Guerini Stone Co. v. P. J. Carlin Construction Co.

248 U.S. 334, 39 S. Ct. 102, 63 L. Ed. 275, 1919 U.S. LEXIS 2317
CourtSupreme Court of the United States
DecidedJanuary 7, 1919
Docket218
StatusPublished
Cited by94 cases

This text of 248 U.S. 334 (Guerini Stone Co. v. P. J. Carlin Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guerini Stone Co. v. P. J. Carlin Construction Co., 248 U.S. 334, 39 S. Ct. 102, 63 L. Ed. 275, 1919 U.S. LEXIS 2317 (1919).

Opinion

Mr. Justice Pitney

delivered the opinion of the court.

This case is before us for the second time, our former decision béing reported in 240 U. S. 264. It was an action for damagés, brought by the present petitioner as plaintiff against the présent respondent as defendant in the District Court of the United States for Porto Rico. Our first review was upon a direct writ of error sued out by plainiiff under § 244, Judicial Code (Act of March 3, 1911, c. 231, 36 Stat. 1087, 1157), prior to the amendment of'January 28, 1915 (c. 22, 38 Stat. 804, §§ 3 & 6). Judgment was reversed and the cause remanded for further proceedings. Upon the going down of the mandate a new trial was had, resulting in a verdict in plaintiff’s favor *337 for substantial damages. To review the judgment entered thereon, defendant, under the Act of 1915, prosecuted a writ of error from the Circuit Court of Appeals for the First Circuit, setting up assignments of error based upon rulings of the trial court in admitting and excluding evidence and in giving and refusing instructions to the jury. The Court of Appeals reversed the judgment and ordered thé cause to be remanded for further proceedings, 241 Fed. Rep. 545; and to review this judgment the present writ of certiorari was allowed, 245 U. S. 643.

The controversy arose in the course of . the construction of a federal post office and court building at San Juan, Porto Rico. Plaintiff had a sub-contract for a part of the work under defendant, which was the general contractor under the Government of the United States, Pertinent clauses of the contract and a general history of the case were set forth in our former opinion and need not be repeated at length.

The evidence at the second trial followed the general lines of the first. Defendant was to construct the foundation complete to the basement floor. Upon this, plaintiff was to construct the principal part of the building, including exterior and interior walls, floors, and roof, to be built of concrete. For this work and the necessary mate- . rials defendant agreed to pay to plaintiff the sum of $64,750 in certain monthly instalments on account and the balance on completion. The plans called for certain granite work, for which defendant was to send the cut blocks from the-United States; and under an option set forth in paragraph 25, afterwards accepted by defendant, plaintiff was to set this granite for 40 cents per square foot of surface.

It appeared that after the work had been in progress for some time a disagreement arose between the parties about payments on account.-. Paragraph 12 of the contract provided that there should be “monthly payments on *338 account, not to exceed in amount 85 per cent, of the cost of the work actually erected in the building, provided that the sub-contractor furnishes to the general contractors a written requisition, on a form to be supplied by the general. contractors, not less than twelve days before payment is required,” etc. The contract, however, did not provide how such cost of the work, other than the granite setting, should be ascertained. In December, 1911, and January, 1912, plaintiff made written requisitions which were not complied with; and, according to plaintiff’s evidence, it was agreed between the parties on or about February 2, 1912, that future applications and payments should be made upon the basis of a schedule which specified, inter alia, “Exterior and interior concrete walls, arches, and cement work $1.07 per cubic foot.” On March 9,1912, plaintiff made a requisition for payment computed oii this basis, and showing a balance-due of $11,735.95. This requisition was in effect refused, and.no further payment > was made except the sum of $674, which was paid a few days later.

