Cunningham Brothers, Inc. v. City of Waterloo

117 N.W.2d 46, 254 Iowa 659, 1962 Iowa Sup. LEXIS 651
CourtSupreme Court of Iowa
DecidedSeptember 18, 1962
Docket50601
StatusPublished
Cited by14 cases

This text of 117 N.W.2d 46 (Cunningham Brothers, Inc. v. City of Waterloo) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cunningham Brothers, Inc. v. City of Waterloo, 117 N.W.2d 46, 254 Iowa 659, 1962 Iowa Sup. LEXIS 651 (iowa 1962).

Opinion

Hays, J.

— Plaintiff contracted with defendant for the construction of two parking ramps. One located on the east side of the City and one on the west side, referred to as the East Ramp and the West Ramp. The contract was for the lump sum of $1,024,000. The Ramps were completed in June 1958 and the contract price together with the cost for certain extra work has been paid by the defendant.

In this action plaintiff seeks recovery for expense incurred for sheetpiling work in connection with the West Ramp; and for *661 additional expense in providing heat for both Ramps, made necessary by alleged delays in the construction work by defendant. Upon completion of the testimony a motion for a directed verdict, as to each item claimed by plaintiff, was overruled and a jury returned a verdict for plaintiff upon each item. Thereafter, defendant’s motion for judgment notwithstanding the verdict was sustained as to each claimed item, as they applied to the West Ramp, and overruled as to the item claimed for the Bast Ramp. Defendant has appealed and plaintiff filed a cross-appeal.

I. We will first consider defendant’s appeal which is concerned only with the Bast Ramp. The basic issue involves a so-called “no damage” clause appearing in the contract.

The contract, by reference, includes the various documents upon which plaintiff’s bid ivas based. We call attention to various provisions of the contract, and other included documents, which have a bearing upon the matter.

Par. 1, Instructions to Bidders, requests all bidders to examine the plans and specifications, site of construction, Notice to Contractors, form of Proposal and Form of Contract, and if there is any doubt as to the meaning of any part thereof, to have the same fully explained before making a proposal.

Par. 18, Section A, General Specifications, Contract Period, includes the beginning date to the completion date unless the period is extended, in which event the contract includes the new date of completion.

Par. 8, Section B, General Specifications, states that the City shall provide the lands upon which the work under the contract is to be done.

Par. 10, Section B, General Specifications, states that when work being carried on by the City or other contractors is contiguous to work covered by this contract, the rights of such various interests are to be established by the City engineer.

Par. 3, Section C, General Specifications, authorizes the engineer to stop work when necessary to insure proper execution of the contract.

Par. 9, Section C, General Specifications, provides that the *662 contractor shall provide and pay for all facilities necessary for execution of the contract.

Par. 1, Section D, General Specifications, requires the contractor to complete any portion of the work in such order as the engineer may direct.

Par. 4, Section D, General Specifications, provides "If ■the contractor be delayed in the completion of the work by an act of neglect of the City or its employees; or by any other contractor employed by the City; * * * or by strikes, lockouts, fire, # * * unavoidable casualties, or any cause beyond the contractor’s control; * * or by any cause which the engineer shall decide justifies the delay, then the time of completion shall be extended * * * as the engineer may decide will compensate for such delay.” (Italics ours.)

Par. 5, Section D, General Specifications, authorizes the engineer to suspend the work, wholly or in part, for such periods of time as he may deem necessary, due to unsuitable weather or other conditions.

Par. 1, Section 1, Detailed Specifications, provides that the contractor shall be responsible for any damage to any part of the work or to any adjacent structures by failure of the Avails of the excavation.

Par. F, Special ProAdsions, states: In the event that temporary heat is required for the protection of the Avork during any period of construction, it shall be the responsibility of the General Contractor to proAdde the heat required.

Par. 2, Contract, requires contractor to furnish at its own cost and expense all necessary materials and labor for said work.

