Seither & Cherry Co. v. Illinois Bank Building Corp.

419 N.E.2d 940, 95 Ill. App. 3d 191, 22 A.L.R. 4th 356, 50 Ill. Dec. 672, 1981 Ill. App. LEXIS 2429
CourtAppellate Court of Illinois
DecidedApril 9, 1981
Docket16435, 16447 cons.
StatusPublished
Cited by25 cases

This text of 419 N.E.2d 940 (Seither & Cherry Co. v. Illinois Bank Building Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seither & Cherry Co. v. Illinois Bank Building Corp., 419 N.E.2d 940, 95 Ill. App. 3d 191, 22 A.L.R. 4th 356, 50 Ill. Dec. 672, 1981 Ill. App. LEXIS 2429 (Ill. Ct. App. 1981).

Opinion

Mr. JUSTICE MILLS

delivered the opinion of the court:

Arbitration.

Award to petitioners.

After two years under advisement, the trial court affirmed the award.

We affirm them both.

The players in this drama and their respective roles are as follows:

Quincy-Peoples Savings <b- Loan Association — the respondent in this action upon whose property the construction work was performed;
Illinois Bank Building Corporation — a respondent who held a construction management contract with Quincy-Peoples;
Seither <b- Cherry Company — a petitioner who was responsible for the plumbing and ventilation portions of the remodeling project; Brown Electric Construction Company — a petitioner responsible for the electrical work on the project;
Heidbreder Brothers Insulation Service, Inc. — a petitioner responsible for the installation of acoustical ceiling; and
PALCO Insulation and Sales (not a party to this action), who performed the insulation of piping, plumbing and air ducts.

Facts

On July 23,1975, Seither, Brown, and Heidbreder demanded arbitration of their claims for monetary damages against Quincy-Peoples and Illinois Bank. According to the demands, petitioners suffered monetary damages when respondents unreasonably delayed completion of the construction project.

One week later, respondent Quincy-Peoples notified the American Arbitration Association that it did not consent to arbitration and that it felt it had no agreement with the petitioners to arbitrate disputes. On August 11, 1975, the AAA, through petitioners’ attorney, responded that Quincy-Peoples submitted to arbitration through its agreement with Illinois Bank, which incorporated Illinois Bank’s contracts with the petitioner-subcontractors. On August 13, 1975, Quincy-Peoples again denied it was subject to arbitration. On August 26, 1975, the AAA determined that an issue of arbitrability existed which could be decided by the arbitrator.

The arbitration hearings commenced on August 9, 1976, with the respondent, Quincy-Peoples, being represented.

William Bergman, a job superintendent for petitioner Seither, was the superintendent for the Quincy-Peoples job. Seither was responsible for plumbing and ventilation and phase 2 of the job which entailed the remodeling of the main building. (The entire construction project consisted of three phases, with only phase 2 being involved in this litigation.) As part of his regular duties, Bergman kept daily records. He testified from an abstract he made from the company’s records as to various delays which occurred between February 2, 1973, and March 14, 1975.

John Ashley testified that he was a construction manager, general manager, and vice president of petitioner Seither during thé time the Quincy-Peoples job was performed. He also testified concerning certain delays. Over respondents’ objections, Ashley was permitted to testify concerning the information used by petitioner in perfecting its bid. While Ashley did not actually prepare the bids, he examined and made notes of company documents in Keokuk, Iowa. These documents were not available at the hearing and apparently were not provided in discovery. Ashley testified that petitioner estimated the date of completion to be September 1973 with a total of 8,885 man-hours being expended. The actual man-hours spent totaled 14,036. The total contracted amount was for $293,408. Ashley computed petitioner Seither’s loss due to the delays to be $55,660. In addition, PALCO, petitioner Scither’s subcontractor, had made a claim for $13,209.50 due to the delay. Ashley determined petitioner Scither’s loss through labor reports covering man-hours attributed to the delay and through the company’s financial statements.

On cross-examination, Ashley stated he took into account delays occasioned by his company. The adjustments he made were matters of judgment on his part. He subtracted 469 hours from the estimated manpower overrun due to factors he felt were attributable to his company. Ashley stated he had no concrete evidence but that he felt the job went a minimum of 12 months beyond a reasonable completion date.

Robert Thomas, foreman for petitioner Brown Electric, stated his company contracted the electrical work. Although his company did not keep daily reports, he testified as to various delays his company experienced.

