Wes-Julian Construction Corp. v. Commonwealth

223 N.E.2d 72, 351 Mass. 588, 1967 Mass. LEXIS 897
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 10, 1967
StatusPublished
Cited by15 cases

This text of 223 N.E.2d 72 (Wes-Julian Construction Corp. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wes-Julian Construction Corp. v. Commonwealth, 223 N.E.2d 72, 351 Mass. 588, 1967 Mass. LEXIS 897 (Mass. 1967).

Opinion

Spiegel, J.

This is a petition brought under G. L. e. 258 against the Commonwealth in which the petitioner seeks damages allegedly sustained for breach of a written contract for the construction of a section of the Southeast Expressway. The claims of the petitioner are for extra work, increased costs, and expense, totaling $276,745.66. The case was referred to an auditor whose findings of fact were not to be final. He found for the petitioner with respect to *590 some of its claims. At a trial before a judge without jury the evidence consisted of the auditor’s report, numerous exhibits, and the testimony of witnesses. The judge found for the petitioner and assessed damages in the sum of $271,911.66 plus an item of interest which was “to be added to the total amount of the finding.” The case is here on exceptions by the respondent to the judge’s “denying its requests for rulings and in making certain findings and assessment of damages.”

We summarize the material findings of the judge. The contract provided that the work was to conform to the 1953 Standard Specifications for Highways and Bridges (the Blue Book). The total amount to be paid for the work specified was $4,111,998. “[W]ark was to be completed March 31, 1959, with an extension of time to June 1, 1959. Work . . . was started May 4,1956 . . . and completed on May 29, 1959.” On June 16, 1959, the Commissioners of Public Works voted to approve, as of May 29, 1959, the work done by the petitioner under the contract, “the engineer in charge having reported that . . . [the] work called for under . . . [the] contract had been completed .... At various times during and toward the end of the construction work and after its completion the officers of petitioner discussed various claims for extra pay arising from the performance of the contract with representatives of the Commonwealth, and were informed that the Commissioners were not in a position to settle them, and that the petitioner should correlate . . . [its] data, submit it as a claim and bring suit. ’ ’

The auditor made “ [c]ertain findings of fact” with reference to several items of increased costs totaling $13,685.67. The respondent “admitted” these items.

The petitioner claims there is due it the sum of $146,371.95 for additional borrow 1 of a type more expensive than that specified in the contract. “ [T]wo types of borrow were *591 specified in . . . the contract to be used above and below . . . [a certain] elevation. One kind consisted of material of which not more than 10 per cent would pass through a 200 mesh sieve to be used below elevation 8 2 and was the better of the two types with a fair market value of $1.75 a cubic yard. The other . . . was material of which not more than 35 per cent would pass through a 200 mesh sieve to be used above elevation 8 with a fair market value of $1.30 per cubic yard. ... On or about December 11,1956, the petitioner was stopped from using 35 per cent borrow . . . [by the respondent’s resident engineer]. 3 . . . Some of this material went below elevation 8 but sometime in April, 1957, petitioner was instructed by . . . [the resident engineer] to use only borrow which would pass the ten per cent test, and from this date to' the completion of the contract, substantially all of the borrow was of this latter grade. The contract . . . provided that borrow . . . in peat excavation areas (underwater backfill) to elevation + 8.00 by the dry fill method shall contain not more than 10 per cent by dry weight of material passing the No. 200 mesh sieve and that all other borrow . . . for embankment from elevation + 8.00 to the top of the subgrades shall contain not more than 35 per cent by dry weight of material passing the 200 mesh sieve. The bid of the petitioner, which became a part of the contract, included the delivery of 895,000 cubic yards of ordinary borrow complete in place at a combined price of . . . $1.60 a cubic yard . . . [for] a total price of $1,432,000.00 to be paid for the amount agreed to be supplied. The petitioner delivered and was paid for the 895,000 cubic yards at the above price and also delivered and received the same price for an additional 80,813 cubic yards, making a total of 975,813 cubic yards delivered and paid for at the same price ($1.60). The rela *592 tive ratio of the borrow specified in the contract of 895,000 yards was two parts below elevation . . . and one part above .... [The petitioner’s] engineer testified that 9,711 cubic yards of borrow did not meet the 10 per cent test, and that he was ‘uncertain’ about an additional 17,009 cubic yards. Deducting these from 975,813 cubic yards leaves a total of 949,093 cubic yards for which the petitioner makes claim at 15 cents per cubic yard, or a total amount of $142,363.95.”

