Regina Construction Corp. v. Envirmech Contracting Corp.

565 A.2d 693, 80 Md. App. 662, 1989 Md. App. LEXIS 191
CourtCourt of Special Appeals of Maryland
DecidedNovember 7, 1989
Docket298, September Term, 1989
StatusPublished
Cited by15 cases

This text of 565 A.2d 693 (Regina Construction Corp. v. Envirmech Contracting Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Regina Construction Corp. v. Envirmech Contracting Corp., 565 A.2d 693, 80 Md. App. 662, 1989 Md. App. LEXIS 191 (Md. Ct. App. 1989).

Opinion

WILNER, Judge.

The issue before us is whether the Circuit Court for Anne Arundel County erred in concluding that the underlying dispute between the parties was not within the scope of a contractual arbitration clause. We think that it did so err.

Regina Construction Corporation, a Nevada corporation having its principal office in Virginia, was the general contractor on a construction project in Washington, D.C. In June, 1984, Envirmech Contracting Corporation, a Maryland corporation, entered into a Subcontract Agreement with Regina under which Envirmech was to perform certain mechanical and plumbing work on the Washington project.

Paragraph 18 of the Subcontract required that disputes arising out of. acts, omissions, or responsibilities of the owner be resolved in accordance with the procedures set forth in the Prime Contract. With respect to disputes between Envirmech and Regina, the paragraph provided:

“Disputes solely with Contractor shall be resolved by arbitration in Washington D.C. in accordance with the rules of the American Arbitration Association. Disputes shall not interfere with the progress of the job. Work shall proceed as ordered, subject to claim.”

Envirmech “substantially completed” its work on the job in September, 1985. In May, 1988, it filed this action contending, essentially, that (1) prior to entering into the *664 subcontract, it had informed Regina that it did not have the financial wherewithal to complete the contract without assistance, (2) in order to induce it to enter into the subcontract, Regina “assured and represented that it would financially assist [Envirmech] in the performance of this project,” and (3) despite repeated requests, Regina failed to honor that commitment.

The complaint consisted of three counts. Count One charged Regina with fraud — falsely representing, “at the inception and throughout the course of this contract,” that Envirmech would be paid its actual costs plus profit and overhead without ever intending to fulfill that promise. Count Two, incorporating by reference the averments of Count One, asserted negligent misrepresentation; Count Three, also incorporating the earlier allegations, charged breach of contract. Compensatory and punitive damages were sought in all three counts.

Regina responded to the Complaint with a Motion to Dismiss. Pointing out the arbitration provision in ¶ 13 of the subcontract, it contended that Envirmech had “failed to take any step to resolve this case by Arbitration, as provided in the contract between the parties” and that the court therefore “does not have any jurisdiction over this case until such time as plaintiff fully complies with the Arbitration provisions of the subcontract____” It asked that the action be dismissed and “for such other and further relief of [sic, as] this Court deems just and proper.”

Envirmech attacked that motion on both procedural and substantive grounds. Procedurally, it urged that a motion to dismiss was not the appropriate vehicle to raise that defense — that if Regina desired to invoke the arbitration clause, it should have filed a petition to compel arbitration. Substantively, Envirmech contended that the dispute was not arbitrable for three reasons: (1) the Complaint charged that the contract, of which the arbitration clause was a part, was induced by fraud, and only the court could determine that issue; (2) the obligation to arbitrate was not mutual *665 and therefore was not binding; and (3) the issue of punitive damages was also for the court and not an arbitrator.

Eschewing the notion that discretion, at least in most instances, is the better part of valor, Regina declined to file a petition to compel arbitration and insisted that its motion to dismiss was a proper response to the Complaint. In a memorandum in support of its motion, however, it did urge that the court “has the power to compel arbitration under § 3-207 of the Courts and Judicial Proceedings Article and that compelling arbitration in this case is appropriate____” It asked that the court “either dismiss or stay this action because the arbitration clause in the contract between the parties is valid and broad.”

In an order entered January 27, 1989, the court denied Regina’s motion to dismiss on the ground that the dispute was not covered by the arbitration clause. Examining the relevant provisions of ¶ 13, the court acknowledged that the general statement that “[disputes solely with Contractor” must be arbitrated was broad enough to cover “all” disputes solely with the contractor. But that sentence, it held, was modified by the next two, requiring that disputes not interfere with the progress of the work. Accordingly, the court concluded:

“Since the work was completed, disputes solely with the Contractor cannot interfere with the progress of work, and therefore, the arbitration provisions are not applicable. The disputes alleged in this complaint are not disputes contemplated by the parties to be resolved by arbitration before resort to the courts.”

This appeal by Regina is from that order.

(1) Appealability

Before considering whether the court was right or wrong, we need to determine whether the order is even appealable at this point. In a motion to dismiss the appeal, Envirmech insists that the order does not constitute a final judgment within the meaning of Md.Cts. & Jud.Proc.Code Ann. § 12-301. It looks then to § 12-303, providing a right *666 of appeal from certain interlocutory orders, but concludes that the order at issue here does not fall within the ambit of that section. The closest possibility, it contends, is § 12-303(3)(ix), allowing an immediate appeal from an order granting a petition to stay arbitration pursuant to § 3-208, but that is not what this order did.

Given the procedural posture of the case — Regina’s unfortunate insistence on a motion to dismiss rather than a petition to compel arbitration — the question of appealability is not an easy one. To decide it, we need to look first at what law applies.

As we indicated, the subcontract at issue was between a Nevada corporation and a Maryland corporation involving a significant construction project in the District of Columbia. In that circumstance, there can be little doubt that the contract evidences “a transaction involving [interstate] commerce” and therefore falls within the ambit of the Federal Arbitration Act. 9 U.S.C. § 1 (1947). Section 2 of that Act makes valid and enforceable a written provision in any such contract “to settle by arbitration a controversy thereafter arising out of such contract or transaction, or the refusal to perform the whole or any part thereof ... save upon such grounds as exist at law or in equity for the revocation of any contract.”

Sections 3 and 4 of the Act provide the two basic mechanisms for enforcing § 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deer Automotive Group, LLC v. Brown
163 A.3d 176 (Court of Appeals of Maryland, 2017)
American Bank Holdings, Inc. v. Kavanagh
82 A.3d 867 (Court of Appeals of Maryland, 2013)
Falls v. 1CI, Inc.
57 A.3d 521 (Court of Special Appeals of Maryland, 2012)
Holloman v. Circuit City Stores, Inc.
894 A.2d 547 (Court of Appeals of Maryland, 2006)
Walther v. Sovereign Bank
872 A.2d 735 (Court of Appeals of Maryland, 2005)
Nowak v. NAHB RESEARCH CENTER, INC.
848 A.2d 705 (Court of Special Appeals of Maryland, 2004)
Aguilera v. Palm Harbor Homes, Inc.
2001 NMCA 091 (New Mexico Court of Appeals, 2001)
NOS Communications, Inc. v. Robertson
936 F. Supp. 761 (D. Colorado, 1996)
Holmes v. Coverall North America, Inc.
649 A.2d 365 (Court of Appeals of Maryland, 1994)
Ditto v. RE/MAX Preferred Properties, Inc.
861 P.2d 1000 (Court of Civil Appeals of Oklahoma, 1993)
Edward Electric Co. v. Automation, Inc.
593 N.E.2d 833 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
565 A.2d 693, 80 Md. App. 662, 1989 Md. App. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/regina-construction-corp-v-envirmech-contracting-corp-mdctspecapp-1989.