Edward Electric Co. v. Automation, Inc.

593 N.E.2d 833, 229 Ill. App. 3d 89, 171 Ill. Dec. 13, 1992 Ill. App. LEXIS 698
CourtAppellate Court of Illinois
DecidedMay 7, 1992
Docket1—91—1630,1—91—1745 cons.
StatusPublished
Cited by66 cases

This text of 593 N.E.2d 833 (Edward Electric Co. v. Automation, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Edward Electric Co. v. Automation, Inc., 593 N.E.2d 833, 229 Ill. App. 3d 89, 171 Ill. Dec. 13, 1992 Ill. App. LEXIS 698 (Ill. Ct. App. 1992).

Opinion

PRESIDING JUSTICE JIGANTI

delivered the opinion of the court:

These consolidated appeals arise from the circuit court’s denial of motions by plaintiff Edward Electric Company (Edward) and counter-defendant Anchor Conveyors, Inc. (Anchor), to confirm an arbitration award. The court instead granted the motion of defendant Emery Air Freight, Inc. (Emery), to vacate the award in its entirety. Edward and Anchor have appealed, contending that the circuit court conducted an impermissibly broad review of the arbitration award and erred in concluding that grounds existed for vacating the award.

The arbitration proceedings stemmed from the construction of a package handling and sortation system at Emery’s facility in Des Plaines, Illinois. Anchor was the general contractor on the project and was responsible for installing both the package handling and sortation system and a unified loading device (ULD) system. Automation, Inc., had a subcontract with Anchor to provide the electrical work and solicited Edward’s participation in the project. According to Edward, it initially entered the project as a joint venturer with Automation but subsequently became a subcontractor of Automation.

Edward filed suit against Emery, Anchor and Automation requesting various forms of relief including damages, an accounting and a mechanic’s lien. Emery filed a counterclaim against Anchor seeking damages for delay and incomplete work, and Anchor filed a counterclaim against Emery seeking money damages. Anchor also filed a motion to compel arbitration which was denied. On appeal, this court reversed the trial court and ordered Anchor and Emery to submit their disputes to arbitration. Edward Electric Co. v. Automation, Inc. (1987), 164 Ill. App. 3d 547, 518 N.E.2d 172.

Anchor filed an arbitration demand with the American Arbitration Association (AAA) asserting a demand against Emery in the amount of $726,364.22 plus interest and costs. In its brief to the arbitrators, Anchor requested damages from Emery in the amount of $1,628,305.84. When Anchor and Emery were unable to agree upon a panel of arbitrators, the AAA in accordance with paragraph 13 of its construction industry arbitration rules appointed three arbitrators. The panel consisted of two architects and a general contractor. Emery objected to the panel on the grounds that at least one of the arbitrators should have been a lawyer. The AAA rejected Emery’s objection and confirmed the appointment of the panel.

Before the arbitration proceedings began, Emery filed a motion to compel the admission of Edward as a party to the arbitration. Edward agreed to participate. On May 11, 1989, Emery, Anchor and Edward executed a written arbitration agreement. The agreement provided in pertinent part:

“[Emery, Anchor and Edward] hereby agree to submit to binding arbitration all controversies, claims, and disputes arising out of or relating to the parties’ involvement in the construction and installation of a ULD Handling System and a Package Handling System at Emery Air Freight Corporation’s facility in Des Plaines, Illinois. *** The extent of Edward’s claims in arbitration will be the same claims that Edward has raised against Anchor and Emery in court. *** This arbitration shall be conducted in accordance with the Construction Industry Rules of the American Arbitration Association.”

The agreement also stated that the dispute would be submitted to “the arbitration panel which had been nominated to arbitrate the disputes between Anchor Conveyors, Inc. and Emery Air Freight Corporation.” The parties agreed “to abide by and perform any award(s) rendered by the arbitrators, and that a judgment of the court having jurisdiction may be entered upon the award(s), subject to all rights of the parties under the Illinois Uniform Arbitration Act *** and the Construction Industry Rules of the American Arbitration Association.”

One of the claims which Edward submitted to the arbitrators was a mechanic’s lien claim against Emery in the amount of $119,633.50 based on labor and materials furnished in connection with the installation of “a package handling system and ULD handling system” at Emery’s facility. The first amended complaint filed by Edward in the circuit court similarly sought a mechanic’s lien in the amount of $119,633.50, but referred only to a “package to sortation system” and did not specifically mention the ULD handling system. 1 Both the arbitration claim and the court complaint filed by Edward sought money damages against Emery for breach of contract. In count V of its arbitration claim, Edward alleged that Emery made false representations that were “willful, wanton and in reckless disregard of truth” and requested punitive damages in excess of $100,000. In count II of its arbitration claim, Edward asserted a contract claim against Anchor in the amount of $30,324.78 plus interest.