Between June 18, 1956, and January 3, 1959, the petitioner had “various . . . installations . . . stakes and . . . platforms” built within the “contract right of way” and was obligated to keep and maintain all of these in good working order during the entire period of construction. “The respondent allowed the Dorchester Yacht Club to erect and maintain its buildings within the contract easement work area so that the petitioner was compelled to hire an additional watchman to police the area for the entire construction period ... [at a cost] of $11,289.04. . . . The contract . . . provided that all iron castings would be . . . [furnished] by the respondent to the petitioner on . . . [its] trucks at the Norfolk State Prison without cost. Petitioner was repeatedly assured over a period of many months that . . . [the] castings would be available at . . . [the] prison when needed and was dissuaded from purchasing them during . . . period. In the interim there were three successive . . . increases in the market price .... [Finally] the petitioner was . . . informed that they would not be available at . . . [the] prison and that they would have to be purchased by the petitioner on the open market. This resulted in an increased cost of $1,657.65 to the petitioner.”

The contract was executed on March 27, 1956, and under its terms the petitioner was to commence its work within fifteen days from that date. The contract had the following specific provision: “Temporary and permanent changes of tracks and telegraph lines of the Railroad made necessary by or to clear, permanent work of the Contractor, will *593 be made by the Railroad without expense to the Contractor.” It “further provided for the construction of a temporary bridge and the removal of the entire existing superstructure then in place over the N.Y., N.H. & H. R.R. tracks at Savin Hill Avenue.”

It was not until October 3,1956, that the respondent “ enter [ed] into a contract with the N.Y., N.H. & H. R.R. . . . and did not compel the commencement of the removal and relocation of the railroad tracks . . . [and so forth] until on or about . . . [May 10, 1957] . . . and failed to compel the completion of . . . [the] work before seventeen months.” The respondent failed to include a completion date in its contract with the railroad and did not undertake any court action to compel the railroad to complete its work in a reasonable time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Jim Walsh Plumbing Co. v. Cresta Construction, Inc.
3 Mass. L. Rptr. 29 (Massachusetts Superior Court, 1994)
Findlen v. Winchendon Housing Authority
553 N.E.2d 554 (Massachusetts Appeals Court, 1990)
B. J. Harland Electrical Co. v. Granger Bros.
510 N.E.2d 765 (Massachusetts Appeals Court, 1987)
Joseph E. Bennett Co. v. Commonwealth
486 N.E.2d 1145 (Massachusetts Appeals Court, 1985)
City of Worcester v. Granger Bros.
474 N.E.2d 1151 (Massachusetts Appeals Court, 1985)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
St. Germain & Son, Inc. v. Taunton Redevelopment Authority
340 N.E.2d 916 (Massachusetts Appeals Court, 1976)
Alpert v. Commonwealth
258 N.E.2d 755 (Massachusetts Supreme Judicial Court, 1970)
Farina Bros. v. Commonwealth
257 N.E.2d 450 (Massachusetts Supreme Judicial Court, 1970)
State Line Contractors, Inc. v. Commonwealth
249 N.E.2d 619 (Massachusetts Supreme Judicial Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
223 N.E.2d 72, 351 Mass. 588, 1967 Mass. LEXIS 897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wes-julian-construction-corp-v-commonwealth-mass-1967.