Psaty & Fuhrman, Inc. v. Housing Authority

68 A.2d 32, 76 R.I. 87, 10 A.L.R. 2d 789, 1949 R.I. LEXIS 84
CourtSupreme Court of Rhode Island
DecidedAugust 16, 1949
StatusPublished
Cited by55 cases

This text of 68 A.2d 32 (Psaty & Fuhrman, Inc. v. Housing Authority) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Psaty & Fuhrman, Inc. v. Housing Authority, 68 A.2d 32, 76 R.I. 87, 10 A.L.R. 2d 789, 1949 R.I. LEXIS 84 (R.I. 1949).

Opinion

*89 Capotosto, J.

These are cross actions in assumpsit which were tried together in the superior court without a jury. Hereinafter Psaty & Fuhrman, Inc., a New York corporation, will be referred to as the contractor, and The Housing Authority of the City of Providence, Rhode Island, a public body organized under the laws of this state, as the Authority. The trial justice rendered a decision for the plaintiff contractor in the sum of $88,921.21, which included $10,921.67 as interest from the date of its writ, and for the plaintiff Authority in the sum of $75,600. Only the contractor has duly prosecuted a bill of exceptions in each case, thus bringing before us its exceptions to the decision of the superior court 'sustaining the Authority’s demurrer to counts 3, 4 and 5 of its declaration, to the above-mentioned decisions of the trial justice, and to numerous rulings on evidence during the trial.

The matters in dispute stem from a written contract for the construction of Roger Williams Homes in the city of Providence, an extensive low rent housing development carried out with federal aid. The project, which covered an area of about twenty-two acres, involved the demolition of some 190 existing buildings and the substitution therefor of 28 multiple dwellings with a total of 744 units, together with a power plant and an administration building.

The Authority advertised for bids and the contractor was the successful bidder. On June 23, 1941 the parties entered *90 into a contract whereby the contractor undertook to carry out its terms for the sum of $2,620,000 in accordance with the specifications, drawings and addenda designated “Specification For Construction U.S.H.A. — Aided Development R.I. 1-2 Roger Williams Homes Providence, R. I.”

The following provisions of the contract are important. “Article 2. Time Of Completion: The Contractor shall commence work under this contract on a date to be specified in a written order of the Local Authority and shall fully complete all work thereunder within the number of consecutive calendar days enumerated in Section 14 of Instructions to Bidders.” That section requires that the construction work be completed in 300 days from the date of said order, and that work on lawns and planting be completed in 200 additional days thereafter.

Article 4, entitled Liquidated Damages, provides: “As actual damages for delay in completion are impossible of determination, the Contractor and his sureties shall be liable for and shall pay to the Local Authority the sum stated in Section 15 of Instructions to Bidders, as fixed, agreed and liquidated damages for each calendar day of delay (not beyond the control of the Contractor) until the work is completed or accepted.” Section 15 of the instructions fixes such damages at $250 a day as to the construction work and $25 a day as to the landscaping.

The following provision, hereinafter called the “no damage” clause, appears in paragraph 12 of the general conditions: “No payment or compensation of any kind shall be made to the Contractor for damages because of hindrance or delay from any cause in the progress of the work, whether such delays be avoidable or unavoidable.” The contractor could, however, obtain an extension of time upon certain conditions not necessary to mention here.

A brief reference to the pleadings in the two cases is necessary. The declaration in the contractor’s case originally consisted of eight special counts. Counts 1, 2, 6, 7 and 8 are framed on the theory that the Authority in bad, *91 faith hindered or delayed the contractor in its work and ultimately refused to pay the balance of the contract price. Counts 3, 4 and 5 allege in substance that the Authority unreasonably hindered or delayed the contractor in its performance of the contract. The Authority demurred to the three counts last mentioned on the ground that it was not liable for mere delay. Resting his decision squarely on the no damage clause of the contract, the trial justice sustained the demurrer holding that the contractor was not entitled to recover for any delay or hindrance caused by the Authority “except those caused by fraud, in bad faith, or with malicious intent to cause damage.” Thereafter the contractor amended count 5 by alleging that the Authority acted with fraudulent intent. The contractor’s case finally went to trial on the Authority’s plea of the general issue to counts 1, 2, 5, 6, 7 and 8 as above summarized.