The arbitration hearings took place over the course of 15 days between June 1, 1989, and December 1, 1989. On May 3, 1990, the arbitrators issued a unanimous award which provided as follows:

“1. Emery Air Freight Corporation shall pay to Anchor Conveyors, Inc. the sum of Eight Hundred Sixty-Eight Thousand, Three Hundred Sixty Dollars and Fifty-Eight Cents ($868,360.58).
2. Emery Air Freight Corporation shall pay to Edward Electric Company the sum of One Hundred Seventy-Nine Thousand, Eight Hundred Dollars and Nineteen Cents ($179,800.19) plus punitive damages in the amount of One Hundred Fifty Thousand Dollars and No Cents ($150,000.00).
3. If Emery Air Freight Corporation doesn’t pay Edward Electric Company, Edward Electric Company shall have a mechanic’s lien in the amount of $119,633.50 upon the leasehold interest of Emery Air Freight Corporation on premises at 401 West Touhy Avenue, Des Plaines, Illinois, said amount, $119,633.50 is included in the $179,800.19 Emery Air Freight Corporation must pay to Edward Electric Company.
[Paragraph 4 divided the administrative fees and expenses of the AAA among the parties.]
5. This Award is in full settlement of all claims and counterclaims submitted to this arbitration.”

On May 18, 1990, Emery filed a request for clarification and correction of the arbitration award pursuant to section 9 of the Illinois Uniform Arbitration Act (Ill. Rev. Stat. 1989, ch. 10, par. 109). On May 23, 1990, the AAA advised Emery that the request had been denied. Counsel for Emery learned that one of the arbitrators advised the AAA not to forward the request to the arbitrators and to inform Emery that it was denied.

Edward and Anchor then filed motions in the circuit court for a judgment confirming the arbitration award. Emery filed a petition to vacate the award. Following argument, the trial court denied the motions to confirm the award, vacated the award in its entirety and remanded the matter to a new panel of arbitrators specifying that one of the arbitrators should be a lawyer with a background in mechanic’s lien laws.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jordan v. Macedo
2024 IL App (1st) 230079-U (Appellate Court of Illinois, 2024)
Policeman's Benevolent & Protective Ass'n of Illinois v. City of Chicago
2023 IL App (1st) 220762-U (Appellate Court of Illinois, 2023)
Clanton v. Ray
2011 IL App (1st) 101894 (Appellate Court of Illinois, 2011)
United Automobile Insurance v. Wilson
942 N.E.2d 717 (Appellate Court of Illinois, 2011)
United Automobile Insurance Company v. Wilson
Appellate Court of Illinois, 2011
City of Chicago v. Fraternal Order of Police, Lodge No. 7
926 N.E.2d 912 (Appellate Court of Illinois, 2010)
Amerisure Mutual Insurance v. Global Reinsurance Corp. of America
927 N.E.2d 740 (Appellate Court of Illinois, 2010)
Rexnord Industries, LLC v. RHI Holdings, Inc.
906 N.E.2d 682 (Appellate Court of Illinois, 2009)
Beatty v. Doctors' Company
Appellate Court of Illinois, 2007
Beatty v. Doctors' Co.
871 N.E.2d 138 (Appellate Court of Illinois, 2007)
Radosevich v. Industrial Commission
856 N.E.2d 1 (Appellate Court of Illinois, 2006)
National Wrecking Company v. Sarang Corporation
851 N.E.2d 787 (Appellate Court of Illinois, 2006)
ARBITRATION BETWEEN WINKELMAN v. Kraft Foods, Inc.
2005 WI App 25 (Court of Appeals of Wisconsin, 2005)
Sloan Electric v. Professional Realty & Development Corp.
819 N.E.2d 37 (Appellate Court of Illinois, 2004)
Town of Cicero v. Illinois Ass'n of Firefighters
Appellate Court of Illinois, 2003
Taxman v. First Illinois Bank of Evanston
Appellate Court of Illinois, 2002

Cite This Page — Counsel Stack

Bluebook (online)
593 N.E.2d 833, 229 Ill. App. 3d 89, 171 Ill. Dec. 13, 1992 Ill. App. LEXIS 698, Counsel Stack Legal Research, https://law.counselstack.com/opinion/edward-electric-co-v-automation-inc-illappct-1992.