Grudem Brothers Co. v. Great Western Piping Corp.

213 N.W.2d 920, 297 Minn. 313, 80 A.L.R. 3d 147, 1973 Minn. LEXIS 1092
Supreme Court of Minnesota·Decided September 21, 1973·No. 43984·Published·Cited by 39 cases

Opinions

Per Curiam.

This is an appeal from an order of Hennepin County District Court denying the motion of plaintiff to vacate an award of arbitration for fraud and perjury and disallowing the right of offset against the award.1 We affirm.

The dispute had arisen between plaintiff, Grudem Brothers Co., a mechanical contractor, and defendant, Great Western Piping Corporation, its excavating subcontractor, concerning liability for certain work performed in the construction of aeration tanks at the Pig’s Eye Sewage Treatment Plant in St. Paul, Minnesota. By written agreement dated July 7, 1971, the parties had agreed to submit the dispute to arbitration. By oral agreement, later confirmed by letters, the parties had also agreed to participate in the hearing before the arbitrators without legal counsel. On November 3, 1971, after receiving testimony from the parties, the arbitration panel filed an award in favor of Great Western. On November 15, 1971, Grudem applied to the arbitrators for change of the award. On December 8, 1971, a Clarification of Award was made so as to include certain liens and claims not previously considered, but in all other respects the award remained unchanged.

On January 28, 1972, Grudem filed a motion in district court requesting vacation of the award pursuant to Minn. St. 572.19. One of the arbitrators was subpoenaed to give testimony to establish that the award was procured by fraud and mistakenly caused an unintended result. On March 6, 1972, the district court issued two orders, one determining that testimony of an arbitrator was inadmissible and the other confirming the award. The latter [315]*315order was thereafter vacated to permit arguments relating to the vacation of the award. The order from which appeal is taken, confirming the award of arbitration and directing entry of judgment against Grudem, was filed on September 6, 1972.

Grudem contends that the award of arbitration should have been vacated because defendant violated a collateral agreement not to use attorneys and committed perjury in submitting facts to the arbitrators. Grudem also contends that arbitrators exceeded the scope of authority granted to them in the submission agreement by the award which denies a setoff of other claims. It is also argued that the testimony of an arbitrator should be admissible to show that the wording of the award causes an unintended result in preventing setoffs.

Minn. St. 572.19, subd. 1, lists five grounds for vacating an award of arbitration including the following:

“(1) The award was procured by corruption, fraud or other undue means;

❖ * * * *

“(3) The arbitrators exceeded their powers.”

Grudem argues that the award was procured through the fraud of Great Western in engaging an attorney to prepare the 50-page statement of claim presented to the arbitrators. This is claimed to be a violation of their agreement not to use counsel.

The parties’ verbal agreement is confirmed in a number of letters to the American Arbitration Association. In a letter of Great Western dated October 7, 1971, it is stated:

“I would like to advise you and ask Grudem Brothers Company to confirm our verbal agreement that we each present our own case without the benefit of legal counsel * *

In a letter of Grudem dated October 21, 1971, this understanding was confirmed:

“* * * The agreement is that neither party shall use nor be accompanied by legal counsel during the course of the hearing.” [316]*316After this letter was received, no attorneys were used by Great Western.

These letters reasonably indicate that the parties intended to restrict the use of counsel at the hearing itself rather than1 their use entirely. However, even if the parties intended to restrict the use of attorneys entirely, Grudem did not confirm the agreement until shortly before the hearing, at which time Great Western dismissed its attorneys. The agreement is capable of different interpretations. The mere fact that the parties viewed the limitation on the use of attorneys differently does not establish that Great Western acted fraudulently in its interpretation of the agreement. Besides, under Minn. St. 572.13, a party in arbitration proceedings or hearings has the right to be represented by an attorney and a waiver of the right prior to the proceeding or hearing is ineffective.

Grudem also alleges that the labor cost figures submitted by Great Western were perjured because they were substantially greater than other sworn cost figures. Great Western submitted these cost figures of about $35,000 based on sworn payroll records. Grudem, on the other hand, presented Great Western’s sworn Davis-Bacon reports2 showing labor costs of only about $10,000. The arbitrators accepted Great Western’s figures as the proper measure of these costs.

