the amount of $191,155.03. Maietta appealed from both orders.

AN ORDER DIRECTING ARBITRATION IS NOT APPEALABLE

The contract between Maietta and Security provides in paragraph 24 thereof that:

“In the case of dispute in regard to any of the articles of this Contract, if arbitration is provided for in the agreement between the Owner and the Contractor, same shall apply with equal force to this Contract.”

*290 Article 7.10.1 of the contract between the owner, Urban Development Company and Associates, and Security states, with exceptions not pertinent here, that “claims, disputes and other matters ins question arising out of, or relating to, this Contract or the breach thereof . . . , shall be decided by arbitration, in accordance with the Construction Arbitration rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.” The agreement between the owner" and Security goes on to provide that the agreement to arbitrate shall be specifically enforceable, that the arbitration award shall be final, “and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.” Ibid.

In 1965, Maryland adopted the Uniform Arbitration Act, now found as Article 7 of the Code (1966 Repl. Vol.). Article 7, § 1 provides as follows:

“A written agreement to submit any existing controversy to arbitration or a provision in a written contract to submit to arbitration .any controversy thereafter arising between the parties is valid, enforceable and irrevocable, save upon such grounds as exist at law or in equity for the revocation of any contract. This article does not apply to an arbitration agreement between employers and employees or between their respective representatives unless it is expressly provided in such agreement that this article shall apply.”

Article 7, Section 18 specifies those orders entered in connection with an arbitration proceeding from which an appeal may be taken. These are:

(1) An order denying an application to compel arbitration made under § 2;
(2) an order granting an application to stay arbitration made under § 2 (b);
(3) an order confirming or denying confirmation of an award;
*291 (4) an order modifying or correcting an award;
(5) an order vacating an award without directing a rehearing; or
(6) a judgment or decree entered pursuant to the provisions of this article.”

Paragraph 24 of the contract between Maietta and Security incorporates by reference article 7.10.1 of the agreement between Security and the owner which requires that “all claims, disputes and other matters in question arising out of, or relating to,” the contract “or the breach thereof,” are to “be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association.” Interpreting paragraph 24 of their contract to require arbitration, the chancellor directed the parties to proceed by arbitration. We think he was correct in that, but, in any event, his order to arbitrate is a non-appealable, interlocutory order and not one of the orders from which an appeal may be taken by virtue of Article 7, Section 18, supra.

In adopting the Uniform Arbitration Act and in limiting the categories of orders thereunder from which an appeal would lie, the General Assembly acted to encourage arbitration where the parties had contracted to arbitrate and limit the appeal of interlocutory orders entered prior to a final judgment of a court confirming, or denying the confirmation of, the arbitrators’ award. At the present time, at least fourteen States, including Maryland, have adopted a Uniform Arbitration Act. All these statutes are very similar in their essential provisions. 1

*292 The issue of the appealability of an order directing parties to arbitrate under a contract calling for arbitration, as provided for in Article 7, Section 1, supra, is one of first impression in this Court. Although cases on the precise point in other jurisdictions are limited, in at least two of the States which have adopted a Uniform Arbitration Act similar to that in effect in Maryland, it has been held that an order directing arbitration is an interlocutory, nonappealable order. Thus, in Roeder v. Huisk, 105 Ariz. 508, 467 P. 2d 902. (1970), the Arizona Supreme Court dismissed an appeal from an order of a trial court directing arbitration under a contract for the construction of a home where the contract contained an arbitration clause.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WSC/2005 LLC v. Trio Ventures Assocs.
190 A.3d 255 (Court of Appeals of Maryland, 2018)
Parker v. K & L Gates, LLP
76 A.3d 859 (District of Columbia Court of Appeals, 2013)
Dennis v. JACK DENNIS SPORTS, INC.
2011 WY 96 (Wyoming Supreme Court, 2011)
Addison v. Lochearn Nursing Home, LLC
983 A.2d 138 (Court of Appeals of Maryland, 2009)
Collier v. Pennington
2003 NMCA 064 (New Mexico Court of Appeals, 2003)
Blitz v. Beth Isaac Adas Israel Congregation
720 A.2d 912 (Court of Appeals of Maryland, 1998)
Town of Chesapeake Beach v. Pessoa Construction Co.
625 A.2d 1014 (Court of Appeals of Maryland, 1993)
Horsey v. Horsey
620 A.2d 305 (Court of Appeals of Maryland, 1993)
Regina Construction Corp. v. Envirmech Contracting Corp.
565 A.2d 693 (Court of Special Appeals of Maryland, 1989)
Evansville-Vanderburgh School Corp. v. Evansville Teachers Ass'n
494 N.E.2d 321 (Indiana Court of Appeals, 1986)
Bluffs, Inc. v. Wysocki
314 S.E.2d 291 (Court of Appeals of North Carolina, 1984)
Gold Coast Mall, Inc. v. Larmar Corp.
468 A.2d 91 (Court of Appeals of Maryland, 1983)
Hodes v. Comprehensive Health Associates, P.A.
670 P.2d 76 (Court of Appeals of Kansas, 1983)
Charles J. Frank, Inc. v. Associated Jewish Charities of Baltimore, Inc.
450 A.2d 1304 (Court of Appeals of Maryland, 1982)
American Federation of Government Employees v. Koczak
439 A.2d 478 (District of Columbia Court of Appeals, 1981)
Litton Bionetics, Inc. v. Glen Construction Co.
437 A.2d 208 (Court of Appeals of Maryland, 1981)
Cape Elizabeth School Board v. Cape Elizabeth Teachers Ass'n
435 A.2d 1381 (Supreme Judicial Court of Maine, 1981)
Town of Danvers v. Wexler Construction Co.
422 N.E.2d 782 (Massachusetts Appeals Court, 1981)
Danvers v. WEXLER CONSTRUCTION, U. ELEC. CONTR
422 N.E.2d 782 (Massachusetts Appeals Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
297 A.2d 244, 267 Md. 287, 1972 Md. LEXIS 670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maietta-v-greenfield-md-1972.