David Co. v. Jim W. Miller Construction, Inc.

444 N.W.2d 836, 1989 Minn. LEXIS 221
CourtSupreme Court of Minnesota
DecidedSeptember 8, 1989
DocketC6-88-327, C4-88-830
StatusPublished
Cited by19 cases

This text of 444 N.W.2d 836 (David Co. v. Jim W. Miller Construction, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
David Co. v. Jim W. Miller Construction, Inc., 444 N.W.2d 836, 1989 Minn. LEXIS 221 (Mich. 1989).

Opinion

KELLEY, Justice.

Appellant Jim W. Miller Construction, Inc. (Miller) contracted with respondent David Company to construct seven townhouses in two phases on a lot owned by respondent on Big Detroit Lake. Following completion of the first phase, a dispute arose between the parties respecting *838 claimed defective workmanship. 1 Arbitrators chosen to resolve the dispute, as part of their award, ordered the general contractor (Miller) to purchase the real property on which the subject buildings had been erected. The issue presented to us is whether in so doing the arbitrators exceeded their powers. A divided court of appeals panel affirmed a district court order which had affirmed the award. 2 We conclude that although the award formulates an innovative remedy which may appear to be anomalous when compared to traditional arbitration awards, it was within the scope of the broad powers delegated to the arbitrators by the construction contract. The extent and magnitude of the many and serious construction defects; the repeated noncompliance with contract obligations; and the numerous building code violations, all of which, when combined, resulted in David Company receiving a building of slight value, and additionally, an exposure to potential future liabilities, justify the novel remedy fashioned. Therefore, we affirm.

The construction contract at issue was entitled “General Conditions of the Contract for Construction.” It included an arbitration clause by which the parties agreed that “[a]ll claims, disputes and other matters in question * * * arising out of, or relating to, the contract documents or the breach thereof * * * ” would be subject to arbitration with the exception of claims waived by the making of final payment. 3

Shortly after the commencement of construction on Phase I of the project, construction problems began to surface and thereafter continued throughout construction. David Company attributed the recurrence of these problems to Miller's inadequate supervision of subcontractors and its tolerance of poor workmanship by them. Primarily because of those problems, completion of construction on Phase I was delayed beyond the contract completion date of May 1984 to October of that year. David Company claimed this delay not only caused it to lose sales of the units and to incur additional interest and other expense, but, in addition, left it with shoddily constructed units which were unmarketable as *839 the luxury-type units originally contemplated by the project.

David Company was aware of numerous construction deficiencies, knew they had not been rectified, and that Phase I completion had been delayed for months, when it made final payment to Miller on Phase I in November 1984. Miller argues that the final payment constituted waiver under subparagraphs 9.9.4 and 9.9.5 of the contract. In response, David Company claims it made the payment reluctantly and only after it had been induced to do so by Miller’s reaffirmation of its contractual and other legal obligations to remedy all construction deficiencies in its work.

Shortly after making final payment, David Company learned of additional previously unknown extensive and serious construction defects. Moreover, further non-conformities with contract requirements and building code violations emerged. After Miller refused to correct the newly discovered deficiencies, David Company filed its Demand for Arbitration with the American Arbitration Association. In its Demand it alleged breach of contract, negligence and misrepresentation. For relief it requested “compensation for damages in excess of $250,000, including damages which continue to accrue, plus costs, disbursements, attorney fees and interest.” It likewise expressly reserved the right to later amend the demand.

A building contractor and two professional engineers were selected by the parties to arbitrate the dispute. The arbitrators heard evidence presented by the parties over a span of three days, heard submissions of counsel for each party, and physically visited the project site to inspect and evaluate the quality of construction. Evidence presented to the arbitrators revealed numerous and serious construction defects and deficiencies, which, in addition to others, included extensive water infiltration problems, structural damage resulting from the collapse of improperly constructed party walls, absence of anchor bolts, walls out of plumb, and corners out of square. 4 The extent and nature of the construction defects demonstrated gross disregard of standard construction practice, noncompliance with contract requirements, and violation of applicable building codes. Further evidence presented to the arbitrators revealed that the omissions, defects, and overall poor workmanship had resulted in rescission demands from owners to whom David had sold units prior to completion, and had rendered the unsold units, in a practical sense, unmarketable absent extensive and costly repairs.

During the course of his closing argument before the arbitration panel, one of David Company’s attorneys, while highlighting the numerous and substantial items of shabby workmanship, observed that his client, and, perhaps as well, vendees who had purchased the units, might be saddled with contingent future liabilities under statutory warranties. 5 He noted that Miller was not only a building contractor, but, as well a developer and owner of real estate thereby implying that, as such, Miller might well better bear that risk than could the respondents. Thereupon, the arbitrators suggested to the parties that they might consider an award resulting in Miller ending up with the project and the property on which it was located in exchange for a cash payment to David Company. Miller’s counsel promptly objected on the ground that to so structure *840 an award, the arbitrators would exceed the power granted to them. Nonetheless, David Company’s lawyers prepared an itemized “sell back” option 6 claiming $884,-476 in damages. (Claimed damages included consequential damages resulting from construction delay and land costs for unordered and unbuilt Phase II units). The arbitrators’ award incorporated the “sell back” option. Alternatively, in the event David Company was unable to convey the property free of liens within 45 days, the award provided for a monetary damages award of $497,925 to be paid to David Company. David Company chose to exercise the “sell back” option, and pursuant thereto, made timely tender of performance. When Miller refused to perform by making the payment as required by the arbitrators’ award, David Company commenced an action in district court to confirm the award. Ultimately the trial court issued an order confirming the award and ordering entry of judgment. A majority of the court of appeals panel affirmed the order.

Before this court Miller contends that the arbitrators exceeded their powers within the meaning of Minn.Stat. § 572.19, subd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seagate Technology, LLC v. Western Digital Corporation, Sining Mao
854 N.W.2d 750 (Supreme Court of Minnesota, 2014)
Seagate Technology, LLC v. Western Digital Corp.
834 N.W.2d 555 (Court of Appeals of Minnesota, 2013)
Brenda Darlene, Inc. v. Bon Secour Fisheries, Inc.
101 So. 3d 1242 (Court of Civil Appeals of Alabama, 2012)
Fietz v. SOUTHLAND NAT. INS. CO.
484 F. Supp. 2d 535 (W.D. Louisiana, 2007)
Bruce v. Cole
854 So. 2d 47 (Supreme Court of Alabama, 2003)
Peggy Rose Revocable Trust v. Eppich
640 N.W.2d 601 (Supreme Court of Minnesota, 2002)
Fedie v. Mid-Century Insurance Co.
631 N.W.2d 815 (Court of Appeals of Minnesota, 2001)
EEC Property Co. v. Kaplan
578 N.W.2d 381 (Court of Appeals of Minnesota, 1998)
Allstate Insurance Co. v. Nodak Mutual Insurance Co.
540 N.W.2d 614 (North Dakota Supreme Court, 1995)
JBC of Wyoming Corp. v. City of Cheyenne
843 P.2d 1190 (Wyoming Supreme Court, 1992)
Ortega v. Farmers Insurance Group
474 N.W.2d 7 (Court of Appeals of Minnesota, 1991)
Michael-Curry Companies v. Knutson Shareholders Liquidating Trust
449 N.W.2d 139 (Supreme Court of Minnesota, 1989)
Olson v. Ronhovde
446 N.W.2d 690 (Court of Appeals of Minnesota, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
444 N.W.2d 836, 1989 Minn. LEXIS 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/david-co-v-jim-w-miller-construction-inc-minn-1989.