Coleman Bros. v. Commonwealth

29 N.E.2d 832, 307 Mass. 205, 1940 Mass. LEXIS 1028
CourtMassachusetts Supreme Judicial Court
DecidedNovember 1, 1940
StatusPublished
Cited by23 cases

This text of 29 N.E.2d 832 (Coleman Bros. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coleman Bros. v. Commonwealth, 29 N.E.2d 832, 307 Mass. 205, 1940 Mass. LEXIS 1028 (Mass. 1940).

Opinion

Dolan, J.

This is a petition brought under G. L. (Ter. Ed.) c. 258, § 1, in which the petitioner seeks to recover amounts claimed to be due for work performed, and for damages occasioned by delay in connection with a contract entered into between the petitioner and the Commonwealth, acting by its metropolitan district commission, for the construction of the 'Wellington Bridge across the Mystic River, between the cities of Somerville and Medford. The claims of the petitioner are three, each of which is subdivided into several items. The first and second claims, in which recovery is sought for work performed, were referred to an auditor whose findings of fact were agreed to be final; and, subsequently, the third class of claims, for damages for delay alleged to have been caused by the respondent, was referred to another auditor, whose findings of fact were not agreed to be final. See G. L. (Ter. Ed.) c. 258, § 2; Arthur A. Johnson Corp. v. Commonwealth, 306 Mass. 347, 349.

The case was heard by the judge upon the auditors’ reports only. The judge found for the petitioner on claims one and two in the amount of $11,460.21, and for the respondent on claim three, and filed the following “Rulings on Petitioner’s Requests”; “On the first and second claims the findings of fact by the auditor are final. Have made my finding by applying to said facts the law which I believe is applicable. The requests of the petitioner which are in[207]*207consistent with this finding are denied.1 On the third claim the findings of fact by the auditor are not final. No additional evidence, however, was offered. On the facts found by the auditor and the reasonable inferences therefrom I rule that the delay was not due to the arbitrar)'', capricious or wanton conduct of the respondent, its agent or agents. [We treat this as a finding.] In so far as the requests under the third claim are inconsistent with this ruling they are denied.” The petitioner properly saved its exceptions to the rulings and refusals to rule on its requests, as above set forth, and thereafter duly claimed an appeal from the decision of the judge and filed a bill of exceptions relating to the rulings on its third claim. Thereafter, on December 21, 1939, the respondent filed an offer of judgment (G. L. [Ter. Ed.] c. 258, § 2) for the sum of $11,460.21. Subsequently the parties entered into a stipulation that the petitioner is entitled to recover $11,460.21 and costs, and that the only controversy existing between them is whether, in addition to that sum, the petitioner is entitled to recover $22,000 for cofferdams under item one of its first claim, $615.55 for “Boston Pattern Fence” under item five of its first claim, $1,234.70 for “extra pile costs” under item seven of its second claim, and for damages for delays under its third claim. The judge then reported the case to this court “for the determination of all questions of law open to the petitioner on . . . [the] record.”

We first consider claims one and two. Since the findings of fact of the auditor constituted a case stated, the petitioner’s appeal from the order of the judge, that judgment be entered for the petitioner in the sum of $11,460.21, brings before us all questions of law raised by the case stated and involved in the decision. Pesce v. Brecher, 302 Mass. 211, 212, and cases cited. Nutter v. Mroczka, 303 Mass. 343, 347. G. L. (Ter. Ed.) c. 231, § 96. Yoffa v. Shaw, 299 Mass. 516, 517.

[208]*208Claim one. Item one. The claim for a balance of $22,000 alleged to be due on cofferdams.

The contract provided that “The bridge is to be built in two sections and so constructed that traffic will be maintained at all times.” The plan adopted was to tear down and remove the downstream sidewalk and about five feet in width of the downstream roadway and then to build the downstream half of the new bridge. When that was done and open for traffic, the rest of the old bridge was torn down and replaced by new construction which constituted the upstream half of the new bridge. Embankments and abutments were thrust out from both sides of the river toward the center of the river. Between the abutments the bridge was to be supported by thirteen granite piers set in the bed of the river. The building of these piers required the construction of cofferdams to keep the water out while the workmen were excavating, driving piles, pouring the concrete footings for the piers, and erecting the piers themselves.

The thirteen granite piers were given numbers by the parties; number one being the first out from the abutment at the Somerville end of the bridge, and number thirteen being nearest to the abutment at the Medford end. The draw hinged on pier seven. There is no claim as to piers seven and eight. The petitioner has been paid for eleven other cofferdams, but contends that, since it built one cofferdam around the downstream half of each of the eleven piers, and after the upstream half of the old bridge was removed, it built eleven more —■ one around each upstream half of the eleven piers — it should be paid in addition for the latter. The respondent contends that the contract called for but eleven complete cofferdams, in addition to those required for the construction of piers seven and eight.