Donald Brown, the secretary-treasurer of Brown Electric, stated his company entered into a contract for phase 2 of the Quincy-Peoples job. The contract amount was $152,788. Their work was completed in midsummer 1975, and he figured his company’s loss due to labor alone to be $24,776.50. When he prepared the initial bid, he estimated it would take 4,015 hours. (He determined this figure by consulting a manual of the National Electric Contractors Association.) His company spent a total of 5,719 hours on the job for an overrun of 1,776 hours (a subtraction of the total hours from the bid hours results in a difference of 1,704 hours.) Brown took these figures from time cards.

John Heidbreder, president of petitioner Heidbreder, stated he prepared a portion of the bid and submitted the entire bid. The contract amount was $32,000 for insulation of plumbing, piping and air ducts. At the time of the bid, his father was president of the corporation and Woodrow LeGrand was secretary-treasurer. Heidbreder’s father died in February of 1973. John Heidbreder and LeGrand split up in August of 1974, at which time LeGrand formed PALCO and as part of the agreement assumed responsibility for the Quincy-Peoples job.

In December of 1973, Heidbreder entered into a $21,000 contract with Quincy-Peoples for installation of acoustical ceiling. His father prepared the bid. Heidbreder testified to certain delays his company experienced in putting in the ceiling. He estimated his company’s loss due to fault on the part of respondents at somewhere between $1,500 and $2,900.

Alan Arp, the present owner of PALCO, stated his company suffered an out-of-pocket loss for labor and materials of $13,209.50.

After petitioners rested, respondent Quincy-Peoples made a motion to dismiss, claiming (a) they had no contract with any of the claimants and (b) they did not agree to arbitrate. The arbitrator denied the motion.

On August 25, 1977, the arbitrator entered his award finding that Quincy-Peoples was subject to arbitration by reason of its full participation in all hearings and further that Quincy-Peoples was bound by the arbitration agreement through the agency relationship existing between it and the Illinois Bank Building Corporation as architect, management consultant and general contractor. Seither was awarded damages in the total sum of $30,762.16, being comprised of the sum of $17,552.66 for the primary benefit of Seither, and $13,209.50 “for the benefit of PALCO” making its claim through petitioner Seither.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago John Dineen Lodge 7 v. City of Chicago
2025 IL App (1st) 240875 (Appellate Court of Illinois, 2025)
Policeman's Benevolent & Protective Ass'n of Illinois v. City of Chicago
2023 IL App (1st) 220762-U (Appellate Court of Illinois, 2023)
Spiska Engineering, Inc. v. SPM Thermo-Shield, Inc.
2004 SD 44 (South Dakota Supreme Court, 2004)
Town of Cicero v. Illinois Ass'n of Firefighters
Appellate Court of Illinois, 2003
Hawrelak v. Marine Bank
735 N.E.2d 1066 (Appellate Court of Illinois, 2000)
Nasca v. State Farm Mutual Automobile Insurance Co.
12 P.3d 346 (Colorado Court of Appeals, 2000)
Wojdak v. Greater Philadelphia Cablevision, Inc.
707 A.2d 214 (Supreme Court of Pennsylvania, 1998)
Arnold v. Morgan Keegan & Co., Inc.
914 S.W.2d 445 (Tennessee Supreme Court, 1996)
May v. First National Pawn Brokers, Ltd.
887 P.2d 185 (Montana Supreme Court, 1994)
Chrobak v. Edward D. Jones & Co.
878 S.W.2d 760 (Court of Appeals of Arkansas, 1994)
Edward Electric Co. v. Automation, Inc.
593 N.E.2d 833 (Appellate Court of Illinois, 1992)
Drinane v. State Farm Mutual Automobile Insurance
584 N.E.2d 410 (Appellate Court of Illinois, 1991)
Hamilton v. Williams
573 N.E.2d 1276 (Appellate Court of Illinois, 1991)
Hough v. Osswald
556 N.E.2d 765 (Appellate Court of Illinois, 1990)
Arkansas Department of Parks & Tourism v. Resort Managers, Inc.
743 S.W.2d 389 (Supreme Court of Arkansas, 1988)
Hahn v. A. G. Becker Paribas, Inc.
518 N.E.2d 218 (Appellate Court of Illinois, 1987)
Henley v. Economy Fire & Casualty Co.
505 N.E.2d 1091 (Appellate Court of Illinois, 1987)
State Farm Mutual Automobile Insurance v. Stuckey
445 N.E.2d 791 (Appellate Court of Illinois, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
419 N.E.2d 940, 95 Ill. App. 3d 191, 22 A.L.R. 4th 356, 50 Ill. Dec. 672, 1981 Ill. App. LEXIS 2429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seither-cherry-co-v-illinois-bank-building-corp-illappct-1981.