Piccolo v. Kapetan, No. Cv88 24 99 09 (Aug. 1, 1991)

1991 Conn. Super. Ct. 7371
CourtConnecticut Superior Court
DecidedAugust 1, 1991
DocketNo. CV88 24 99 09 CV88 24 99 08
StatusUnpublished

This text of 1991 Conn. Super. Ct. 7371 (Piccolo v. Kapetan, No. Cv88 24 99 09 (Aug. 1, 1991)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piccolo v. Kapetan, No. Cv88 24 99 09 (Aug. 1, 1991), 1991 Conn. Super. Ct. 7371 (Colo. Ct. App. 1991).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The two above entitled cases have previously been consolidated for trial. The plaintiff in each action pleads in the alternative and claims judgment and damages in the amount of $29,874.45, together with interest from February 20, 1987. The claims are for labor and materials furnished by the plaintiffs to the defendant pursuant to a contractual agreement or that the reasonable value of said labor and materials furnished was $29,874.45, or that the defendant, Kapetan, Inc. as principal and the defendant Travelers Indemnity Company as surety are jointly and severally liable under two bonds which were substituted in lieu of a mechanic's lien previously filed by each of the plaintiffs.

The defendant, Kapetan Inc. filed answers to each complaint denying the material allegations contained therein. In the Piccolo, d/b/a P C Fence Company claim the defendant filed special defenses alleging the failure of P C to perform the work in accordance with said contract, the mutual termination of the contract, the failure of P C to timely file a mechanic's lien, and the waiver by P C of its right to file a mechanic's lien. The defendant Kapetan, Inc. filed special defenses in the Ayala Construction Company claim alleging that the plaintiff did not provide services and materials in accordance with its agreement, that Ayala failed to execute a written contract as required by the agreement and that Ayala waived its right to file a mechanic's lien.

The defendant, Kapetan, Inc., filed a counterclaim against both P C and Ayala alleging damages because of the failure of each plaintiff to complete the work as agreed. Kapetan alleged it expended money in excess of the contract to complete said CT Page 7372 work and further incurred damages by reason of substituting a bond in lieu of the mechanic's liens as filed by each of the two plaintiffs.

Both complaints arise from the following factual situation. The plaintiff, John R. Piccolo d/b/a P C Fence Company, entered into a written agreement dated March 14, 1986 with Kapetan, Inc. to provide materials and labor as required in the installation of fencing and guard rails as delineated in Exhibit A of said contract. Kapetan, Inc. was installing same as the general contractor for Westfield Properties, owner of the Trumbull Shopping Park. The contract price was $56,500.00 with unit prices set forth for additional fencing, guard rails and gates. The parties agreed to several change orders during the course of the contract. Plaintiff commenced work in October 1986 and continued until late December 1986 or early January 1987 when Ronald Nobili, business manager of the Laborer's Union complained to Kapetan that P C Fence Company was performing work on this project with non-union labor. Kapetan had entered a previous agreement with the labor union which required that all of its sub-contractors in fact use union labor. On January 8, 1987, Peter Kapetan, John Piccolo and Robert Testo, Jr., general manager of Ayala Construction Company, met and informally agreed that the work would be completed by Ayala Construction Company employing union labor, that Ayala would enter a new contract with Kapetan in accordance with which Kapetan would pay Ayala an additional nine dollars per hour for union labor which was the then current wage differential between union and non-union labor, that Ayala would complete the work and receive the balance due P C on their contract. It was further contemplated that Ayala would then reimburse P C for all materials and labor supplied to date. Kapetan, Inc. sent Ayala a contract which was never executed by and between the parties.

Ayala Construction installed fencing and guard rail on the subject premises from about January 12, 1987 through February 15, 1987 using union labor. At this time Ronald Nobili, business manager of the Laborer's Union, again appeared on the job site and claimed that Ayala was merely the alter-ego for P C Fence Company which was a non-union employer. Ayala continued work from February 16, 1987 through February 22, 1987 using union labor provided by Kapetan. Inc. to install P C Fence Company's material under P C supervision. However, Ronald Nobili's actions and protest did not go unheeded and Ayala's attorney soon advised that Ayala could not perform further work on this job.

On or about February 25, 1987, Keith Langston representing Ayala met with Vito LaVacca. Project Manager for Kapetan, Inc., CT Page 7373 and discussed how much work had been done to date and how much money Kapetan owed to Ayala and or P C Fence Company. At or shortly after this February 25, 1987 meeting, Mr. LaVacca prepared defendant's exhibits M and N. On March 25, 1987 the defendant forwarded a check to the plaintiff in the amount of $14,615.61. After receipt of this check the plaintiffs were still claiming that there was a balance owed in the amount of $29,874.69 and were demanding payment of same in accordance with a Mailgram sent to defendant on April 16, 1987. (P's Ex. 9).