The subject of cofferdams is referred to in several places in the contract. Item 22 of the contract is as follows: “Cofferdam for pier 7, complete in place, the lump sum of $12,000.” Item 23 (cofferdam for pier eight) is identical in its terms with item 22 except for price. Item 24 reads: “Cofferdams for piers 5, 6, 9 and 10, complete in place, the [209]*209sum of $2,000.00 each”; under the heading “Approximate Quantities” appears the figure “4,” and under the heading “Computed Totals” appear the figures “8,000.00.” Provisions for the cofferdams for piers seven and eight (not in controversy but of assistance in construing the contract) are in part that “The cofferdam for the draw pier is to be built in such a manner as to allow one half of the draw pier to be built at a time and all cofferdam work required to complete the entire draw pier built in sections shall be considered as one cofferdam. . . . Basis of payment. The amount of work done under this item will be paid for by a lump sum for each cofferdam, complete in place . . . .” Pertinent provisions of the contract applying to cofferdams for the other piers are these: “On piers numbered 5, 6, 9 and 10, as designated on the plans, or on other piers as the engineer may direct, wood sheeting cofferdams are to be built to the established lines and grades.” The auditor found that the engineer directed that piers one, two, three, four, eleven, twelve and thirteen be encased in cofferdams in accordance with this part of the contract. The question raised as to this item of claim one is what the words “pier” and “cofferdams” as used in the contract mean.

A reading of item 24 set forth above would seem to make it clear that there was to be but one cofferdam for each pier. The petitioner does not contend that the word “pier” as used in item 24 means half piers such as were constructed at the downstream end of the bridge and then completed in the construction of the other half of the bridge. But even if it be assumed in favor of the petitioner that portions of the contract dealing with the erection of cofferdams are ambiguous, it cannot prevail. ^

Where there is an ambiguous term in a contract parol evidence is admissible to explain the meaning intended by the parties. Kennedy Bros. Inc. v. Bird, 287 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clerico v. Great Road Floors, Inc.
10 Mass. L. Rptr. 678 (Massachusetts Superior Court, 1999)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Findlen v. Winchendon Housing Authority
553 N.E.2d 554 (Massachusetts Appeals Court, 1990)
B. J. Harland Electrical Co. v. Granger Bros.
510 N.E.2d 765 (Massachusetts Appeals Court, 1987)
City of Houston v. R. F. Ball Construction Co.
570 S.W.2d 75 (Court of Appeals of Texas, 1978)
Alden Plumbing & Heating, Inc. v. Brini
59 Mass. App. Dec. 1 (Mass. Dist. Ct., App. Div., 1976)
St. Germain & Son, Inc. v. Taunton Redevelopment Authority
340 N.E.2d 916 (Massachusetts Appeals Court, 1976)
Casino Operations, Inc. v. Graham
476 P.2d 953 (Nevada Supreme Court, 1970)
Western Engineers, Inc. v. State Ex Rel. Road Commission
437 P.2d 216 (Utah Supreme Court, 1968)
Malden Door & Window Co. v. Goss
38 Mass. App. Dec. 53 (Mass. Dist. Ct., App. Div., 1967)
Wes-Julian Construction Corp. v. Commonwealth
223 N.E.2d 72 (Massachusetts Supreme Judicial Court, 1967)
Chas. T. Main, Inc. v. Massachusetts Turnpike Authority
196 N.E.2d 821 (Massachusetts Supreme Judicial Court, 1964)
Maine v. Burnett
179 N.E.2d 903 (Massachusetts Supreme Judicial Court, 1962)
Holland v. Crummer Corporation
368 P.2d 63 (Nevada Supreme Court, 1962)
M. DeMatteo Construction Co. v. Commonwealth
156 N.E.2d 659 (Massachusetts Supreme Judicial Court, 1959)
Cetrone v. Paul Livoli, Inc.
150 N.E.2d 732 (Massachusetts Supreme Judicial Court, 1958)
A. Kaplen & Son, Ltd. v. Housing Authority of Passaic
126 A.2d 13 (New Jersey Superior Court App Division, 1956)
Psaty & Fuhrman, Inc. v. Housing Authority
68 A.2d 32 (Supreme Court of Rhode Island, 1949)
City of Boston v. Commonwealth
76 N.E.2d 121 (Massachusetts Supreme Judicial Court, 1947)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
29 N.E.2d 832, 307 Mass. 205, 1940 Mass. LEXIS 1028, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coleman-bros-v-commonwealth-mass-1940.