Par. 5, Contract, states the work shall start May 1, 1957, and be completed November 30, 1957, unless an extension of time is granted.

Par. 11, Contract, provides: “The Second Party [contractor] shall have no right of action against first party [City] on account of delays in prosecution of work, but if said work is delayed by first party, second party shall have such extra time for the completion of the job as was lost by reason of the delay caused by first party.” (Italics supplied.)

Par. 18, Contract, states: “This contract is not divisible, *663 but in the event of a conflict between this contract and the various instruments incorporated by reference, this contract shall govern.”

II. The facts so far as material: Plaintiff was ready to start work May 1, 1957. The premises, at the time of contracting, contained buildings which were to be demolished, which work was done by an independent contractor. Plaintiff commenced work on West Ramp, May 13, 1957, at which time the demolition crew had finished on that ramp. June 6, 1957, a wall adjacent to construction site collapsed killing two of plaintiff’s workmen. Apparently due to this accident, plaintiff examined the Bast Ramp where buildings were to be demolished and some buildings stood adjacent to the building site. Plaintiff refused to start work on Bast site until it was certified safe by an independent engineer. Two different engineers examined it and made reports. Certain precautions were suggested to stabilize adjacent buildings, which work was done by an independent contractor presumably at the defendant’s expense. Not until July 29, 1957, did plaintiff commence work at the Bast site, when the demolition crew had completed its work. It appears without dispute that for some time prior to that date, the demolition contractor ivas working at one end of the site and plaintiff could have commenced work without any interference thereto on account thereof. This was suggested by the engineer for the defendant and refused by plaintiff. Plaintiff’s position was that an agreement to provide a .site requires that such site be cleared and made safe in the judgment of the plaintiff, i.e., that no other contractor be working thereon. How much time elapsed because of plaintiff’s position does not appear. There is evidence that had plaintiff started Avork on May 1, 1957, the starting time under the contract, it could have been finished by November 30, 1957, as per contract. Plaintiff requested and received two extensions of time in which to complete the work. It is clear that plaintiff was at considerable expense in furnishing heat for winter work made necessary by the delays in starting work. .

III. Defendant relies upon Par. 11 of the contract, supra, as a defense to this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MacOmb Mechanical Inc v. Lasalle Group Inc
Michigan Court of Appeals, 2015
Tricon Kent Co. v. Lafarge North America, Inc.
186 P.3d 155 (Colorado Court of Appeals, 2008)
H. PEPPER & ASSOC., INC. v. Hardrives Co., Inc.
528 So. 2d 72 (District Court of Appeal of Florida, 1988)
Clinton Federal Savings & Loan Ass'n v. Iowa-Des Moines Natioanal Bank
391 N.W.2d 712 (Court of Appeals of Iowa, 1986)
Owen Construction Co. v. Iowa State Department of Transportation
274 N.W.2d 304 (Supreme Court of Iowa, 1979)
City of Houston v. R. F. Ball Construction Co.
570 S.W.2d 75 (Court of Appeals of Texas, 1978)
McIntire v. Green-Tree Communities, Inc.
318 So. 2d 197 (District Court of Appeal of Florida, 1975)
Kolls v. Aetna Casualty and Surety Company
378 F. Supp. 392 (S.D. Iowa, 1974)
Southern Gulf Utilities, Inc. v. Boca Ciega Sanitary District
238 So. 2d 458 (District Court of Appeal of Florida, 1970)
Western Engineers, Inc. v. State Ex Rel. Road Commission
437 P.2d 216 (Utah Supreme Court, 1968)
Hallett Construction Co. v. Iowa State Highway Commission
154 N.W.2d 71 (Supreme Court of Iowa, 1967)
Brecht v. Cedar Rapids Development Co.
136 N.W.2d 287 (Supreme Court of Iowa, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
117 N.W.2d 46, 254 Iowa 659, 1962 Iowa Sup. LEXIS 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cunningham-brothers-inc-v-city-of-waterloo-iowa-1962.