MacOmb Mechanical Inc v. Lasalle Group Inc

CourtMichigan Court of Appeals
DecidedApril 23, 2015
Docket319357
StatusUnpublished

This text of MacOmb Mechanical Inc v. Lasalle Group Inc (MacOmb Mechanical Inc v. Lasalle Group Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MacOmb Mechanical Inc v. Lasalle Group Inc, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

MACOMB MECHANICAL, INC., UNPUBLISHED April 23, 2015 Plaintiff-Appellant,

v No. 319357 Wayne Circuit Court LASALLE GROUP, INC. and TRAVELERS LC No. 11-013403-CK CASUALTY AND SURETY COMPANY OF AMERICA,

Defendants-Appellees.

Before: TALBOT, C.J., and MURPHY and GLEICHER, JJ.

PER CURIAM.

The circuit court summarily dismissed a plumbing subcontractor’s lawsuit against a general contractor for payment of various costs, some arising under and others going beyond the scope of the subcontract. The circuit court inaccurately interpreted and incorrectly applied various provisions of the subcontract and therefore failed to recognize that plaintiff created several genuine issues of material fact. We therefore affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.

I. BACKGROUND

This contractual dispute arises out of the construction of a dining facility at Fort Sill in Oklahoma. The United States Army Corps of Engineers (USACE) owns the project. The USACE contracted with Veterans Enterprise Technology Services, L.L.C. (VETS) to act as the prime contractor on the project. VETS subcontracted its general contracting duties to LaSalle Group, Inc. LaSalle, in turn, employed several sub-subcontractors, including Macomb Mechanical, Inc., which agreed to provide plumbing and mechanical work for the sum of $270,000. Macomb alleged that its work “was originally scheduled to be about 6 months,” but that “unforeseen and differing site conditions” extended Macomb’s work to 15 months.1 Macomb further asserted that the project scope changed after entering its sub-subcontract, but

1 In some lower court documents, Macomb asserts that it ultimately spent 16 months working on the project.

-1- that LaSalle refused to sign change orders necessary to secure Macomb’s proper payment. When LaSalle failed to pay Macomb the entirety of its requested compensation, Macomb filed this breach of contract action against LaSalle and sought payment under a surety bond issued by Travelers Casualty and Surety Company of America.

The circuit court summarily dismissed Macomb’s claims based on two categories of the parties’ sub-subcontract. First, Article 5.4 encompasses a broad “no damages for delay” clause: “In no event shall Subcontractor be entitled to claim nor shall Subcontractor be compensated for any delays, or any claims for acceleration, inefficiency, interruption, interference or the like.”

Second, the circuit court relied upon a series of articles comprising “pay if paid” clauses:

2.1 Subject to approval by Contractor, and approval as required by the Subcontract Documents, Contractor will pay Subcontractor monthly progress payments provided as a condition precedent that Owner has paid Contractor. . . .

***

2.7 Contractor will use Owner funds to pay Subcontractor within ten (10) days after receipt and Contractor shall have no obligation to pay Subcontractor for the Subcontract work, or any claims related thereto, unless and until Owner pays Contractor for the same. Receipt of funds by payment from Owner for specific payment to the subcontractor, shall be a condition precedent to Contractor’s obligation to pay Subcontractor.

2.8 [Directions to Subcontractor for providing documentation for final payment.]

2.9 Upon satisfactory compliance with 2.8 above, Contractor shall incorporate Subcontractor’s final payment application into Contractor’s application to Owner, Conditioned upon precedent payment by Owner, Contractor will pay to Subcontractor the final payment for the Subcontract work within ten (10) days after receipt thereof from the Owner. . . .

5.5 Subcontractor shall not be entitled to any increase in the Subcontract price or extension of the time unless the amount of any such increase and time extension has been agreed upon in writing, accepted by Owner . . . as provided in the Subcontract Documents, and as a condition precedent, paid by Owner to Contractor . . . .

The circuit court also summarily denied Macomb’s claims against the surety bond, concluding that the bond’s liability was coextensive with the bond holder. The court then awarded LaSalle and Travelers attorney fees as the prevailing parties. This appeal followed.