The declaration in the case of the Authority is in three counts. Count 1 alleges nonperformance of the contract; count 2 alleges omitted, unfinished or defective work and makes specific claim for liquidated damages for delay; and count 3 contains the common counts. The contractor pleaded the general issue to all three counts and also filed special pleas to counts 1 and 2, which pleas in effect admitted the delays but excused them on the ground that they were due to the actions of the Authority or to governmental interference, or to causes beyond its control. This case went to trial on the issues thus drawn.

The contractor’s first exception is to the decision of the trial justice sustaining the demurrer to counts 3, 4 and 5 of its declaration. Under this exception it contends that it was entitled to recover damages for delay caused by the arbitrary or unreasonable conduct of the Authority. In other words, its contention is that the no damage clause of the contract did not mean that it could recover only for such delays and hindrances that were due to fraud, bad faith or malicious intent on the part of the Authority, as the trial justice ruled in sustaining the demurrer.

*92 The contractor apparently realizes that the no damage clause is of serious import and therefore seeks to minimize its force and effect by giving it practically no meaning. Although it refers to that clause, it argues its contention in connection therewith as if it were nonexistent. No useful purpose will be served by the contractor’s reliance in the circumstances on general propositions of law which, conceding their soundness in the ordinary case, do not control the fundamental question at issue here. There is no doubt that ordinarily if one exacts a promise from another to perform an act the law implies a counter promise against arbitrary or unreasonable conduct on the part of the promisee. The following cases, among others, upon which the contractor relies plainly and properly support such view: Marcaccio, Inc. v. Santurri, 51 R. I. 440; Danforth & Armstrong v. Tennessee & Coosa R. R., 93 Ala. 614; People ex rel. v. Craig, 232 N. Y. 125; Rogers v. United States, 99 Ct. Cl. 393. But these cases are clearly distinguishable in their facts from the instant cases.

The no damage clause in this contract expressly states that the contractor shall not recover damages because of hindrance or delay from any cause in the progress of the work “whether such delays be avoidable or unavoidable.” The language of this provision, though broad in scope, is not ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bennett v. Steliga
Supreme Court of Rhode Island, 2024
MacOmb Mechanical Inc v. Lasalle Group Inc
Michigan Court of Appeals, 2015
Empire Merch. Corp. v. Bancorp R.I.
Superior Court of Rhode Island, 2011
Papudesu v. Medical Malpractice Joint Underwriting Ass'n
18 A.3d 495 (Supreme Court of Rhode Island, 2011)
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
Tidewater Realty, LLC v. State
Superior Court of Rhode Island, 2010
Sovereign Bank v. Fowlkes
Superior Court of Rhode Island, 2010
Depasquale Bldgs. v. Bd. of Governors
Superior Court of Rhode Island, 2009
Airfreight Express Ltd. v. Evergreen Air Center, Inc.
158 P.3d 232 (Court of Appeals of Arizona, 2007)
Town of Narragansett v. Palmisciano
Superior Court of Rhode Island, 2006
Gorman v. Gorman
883 A.2d 732 (Supreme Court of Rhode Island, 2005)
Baris v. Steinlage, 99-1302 (2003)
Superior Court of Rhode Island, 2003
Hord Corp. v. Polymer Research Corp. of America
275 F. Supp. 2d 229 (D. Rhode Island, 2003)
PRIDE HYUNDAL, INC. v. Chrysler Financial Co., LLC
263 F. Supp. 2d 374 (D. Rhode Island, 2003)
Bradford Dyeing Assoc. v. J. Stog Tech GmbH
765 A.2d 1226 (Supreme Court of Rhode Island, 2001)
Clauson v. New England Insurance
83 F. Supp. 2d 278 (D. Rhode Island, 2000)
Ross-Simons of Warwick, Inc. v. Baccarat, Inc.
66 F. Supp. 2d 317 (D. Rhode Island, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
68 A.2d 32, 76 R.I. 87, 10 A.L.R. 2d 789, 1949 R.I. LEXIS 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/psaty-fuhrman-inc-v-housing-authority-ri-1949.