St. Germain & Son, Inc. v. Taunton Redevelopment Authority

340 N.E.2d 916, 4 Mass. App. Ct. 46, 1976 Mass. App. LEXIS 689
CourtMassachusetts Appeals Court
DecidedJanuary 29, 1976
StatusPublished
Cited by12 cases

This text of 340 N.E.2d 916 (St. Germain & Son, Inc. v. Taunton Redevelopment Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. Germain & Son, Inc. v. Taunton Redevelopment Authority, 340 N.E.2d 916, 4 Mass. App. Ct. 46, 1976 Mass. App. LEXIS 689 (Mass. Ct. App. 1976).

Opinion

Hale, C.J.

The plaintiff, St. Germain & Son, Inc. (contractor), brought an action of contract against the defendant, Taunton Redevelopment Authority (Authority). The plaintiff’s declaration contained three counts labeled (1) breach of contract, (2) quantum meruit, and (3) action on a written contract, respectively. 1 The action was tried before a jury in the Superior Court, and the jury returned a verdict in the sum of $20,000 on count 3. The contractor appealed after verdicts were returned by the jury on counts 1 and 2 by direction of the court; the Authority cross appealed after a jury verdict on count 3, contending that its motion for a directed verdict was improperly denied. 2

The plaintiff is a Massachusetts corporation engaged in the general contracting and demolition business in the city of Taunton. The Authority is a public body created under the laws of the Commonwealth to promote urban redevelopment. The contractor entered into a written agreement with the Authority for the demolition of various structures in Taunton for a total price of $56,560. The contract, which was prepared by the Authority, required that the contractor complete its work by January 31, 1969. There were provisions in the contract specifying liquidated dam *48 ages of $50 for each day of delay by the contractor and allowing for extensions of time for delays caused by the Authority.

The contract specified that the contractor should not demolish any structure until it had received written notice to proceed. From time to time, the Authority gave such notice with respect to various buildings, and the contractor demolished them as agreed. However, not all the work was completed by January 31, 1969, due to the failure of the Authority to release various structures. The Authority had been delayed by difficulties in acquiring possession of some of the property and problems concerning relocation of certain tenants. There was evidence introduced to show that, at the time of the execution of the contract, the Authority did not own all of the buildings covered by the contract. Most of the remaining work was performed in 1969, but not all of it was completed until May, 1972.

On November 3, 1970, the plaintiff wrote to the Authority pursuant to the contract, seeking an upward revision in the contract price to reflect increases in labor and equipment costs. The testimony is in dispute as to the type of response by the Authority (the contract calls for a written reply), but it is clear that no increase was granted to the plaintiff. In order to recover the cost increases occasioned by the delay, the plaintiff entered the instant action on June 4,1973.

1. In the absence of a specific contract provision to the contrary, a party to a contract may recover damages caused by delay in the commencement or completion of performance if it can be shown that the delay was a breach of that contract. Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. 495, 499-500 (1939). Wes-Julian Constr. Corp. v. Commonwealth, 351 Mass. 588, 594 (1967). However, if the contract contains a provision relieving the Authority of liability, it will be enforced, and actions for damages will be precluded. Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. at 504. We are faced with the question whether the contract contains a provision which relieves the Authority from liability for delay.

*49 The Authority argues that section 402 3 of the contract expressly limits the Authority’s liability for delays to the obligation of granting appropriate extensions to the contractor. Section 402 is entitled “Time of Completion,” and subparagraph “a” bears the title “Limit of the Authority’s Liability.” However, we find nothing in the text of this subparagraph which would bar the present action. The text simply states that the contractor shall be granted an extension of time if it is prevented from performing within the specified time due to failure of the Authority to release a building for demolition. Nowhere is it stated that the contractor is denied the right to recover for damages caused by delay. The text and not the title is controlling. A title may be considered when construing the text, but the scope of the text cannot be expanded by the title. Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. at 501.

A contract is to be construed to give reasonable meaning to each of its provisions. McMahon v. Monarch Life Ins. Co. 345 Mass. 261, 264 (1962). Section 402 need not be construed so as to exculpate the Authority from all liability due to delay. Section 402 is given its clearest and most reasonable meaning when it is construed so as to grant extensions to the contractor for delays caused by the Authority. Its purpose is to prevent the application of the liquidated damages provision of the contract against the contractor when the delay is caused by the Authority itself.

The agreement in question is a lengthy, complicated one containing numerous detailed provisions. A clause depriving the contractor of a claim for damages arising out of delay would be of extreme importance to both the contractor and the Authority. It it had been the intention of the parties to preclude such a claim, the contract could have *50 specifically stated such a prohibition. This court will not read such a provision into an already detailed contract.

There have been numerous cases which have upheld contract provisions depriving the contractor of a claim for damages arising out of delay. See Charles I. Hosmer, Inc. v. Commonwealth, 302 Mass. 495 (1939); Coleman Bros. Corp. v. Commonwealth, 307 Mass. 205 (1940); Charles T. Main, Inc. v. Massachusetts Turnpike Authy. 347 Mass. 154 (1964); Wes-Julian Constr. Corp. v. Commonwealth, 351 Mass. 588 (1967). It should be noted that the contracts in those cases both gave the contractor the right to extensions in cases of delay and specifically prohibited claims for damages caused by delay. For example, the contract in the Wes-Julian case provided in part “[the contractor] shall have no claim for damages on account of such delay, but shall be entitled to an equivalent extension of time in which to complete ... the work____” 351 Mass. at 594. Because the contract in the instant case does not specifically preclude such actions for damages, the present action is not barred by the contract.

2. The Authority excepted to the denial of its motion for a directed verdict on count 3 (action on a written contract) . Since we have determined that the present action is not barred by the terms of the contract, we must now decide whether there was any provision of the contract under which the contractor could recover on count 3.

The contractor’s claim for recovery of increased costs due to delay is based on sections 107 and 108 of the contract which are set forth in relevant part in the margin.

Related

XL Specialty Insurance v. Massachusetts Highway Department
31 Mass. L. Rptr. 147 (Massachusetts Superior Court, 2013)
Perroncello v. Donahue
835 N.E.2d 256 (Massachusetts Appeals Court, 2005)
780 L.L.C. v. DiPrima
611 N.W.2d 637 (Nebraska Court of Appeals, 2000)
Dominic Gentile Painting Co. v. Aulson Co.
2000 Mass. App. Div. 19 (Mass. Dist. Ct., App. Div., 2000)
Findlen v. Winchendon Housing Authority
553 N.E.2d 554 (Massachusetts Appeals Court, 1990)
Lipson v. Adelson
456 N.E.2d 470 (Massachusetts Appeals Court, 1983)
Hillman v. Slater
434 N.E.2d 679 (Massachusetts Appeals Court, 1982)
Frank Construction Corp. v. Republic Powdered Metals, Inc.
417 N.E.2d 38 (Massachusetts Appeals Court, 1981)
Newburyport Redevelopment Authority v. Commonwealth
401 N.E.2d 118 (Massachusetts Appeals Court, 1980)
John F. Miller Co. v. George Fichera Construction Corp.
388 N.E.2d 1201 (Massachusetts Appeals Court, 1979)
Poskus v. Braemoor Nursing Home, Inc.
377 N.E.2d 705 (Massachusetts Appeals Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
340 N.E.2d 916, 4 Mass. App. Ct. 46, 1976 Mass. App. LEXIS 689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-germain-son-inc-v-taunton-redevelopment-authority-massappct-1976.