-2- II. STANDARD OF REVIEW

We review “de novo a trial court’s decision on a motion for summary disposition.” Hackel v Macomb Co Comm, 298 Mich App 311, 315; 826 NW2d 753 (2012). The circuit court relied upon materials beyond the pleadings in considering the motions, and summary disposition was thereby granted pursuant to MCR 2.116(C)(10). See Spiek v Dep’t of Transp, 456 Mich 331, 338 n 9; 572 NW2d 201 (1998) (even if summary disposition is granted under the wrong rule, this Court may review the order under the correct rule). “In reviewing a motion under MCR 2.116(C)(10), this Court considers the pleadings, admissions, affidavits, and other relevant documentary evidence of record in the light most favorable to the nonmoving party to determine whether any genuine issue of material fact exists to warrant a trial.” Walsh v Taylor, 263 Mich App 618, 621; 689 NW2d 506 (2004). “Summary disposition is appropriate if there is no genuine issue regarding any material fact and the moving party is entitled to judgment as a matter of law.” Latham v Barton Malow Co, 480 Mich 105, 111; 746 NW2d 868 (2008). “A genuine issue of material fact exists when the record, giving the benefit of reasonable doubt to the opposing party, leaves open an issue upon which reasonable minds might differ.” West v Gen Motors Corp, 469 Mich 177, 183; 665 NW2d 468 (2003).

The proper interpretation of a contract is a question of law that we also review de novo. Klapp v United Ins Group Agency, Inc, 468 Mich 459, 468; 663 NW2d 447 (2003).

In interpreting a contract, it is a court’s obligation to determine the intent of the parties by examining the language of the contract according to its plain and ordinary meaning. If the contractual language is unambiguous, courts must interpret and enforce the contract as written, because an unambiguous contract reflects the parties’ intent as a matter of law. However, if the contractual language is ambiguous, extrinsic evidence can be presented to determine the intent of the parties. [In re Smith Trust, 480 Mich 19, 24; 745 NW2d 754 (2008) (citations omitted).]

III. “NO DAMAGES FOR DELAY” CLAUSE

Macomb challenges the circuit court’s dismissal of its claim to payments for costs arising because of project delay. Macomb sought $347,786 in delay-related costs. Macomb contends that the “no damages for delay” clause in the sub-subcontract is unenforceable because the delay in this case was not of a type contemplated by the contracting parties. Macomb asserts that LaSalle refused to permit Macomb to leave the project site during a partial stop-work period, failed to properly manage the project, and directed Macomb to submit delay damages to pass through to the project owner. Macomb further avers that the alleged increase in performance time from six to 15 months could not reasonably have been anticipated when Macomb prepared its bid. According to Macomb, LaSalle’s conduct and the duration of the delay supports the conclusion that the “no damages for delay” clause does not preclude relief.

As noted, Article 5.4 of the sub-subcontract provides, in relevant part: “In no event shall Subcontractor be entitled to claim nor shall Subcontractor be compensated for any delays, or any claims for acceleration, inefficiency, interruption, interference or the like.” This contractual language unambiguously provides that Macomb may not recover damages for delays,

-3- acceleration, inefficiency, interruption, or interference.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Latham v. Barton Malow Co.
746 N.W.2d 868 (Michigan Supreme Court, 2008)
In Re EGBERT R SMITH TRUST
745 N.W.2d 754 (Michigan Supreme Court, 2008)
West v. General Motors Corp.
665 N.W.2d 468 (Michigan Supreme Court, 2003)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
Spiek v. Department of Transportation
572 N.W.2d 201 (Michigan Supreme Court, 1998)
Western Engineers, Inc. v. State Ex Rel. Road Commission
437 P.2d 216 (Utah Supreme Court, 1968)
James Corp. v. North Allegheny School District
938 A.2d 474 (Commonwealth Court of Pennsylvania, 2007)
Edwin J. Dobson, Jr., Inc. v. State
526 A.2d 1150 (New Jersey Superior Court App Division, 1987)
Houghton v. Keller
662 N.W.2d 854 (Michigan Court of Appeals, 2003)
Cunningham Brothers, Inc. v. City of Waterloo
117 N.W.2d 46 (Supreme Court of Iowa, 1962)
Smith v. Department of Treasury
414 N.W.2d 374 (Michigan Court of Appeals, 1987)
Phoenix Contractors, Inc. v. General Motors Corp.
355 N.W.2d 673 (Michigan Court of Appeals, 1984)
Barber v. Smh (Us), Inc
509 N.W.2d 791 (Michigan Court of Appeals, 1993)
Mehling v. Evening News Ass'n
132 N.W.2d 25 (Michigan Supreme Court, 1965)
Morris Pumps v. Centerline Piping, Inc.
729 N.W.2d 898 (Michigan Court of Appeals, 2007)
Berkel & Co. Contractors v. Christman Co.
533 N.W.2d 838 (Michigan Court of Appeals, 1995)
Will H Hall & Son, Inc v. Ace Masonry Construction, Inc
677 N.W.2d 51 (Michigan Court of Appeals, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
MacOmb Mechanical Inc v. Lasalle Group Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/macomb-mechanical-inc-v-lasalle-group-inc-michctapp-2015.