City of Worcester v. Granger Bros.

474 N.E.2d 1151, 19 Mass. App. Ct. 379, 1985 Mass. App. LEXIS 1556
CourtMassachusetts Appeals Court
DecidedFebruary 21, 1985
StatusPublished
Cited by11 cases

This text of 474 N.E.2d 1151 (City of Worcester v. Granger Bros.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Worcester v. Granger Bros., 474 N.E.2d 1151, 19 Mass. App. Ct. 379, 1985 Mass. App. LEXIS 1556 (Mass. Ct. App. 1985).

Opinion

Greaney, C.J.

This appeal arises from a judgment of the Superior Court confirming an arbitration award received by the parties on January 3, 1984. We affirm the judgment.

I. Parties and Background.

The arbitration arose out of the construction of the Worcester Civic Center (project), a twelve-thousand seat, multipurpose arena in Worcester. The parties to the arbitration were the project’s owner, the city of Worcester (city); its developer, Worcester Development Consortium (WDC); the phase III general contractor, Granger Bros., Inc. (Granger), and its surety, United States Fidelity & Guaranty Company (USF & G); and the phase IV general contractor, Finance/Design/Construct, Inc. (F/D/C), and its surety, St. Paul Fire & Marine Insurance Co. (St. Paul).

The initial “Design/Construct Agreement” between the city and WDC, dated October 14, 1977, provided that the project would be built in six separate phases, each awarded by separate bid. 2 The “[guaranteed, [mjaximum [pjrice” of the project, as authorized by the Legislature, see St. 1976, c. 216, § 4(d), and fixed by the contract, was $14,500,000. However, the contract expressly provided that this sum could be increased in several ways, including, insofar as relevant here, by “equitable adjustment (including any arbitration award).” The contract also contained a very broad and general arbitration clause which called for the arbitration of “[a]ll claims, disputes and other matters in question arising out of, or relating to this [cjontract, or the breach thereof.”

The design/construct contract required WDC to furnish the city with design plans and to manage construction of the project *381 on a so-called fast-track basis. 3 To satisfy this obligation, WDC gave assurances in the contract that it had obtained the necessary design services by its separate agreement with Ellerbe Associates, Inc. (Ellerbe), and Ellerbe’s principals, licensed architects and engineers in Massachusetts. The city was not a party to the contract between WDC and Ellerbe.

On May 15, 1978, the city executed with Granger the phase TTT contract for foundation work and steel erection. On October 19, 1978, the city executed with F/D/C the phase IV contract for the enclosure of the project and finishing work. Both the phase m and IV contracts also contained broad and general “all claims and disputes” arbitration clauses which were virtually identical to the arbitration clause in the design/construct contract quoted above. The general conditions to these contracts further provided that the general contractors’ remedy for any delay caused by either the owner (the city) or the developer (WDC) would be a time extension rather than damages. However, the phase IV contract also contained a provision, in possible conflict with the no-damages-for-delay clause, which made the contract subject to G. L. c. 30, § 390, inserted by St. 1973, c. 1164. This statute requires a price adjustment in the general contractor’s favor if a change in the cost of the contractor’s performance is increased by any delay attributable to the awarding authority lasting fifteen days or longer. Pursuant to its contract with the city, F/D/C entered into several subcontracts for the execution of various elements of the enclosure and finish work.

II. The Arbitration.

In the summer of 1979, while the phase III and phase IV work was in progress, dispute arose among the parties involving claims of design error, construction mismanagement, and violations of the phase III and phase IV general contracts. In *382 September of 1979, F/D/C and WDC each independently initiated arbitration against the city. The city responded with arbitration demands against WDC, F/D/C and Granger, and their sureties, St. Paul and USF & G. After arbitration commenced, F/D/C notified the city in writing that it was terminating performance under the phase IV contract because of the city’s alleged breach of contract. 4 The city subsequently negotiated change orders directly with the phase IV subcontractors for completion of the phase IV work.

The various demands for arbitration may be summarized (in an overly simplified manner) as follows: As to phase HI, the city claimed that Granger had violated the contract in several specific respects, and that WDC had failed to supervise adequately the construction of the project and had failed to provide proper design plans and specifications. WDC claimed that the city’s actions had prevented it from properly supervising and managing the project. As to phase IV, F/D/C claimed that the city had committed a breach of contract by failing to deliver the site to it on time with phase III work completed and by failing to grant F/D/C an extension of time to complete its work (made late by alleged phase III delinquencies) with an appropriate price adjustment. The city claimed, in turn, that F/D/C was in breach of its contract and was responsible, among other things, for extra costs and damages incurred by the city in renegotiating the phase IV subcontracts. The American Arbitration Association consolidated the parties’ numerous claims and demands for relief into a single proceeding which was conducted before a panel of three specialized arbitrators. Evidence was thereafter received by the arbitrators over a period of 186 days. The evidence resulted in more than 31,000 pages of transcript. 5

*383 The arbitrator’s award found that Granger, the phase III general contractor, and its surety, USF & G, were liable to the city in the amount of $2,253,182.01. The award further determined that WDC was not liable to the city for design failures or for construction of the project, and that F/D/C was not liable to the city in connection with its performance under the phase IV contract. Finally, the award found that the city was liable to F/D/C, the phase IV general contractor, in the amount of $275,596.49. In addition, the arbitrators ordered the city to indemnify F/D/C against pending court claims and arbitration proceedings which had been brought against F/D/C by the phase IV subcontractors. The city moved in the Superior Court to vacate or modify certain portions of the award and to confirm other portions. WDC, F/D/C, and St. Paul filed cross motions to confirm the award in its entirety. (Granger and USF & G entered an agreement for judgment for the city confirming the award as to those claims). A Superior Court judge allowed the motions to confirm the award and denied the city’s motion to vacate or modify the award. The city took a timely appeal and on appeal contests the validity of paragraphs 3 and 5 of the award.

III. The Paragraph 3 Issues.

Paragraph 3 of the award states that the city had failed to prove “that it was injured by any design failures for which the other parties, or any of them, might be liable, including any injury occasioned by any third party for whose acts any of the parties named might be liable, specifically including Ellerbe, Inc.” (emphasis supplied).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sun Fire Protection & Engineering, Inc. v. D.F. Pray, Inc.
899 N.E.2d 114 (Massachusetts Appeals Court, 2009)
City of Lynn v. Lynn Police Ass'n
899 N.E.2d 106 (Massachusetts Appeals Court, 2009)
Perseus of N.E., MA, Inc. v. Commonwealth
706 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1999)
TLT Construction Corp. v. Anthony Tappe & Associates, Inc.
6 Mass. L. Rptr. 202 (Massachusetts Superior Court, 1996)
Barletta v. French
607 N.E.2d 410 (Massachusetts Appeals Court, 1993)
JBC of Wyoming Corp. v. City of Cheyenne
843 P.2d 1190 (Wyoming Supreme Court, 1992)
E. I. Constructors, Inc. v. Dahman, No. Cv-90 29 84 79 (Jul. 20, 1990)
1990 Conn. Super. Ct. 290 (Connecticut Superior Court, 1990)
Findlen v. Winchendon Housing Authority
553 N.E.2d 554 (Massachusetts Appeals Court, 1990)
David Co. v. Jim W. Miller Construction, Inc.
444 N.W.2d 836 (Supreme Court of Minnesota, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
474 N.E.2d 1151, 19 Mass. App. Ct. 379, 1985 Mass. App. LEXIS 1556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-worcester-v-granger-bros-massappct-1985.