The Jamar Company v. Independent School District No. 2142, St. Louis County Schools, Minnesota

CourtCourt of Appeals of Minnesota
DecidedMay 18, 2015
DocketA14-1187
StatusUnpublished

This text of The Jamar Company v. Independent School District No. 2142, St. Louis County Schools, Minnesota (The Jamar Company v. Independent School District No. 2142, St. Louis County Schools, Minnesota) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Jamar Company v. Independent School District No. 2142, St. Louis County Schools, Minnesota, (Mich. Ct. App. 2015).

Opinion

This opinion will be unpublished and may not be cited except as provided by Minn. Stat. § 480A.08, subd. 3 (2014).

STATE OF MINNESOTA IN COURT OF APPEALS A14-1187

The Jamar Company, Respondent,

vs.

Independent School District No. 2142, St. Louis County Schools, Minnesota, Appellant.

Filed May 18, 2015 Reversed and remanded Chutich, Judge

St. Louis County District Court File No. 69VI-CV-13-260

Dean B. Thomson, Matthew T. Collins, Lucas T. Clayton, Fabyanske, Westra, Hart & Thomson, P.A., Minneapolis, Minnesota (for respondent)

Stephen M. Knutson, Michelle D. Kenney, Knutson, Flynn & Deans, P.A., Mendota Heights, Minnesota (for appellant)

Considered and decided by Smith, Presiding Judge; Chutich, Judge; and

Minge, Judge.

 Retired judge of the Minnesota Court of Appeals, serving by appointment pursuant to Minn. Const. art. VI, § 10. UNPUBLISHED OPINION

CHUTICH, Judge

Appellant Independent School District No. 2142, St. Louis County Schools (the

school district) challenges the district court’s decision to vacate an arbitration award

designating the school district as the prevailing party in a construction contract dispute.

The school district further argues that the district court erred in modifying the arbitration

award to name respondent Jamar Company as the prevailing party entitled to attorney

fees. Because the arbitrator did not exceed his authority in designating the school district

as the prevailing party, we reverse and remand for the district court to calculate the

appropriate amount of attorney fees to award in favor of the school district.

FACTS

In August 2010, Jamar signed a $1,430,485 contract with the school district to

construct a roof for a new school building in New Independence. Installation of the new

roof was to begin on February 3, 2011, and be completed by March 31, 2011. The

contract stated that Jamar would install a certain type of roof, known as a sure-white

roofing system, which could only be installed if the surface and/or ambient temperature

was 25 degrees Fahrenheit or warmer. The contract also specified that Jamar was

responsible for ensuring that it could install the roof despite winter conditions.

In early November 2010, Jamar told the school district, through the project

construction manager, that installation of the sure-white roofing system would be

impossible because the temperature would likely remain below 25 degrees Fahrenheit for

at least some of the installation period. Despite Jamar’s breach, the school district chose

2 not to terminate the contract and instead elected to accommodate Jamar and change to an

alternative hot-mopped roof system. On March 7, 2011, the school district issued a

construction change directive to allow Jamar to proceed with installation of the hot-

mopped system.

In August 2011, Jamar estimated that changing to the hot-mopped roof had cost an

additional $183,000. The school district refused to pay this amount. On April 16, 2012,

Jamar initiated an arbitration proceeding to recover the cost of installing the hot-mopped

system, seeking $149,308.65 in damages plus interest, fees, and costs. The school district

counterclaimed, seeking an award of $75,000 plus interest, fees, and costs. Before the

arbitration in September 2012, Jamar hired an expert witness to review its claim and as a

result, reduced its demand to $86,786.72.

During arbitration, Jamar argued that the temperature only became an issue after

the project construction manager, Kraus-Anderson, moved its installation schedule up to

early January. The arbitrator found that this argument was inconsistent with testimony

presented because Kraus-Anderson did not raise the issue of moving up the schedule until

December 2010 and Jamar asked to change the roof type in November. Indeed, Jamar’s

own expert testified that the proposed change in the construction schedule was immaterial

because Jamar would have needed to use some form of winter protection regardless of

whether the work was performed in January or February.