In the month of February, 1912, the government superintendent of construction found a serious settlement in the foundation, as a result of which work upon the building was ordered to be stopped. This order was communicated verbally by defendant’s representative to . plaintiff’s agent at San Juan on the 9th of March, and was confirmed two days later by letter, in which, however, a request made by plaintiff’s agent for instructions as to what should be done with plaintiff’s force of men pending the suspension of the work was evaded. Plaintiff stopped work pursuant to defendant’s notice, and did nothing more upon the building.

Thus matters remained until May 22, 1912, plaintiff in the meantime having received no payment pursuant to its requisition of March 9 beyond the small sum mentioned above, nor any instructions or permission to pro *339 ceed with the work upon the building; and, according to plaintiff’s evidence, it was impossible to tell when the work could proceed. On May 22 plaintiff wrote to the defendant referring to the stoppage of the work and to “the very considerable cost and damage to us caused by your breach of contract,” to the inability to get payments from defendant in accordance with the terms of the contract, and to defendant’s refusal of an offer of arbitration and refusal of “an assurance that even now we would have ' an opportunity within any reasonable time to proceed with our work,” and concluding with this notification: “Under these circumstances and owing to your entire failure to comply with the terms of the contract, we hereby notify you that we now terminate the contract and shall proceed no further with the work, and that we shall hold you liable for the damages we have sustained by reason of your breach of contract, including your failure to provide labor and materials not included in the contract with us in such manner as not to delay the material progress of our work and your failure to make payments in accordance with the terms of the contract, and all other breaches of contract on your part.”

The principal ground of action was based upon the contention that in refusing to respond to plaintiff’s requisitions for payments on account, and in the complete and indefinite stoppage of plaintiff’s work under the circumstances mentioned, defendant had committed breaches of the contract so material as to amount to a total breach, justifying plaintiff in declining to proceed further and in suing at once for its damages. See Anvil Mining Co. v. Humble, 153 U. S. 540, 552. But as we pointed out in 240 U. S. 283, plaintiff counted also upon a quantum meruit for work and labor performed and materials furnished in and about the construction of the building.

The Circuit Court of Appeals attributed error to the trial court in the following respects:

*340

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flagship West, LLC v. Excel Realty Partners, L.P.
758 F. Supp. 2d 1004 (E.D. California, 2010)
In Re Regional Building Systems, Inc.
273 B.R. 423 (D. Maryland, 2001)
Gm Testani Construction Co. v. Delcegno, No. Cv-92-0291747s (Oct. 25, 1994)
1994 Conn. Super. Ct. 10872 (Connecticut Superior Court, 1994)
Piccolo v. Kapetan, No. Cv88 24 99 09 (Aug. 1, 1991)
1991 Conn. Super. Ct. 7371 (Connecticut Superior Court, 1991)
Statler Manufacturing, Inc. v. Brown
691 S.W.2d 445 (Missouri Court of Appeals, 1985)
Village of Cairo v. Bodine Contracting Co.
685 S.W.2d 253 (Missouri Court of Appeals, 1985)
Silliman Co. v. S. Ippolito & Sons, Inc.
467 A.2d 1249 (Connecticut Appellate Court, 1983)
Tennessee Asphalt Co. v. Purcell Enterprises, Inc.
631 S.W.2d 439 (Court of Appeals of Tennessee, 1982)
Chrysler Corp. v. Airtemp Corp.
426 A.2d 845 (Superior Court of Delaware, 1980)
Michel & Pfeffer v. Oceanside Properties, Inc.
61 Cal. App. 3d 433 (California Court of Appeal, 1976)
Hartford Electric Applicators of Thermalux, Inc. v. Alden
363 A.2d 135 (Supreme Court of Connecticut, 1975)
Argonaut Insurance Company v. United States
434 F.2d 1362 (Third Circuit, 1970)
Pittman Const. Co. v. Housing Auth. of New Orleans
169 So. 2d 122 (Louisiana Court of Appeal, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
248 U.S. 334, 39 S. Ct. 102, 63 L. Ed. 275, 1919 U.S. LEXIS 2317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guerini-stone-co-v-p-j-carlin-construction-co-scotus-1919.