Garver v. Ferguson

389 N.E.2d 1181, 76 Ill. 2d 1, 27 Ill. Dec. 773, 1979 Ill. LEXIS 308
CourtIllinois Supreme Court
DecidedMay 18, 1979
Docket51091
StatusPublished
Cited by96 cases

This text of 389 N.E.2d 1181 (Garver v. Ferguson) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garver v. Ferguson, 389 N.E.2d 1181, 76 Ill. 2d 1, 27 Ill. Dec. 773, 1979 Ill. LEXIS 308 (Ill. 1979).

Opinion

MR. CHIEF JUSTICE GOLDENHERSH

delivered the opinion of the court:

Petitioner, Bill R. Garver, filed in the circuit court of Madison County a petition to vacate (Ill. Rev. Stat. 1975, ch. 10, par. 112) or modify (Ill. Rev. Stat. 1975, ch. 10, par. 113) an arbitration award of $26,400 in favor of respondents, Roy D. Ferguson and R. Gene Cobbel, d/b/a Ferguson-Cobbel Construction. The circuit court denied the petition, confirmed the award, and entered judgment in favor of respondents and against petitioner in the amount of $26,400, together with interest from the date of the award. Petitioner appealed, the appellate court reversed and remanded for re arbitration before a new panel of arbitrators (63 Ill. App. 3d 453), and we allowed respondents’ petition for leave to appeal.

On February 25, 1975, petitioner, as owner and architect, entered into a contract with respondents, as contractors, for the construction of a house on petitioner’s lot. The contract provided for a price of $45,669 and that all work should be of good quality and in conformance with the contract documents, which included the plans and specifications "prepared by petitioner, an architectural engineer. It also provided that if the contractor substantially violated the contract, the owner, after giving the contractor seven days’ written notice, could terminate the contractor’s employment and finish the work by whatever method the owner deemed expedient, any additional costs to be paid by the contractor. The contract further provided:

“All claims, disputes, and other matters in question arising out of, or relating to, this Contract or the breach thereof except *** with respect to the Architect’s decisions on matters relating to artistic effect, and except for claims which have been waived by the making or acceptance of final payment *** shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association ***. *** [T]he award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.”

Shortly after construction began, disputes arose between the parties. Petitioner accused respondents of numerous violations of the specifications regarding the footings and basement walls; petitioner charged that as a result of the contractor’s work, the footings were too thin, the concrete used in the walls was too watery, and the walls themselves were out of plumb and out of line. Petitioner also charged that the waterproofing used on the basements walls was inferior to the grade required under the detailed waterproofing specifications contained in the contract. Petitioner continued to complain to the respondents of their noncompliance with the contract, both orally and by letter. Petitioner alleged that the wood framing was deficient; that the tub and shower were defectively installed; that the roof flashing was too thin and had been cut when installed; and that the roofing paper was torn and improperly laid. On June 10, 1975, following the dispute regarding the roof, petitioner terminated the contract and had the sheriff remove respondents’ employees from the property. Petitioner attempted to obtain bids to finish the construction, but was unable to find a contractor who would complete the house unless paid for “time and material.” On this basis petitioner employed another contractor, paying him $47,040. The house was eventually completed at a total cost to petitioner of $59,222.

On March 1, 1976, respondents filed a demand for arbitration. Alleging that “work stoppage and refusal to pay by the owner were without reasonable cause,” respondents claimed that there was due them the sum of $45,000. Petitioner denied liability and counterclaimed in the amount of $18,211.30, the amount by which his total construction costs exceeded the contract price, after adjustment for items furnished by petitioner and for materials not used by respondents. The parties selected three arbitrators, but when one arbitrator did not appear the parties agreed to proceed with a two-member panel comprised of an architect and a building contract estimator. Although no stenographic record was kept at the arbitration hearing, petitioner made a tape recording from which a transcript was later typed. After a two-day hearing, the arbitrators entered an award in favor of respondents for $26,400, stating only that the award was “in full settlement of all claims and counterclaims submitted to this arbitration.” The arbitrators made no findings of fact or law.