Great Western explains the discrepancy in the different payroll figures as follows: (1) The Davis-Bacon reports covered a lesser period of work time; (2) they did not include the wages of company officials; (3) they did not reflect employee overhead expenses; (4) wages of some workers were not reported under instructions from Grudem.

The arbitrators make the final determination of all questions submitted to them whether legal or factual. The court will not overturn these conclusions even if it believes the arbitrators [317]*317made an incorrect conclusion. If arbitrators’ decisions were subject to reconsideration by the courts, arbitration proceedings would work merely to delay final decisions of controversies rather than bring them to speedy resolution. Cournoyer v. American Television & Radio Co. 249 Minn. 577, 580, 83 N. W. 2d 409, 411 (1957). In the present case, the arbitrators, as the final judges of the facts, were justified in accepting whichever payroll figures they decided most accurately reflected these costs. Furthermore, if Great Western did commit perjury in preparing the Davis-Bacon reports, it was perjury before the Federal authorities and not before the arbitrators.

Grudem also contends that the award should be vacated because the arbitrators exceeded their authority under the submission agreement. Grudem claims the arbitrators went beyond the matters submitted in that the language of the award prevents setoff against the award for other claims between the parties.

The dispute between the parties was submitted to arbitration to be determined according to the Construction Industry Arbitration Rules. The scope of the matters submitted was as follows:

“Great Western Piping Corporation claims that Grudem Brothers Company owes Great Western the sum of $49,760.35, in addition to amounts thus far paid, for work done, materials purchased, costs incurred and damages suffered by Great Western in connection with its undertaking as a subcontractor to Grudem Brothers on the project for the construction of aeration tanks at the Metropolitan Sanitary Sewer District sewage treatment plant at Pig’s Eye, St. Paul, Minnesota.

“Grudem Brothers Company denies said claim and any liability in connection therewith.”

In addition, the submission agreement stated:

“We agree that we will abide by and perform any Award rendered hereunder and that a judgment may be entered upon the Award” (Italics supplied.) [318]

Free access — add to your briefcase to read the full text and ask questions with AI

Grudem Brothers Co. v. Great Western Piping Corp., 213 N.W.2d 920, 297 Minn. 313, 80 A.L.R. 3d 147, 1973 Minn. LEXIS 1092 (Mich. 1973).

213 N.W.2d 920 (Grudem Brothers Co. v. Great Western Piping Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

University of Minnesota v. Woolley
659 N.W.2d 300 (Court of Appeals of Minnesota, 2003)
Ray v. City of Maple Grove
519 N.W.2d 466 (Court of Appeals of Minnesota, 1994)
Thompson v. Lee
589 A.2d 406 (District of Columbia Court of Appeals, 1991)
Aufderhar v. Data Dispatch, Inc.
452 N.W.2d 648 (Supreme Court of Minnesota, 1990)
David Co. v. Jim W. Miller Construction, Inc.
444 N.W.2d 836 (Supreme Court of Minnesota, 1989)
Aufderhar v. Data Dispatch, Inc.
437 N.W.2d 679 (Court of Appeals of Minnesota, 1989)
Littfin Lumber Co. v. Fasching
436 N.W.2d 791 (Court of Appeals of Minnesota, 1989)
David Co. v. Jim W. Miller Construction, Inc.
428 N.W.2d 590 (Court of Appeals of Minnesota, 1988)
Independent School District No. 51 v. School Service Employees Union Local 284
428 N.W.2d 844 (Court of Appeals of Minnesota, 1988)
Gruman v. Hendrickson
416 N.W.2d 497 (Court of Appeals of Minnesota, 1987)
E.D.S. Construction Co. v. North End Health Center, Inc.
412 N.W.2d 783 (Court of Appeals of Minnesota, 1987)
Koranda v. Austin Mutual Insurance Co.
397 N.W.2d 357 (Court of Appeals of Minnesota, 1986)
Afscme Dist. Coun. 96 v. Ind. Sch. Dist. 381
351 N.W.2d 33 (Court of Appeals of Minnesota, 1984)
Western Waterproofing Co. v. Lindenwood Colleges
662 S.W.2d 288 (Missouri Court of Appeals, 1983)
Bingham County Commission v. Interstate Electric Co.
665 P.2d 1046 (Idaho Supreme Court, 1983)