The arbitrator awarded Jamar $40,809.22. The arbitrator determined that Jamar

breached its contract when it refused to install the sure-white roofing system but that the

school district waived its right to terminate the contract when it elected to accept the hot-

3 mop roof system. The arbitrator stated that Jamar had originally priced its work on the

hot-mopped system at $183,000, and reduced it to $149,000, then to $86,786.72, and

ultimately recovered only $40,809.22. The arbitrator stated that “[i]f Jamar had

accurately calculated the costs for the changed work from the beginning, this entire

dispute would have likely been avoided.” The arbitrator then concluded that the school

district was the prevailing party and awarded it $109,454.85 for attorney fees and

$10,300 for expert-witness fees.

Jamar moved to vacate and modify the arbitration award in district court, arguing

that the arbitrator exceeded his authority. The district court granted Jamar’s motion and

vacated the portion of the arbitration award designating the school district as the

prevailing party. It concluded that the arbitrator exceeded his authority by relying on

facts outside the record, specifically focusing on the arbitrator’s statement that “[i]f Jamar

had accurately calculated the costs for the changed work from the beginning, this entire

dispute would have likely been avoided.” The district court characterized this statement

as “pure speculation and without any evidentiary support in the record.” The district

court also modified the award and named Jamar as the prevailing party entitled to recover

attorney fees and costs and remanded the issue of calculating attorney fees to the

arbitrator.

The school district then appealed the district court’s decision to vacate and modify

the arbitration award. This court dismissed the appeal because it was taken from a

nonfinal order. Jamar next moved the arbitrator for an award of all attorney fees, costs,

and disbursements that it had incurred.

4 The arbitrator issued a modified award, granting Jamar $125,865.20 in attorney

fees, costs, and disbursements relating to the arbitration. The arbitrator declined to award

Jamar attorney fees for its motion to vacate and modify the arbitration award, stating that

these amounts would be “more appropriately addressed by the District Court.”

Accordingly, Jamar filed a motion in district court to confirm the arbitration

award. The district court confirmed the award and concluded that Jamar’s motion for

attorney fees was timely. The district court also granted Jamar an additional $37,374.58

for attorney fees and costs incurred in the lawsuit following the arbitration. The school

district appealed.

DECISION

The arbitration process is favored in the law. Ehlert v. W. Nat’l Mut. Ins. Co., 296

Minn. 195, 199, 207 N.W.2d 334, 336 (1973). Arbitrators make final determinations of

law and fact. Grudem Bros. Co. v. Great W. Piping Corp., 297 Minn. 313, 316, 213

N.W.2d 920, 922-23 (1973). An arbitration award is set aside “only when the objecting

party meets its burden of proof that the arbitrators have clearly exceeded the powers

granted to them in the arbitration agreement.” Seagate Tech., LLC v. W. Digital Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
Ehlert Ex Rel. Ehlert v. Western National Mutual Insurance
207 N.W.2d 334 (Supreme Court of Minnesota, 1973)
Grudem Brothers Co. v. Great Western Piping Corp.
213 N.W.2d 920 (Supreme Court of Minnesota, 1973)
Ag Services of America, Inc. v. Schroeder
693 N.W.2d 227 (Court of Appeals of Minnesota, 2005)
County of Hennepin v. Law Enforcement Labor Services, Inc., Local 19
527 N.W.2d 821 (Supreme Court of Minnesota, 1995)
National Indemnity Co. v. Farm Bureau Mutual Insurance Co.
348 N.W.2d 748 (Supreme Court of Minnesota, 1984)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Seagate Technology, LLC v. Western Digital Corporation, Sining Mao
854 N.W.2d 750 (Supreme Court of Minnesota, 2014)
Seagate Technology, LLC v. Western Digital Corp.
834 N.W.2d 555 (Court of Appeals of Minnesota, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
The Jamar Company v. Independent School District No. 2142, St. Louis County Schools, Minnesota, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-jamar-company-v-independent-school-district-no-2142-st-louis-county-minnctapp-2015.