Petitioner filed a petition in circuit court to vacate or modify the award alleging that one of the arbitrators was partial and that the arbitrators exceeded their powers. Respondents filed an answer and counterpetition, asking that the arbitration award be confirmed and judgment entered upon it. Respondents’ petition was granted.

The appellate court found that the arbitrators “exceeded their power and did not arbitrate on the basis of the contract” (63 Ill. App. 3d 453, 457), that the breach of contract was entirely due to respondent’s failure to follow the contract specifications, and remanded the cause to the circuit court “to implement arbitration before a new panel of arbitrators.”

Section 12(a) of the Uniform Arbitration Act (Ill. Rev. Stat. 1975, ch. 10, par. 112(a)) provides:

“(a) Upon application of a party, the court shall vacate an award where:
(1) The award was procured by corruption, fraud or other undue means;
(2) There was evident partiality by an arbitrator appointed as a neutral or corruption in any one of the arbitrators or misconduct prejudicing the rights of any party;
(3) The arbitrators exceeded their powers;
(4) The arbitrators refused to postpone the hearing upon sufficient cause being shown therefor or refused to hear evidence material to the controversy or otherwise so conducted the hearing, contrary to the provisions of Section 5, as to prejudice substantially the rights of a party; or
(5) There was no arbitration agreement and the issue was not adversely determined in proceedings under Section 2 and the party did not participate in the arbitration hearing without raising the objection; but the fact that the relief was such that it could not or would not be granted by a court of law or equity is not ground for vacating or refusing to confirm the award.”

Prior to the enactment of the Uniform Arbitration Act, section 11 of “An Act to revise the law in relation to arbitrations and awards” (Ill. Rev. Stat. 1959, ch. 10, par. 11) provided that a court could vacate an award if “obtained by fraud, corruption or other undue means”; if “any legal defects shall appear in the award”; or if “such arbitrators misbehaved.” Although appearing to vest a court with broader powers to vacate an award than does the present statute, the prior provision was given an interpretation consistent with the present act. (Ill. Ann. Stat., ch. 10, par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgan v. Silver Financial Capital, Inc.
2025 IL App (1st) 241488-U (Appellate Court of Illinois, 2025)
Policeman's Benevolent & Protective Ass'n of Illinois v. City of Chicago
2023 IL App (1st) 220762-U (Appellate Court of Illinois, 2023)
Birkelbach v. The Braeside Foundation
2023 IL App (1st) 220956-U (Appellate Court of Illinois, 2023)
Power Construction Company, LLC v. Michels Corporation
2020 IL App (1st) 200084-U (Appellate Court of Illinois, 2020)
Pluciennik v. Vandenberg
2018 IL App (3d) 160726 (Appellate Court of Illinois, 2019)
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Ass'n
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Radiant Star Enterprises, L.L.C. v. Metropolis Condominium Association
2018 IL App (1st) 171844 (Appellate Court of Illinois, 2018)
Bankers Life & Casualty Insurance v. CBRE, Inc.
830 F.3d 729 (Seventh Circuit, 2016)
Advocate Financial Group v. Poulos
2014 IL App (2d) 130670 (Appellate Court of Illinois, 2014)
United Automobile Insurance v. Wilson
942 N.E.2d 717 (Appellate Court of Illinois, 2011)
United Automobile Insurance Company v. Wilson
Appellate Court of Illinois, 2011
Kenny v. KENNY INDUSTRIES, INC.
951 N.E.2d 499 (Appellate Court of Illinois, 2010)
Amerisure Mutual Insurance v. Global Reinsurance Corp. of America
927 N.E.2d 740 (Appellate Court of Illinois, 2010)
International Association of Firefighters v. City of Springfield
883 N.E.2d 590 (Appellate Court of Illinois, 2008)
TruServ Corp. v. Ernst & Young LLP
876 N.E.2d 77 (Appellate Court of Illinois, 2007)
Spencer v. Ryland Group Inc.
865 N.E.2d 301 (Appellate Court of Illinois, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
389 N.E.2d 1181, 76 Ill. 2d 1, 27 Ill. Dec. 773, 1979 Ill. LEXIS 308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garver-v-ferguson-ill-1979.