Paragraph II of the March 14, 1986 contract between P C and Kapetan provided that work and materials accepted will be paid for at the rate of 90% of value on the 20th of the next month, 10% balance to be paid upon completion. (P's Ex. 1)

Defendant's Exhibit N prepared by Vito LaVacca indicates that plaintiffs were and had been entitled to at least 90% of another $14,615.60 which was due and owed at this time. Plaintiffs claim they were entitled to 90% of at least an additional $29,874.69 at this juncture.

Thereafter, correspondence was exchanged between the parties with plaintiffs demanding immediate payment and defendant demanding plaintiffs resume and complete the job using union employees. On April 14, 1987 Kapetan ordered plaintiffs to commence completion of the work using union labor or Kapetan would complete the work with another contractor. Plaintiffs requested defendant provide the union labor in which case P C would provide materials and supervision and further demanded payment for the work completed to date, all as set forth in plaintiff's Mailgram of April 16, 1987.

Defendant notified plaintiff by letter of April 28, 1987 that "we have proceeded with the work with another contractor and referred to paragraph X of the March 14, 1986 agreement." However, defendant Peter Kapetan admitted as set forth in plaintiff's post trial memorandum that said paragraph X was "applicable to jurisdictional disputes between subcontractors over which craft was entitled to perform work and that the objection of the Laborers Union to a non-union subcontractor was not a jurisdictional dispute," and therefore paragraph X was in no way applicable to this matter.

Defendant hired Westport Fence Company and completed the job with Kapetan labor. On May 18, 1987 each plaintiff filed a mechanic's lien against the defendant Kapetan, Inc. in the amount of $29,874.25. The parties agree that the original contract price was $56,500.00 but unfortunately can agree on little else. They do not agree on the amounts of materials furnished, the number of lineal feet of each item required by the CT Page 7374 contract, the price per lineal foot to be paid for said items, the number of hours of labor performed and whether certain items are "extras" or included in the original contract.

The court has carefully considered all of the evidence presented by the opposing parties, plaintiffs' Exhibits 1 through 14 and defendant's exhibits A through MM. The following witnesses appeared and testified: John Piccolo, plaintiff and owner of P C Fence Company since 1972, Robert J. Testo. Jr., former general estimator for P C and incorporator of Ayala Construction Company, Vito J. LaVacca, project manager for Kapetan Construction, Peter M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guerini Stone Co. v. P. J. Carlin Construction Co.
248 U.S. 334 (Supreme Court, 1919)
Story Parchment Co. v. Paterson Parchment Paper Co.
282 U.S. 555 (Supreme Court, 1931)
Southern Construction Co. v. Pickard
371 U.S. 57 (Supreme Court, 1962)
Collins v. Sears, Roebuck & Co.
321 A.2d 444 (Supreme Court of Connecticut, 1973)
Gilman v. Pedersen
438 A.2d 780 (Supreme Court of Connecticut, 1981)
Morici v. Jarvie
75 A.2d 47 (Supreme Court of Connecticut, 1950)
Keyes v. Brown
232 A.2d 486 (Supreme Court of Connecticut, 1967)
Martin v. Kavanewsky
255 A.2d 619 (Supreme Court of Connecticut, 1969)
Southern New England Contracting Co. v. State
345 A.2d 550 (Supreme Court of Connecticut, 1974)
Silliman Co. v. S. Ippolito & Sons, Inc.
467 A.2d 1249 (Connecticut Appellate Court, 1983)
Bartolotta v. Calvo
152 A. 306 (Supreme Court of Connecticut, 1930)
Valente v. Weinberg
67 A. 369 (Supreme Court of Connecticut, 1907)
McCleave v. John J. Flanagan Co.
160 A. 305 (Supreme Court of Connecticut, 1932)
Lee v. Harris
82 A. 186 (Supreme Court of Connecticut, 1912)
Edward DeV. Tompkins, Inc. v. City of Bridgeport
110 A. 183 (Supreme Court of Connecticut, 1920)
Walter Kidde Constructors, Inc. v. State
434 A.2d 962 (Connecticut Superior Court, 1981)
Lavigne v. Lavigne
488 A.2d 1290 (Connecticut Appellate Court, 1985)
Pero Building Co. v. Smith
504 A.2d 524 (Connecticut Appellate Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
1991 Conn. Super. Ct. 7371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piccolo-v-kapetan-no-cv88-24-99-09-aug-1-1991-connsuperct-1991.