Valente v. Weinberg

67 A. 369, 80 Conn. 134, 1907 Conn. LEXIS 22
CourtSupreme Court of Connecticut
DecidedJuly 30, 1907
StatusPublished
Cited by41 cases

This text of 67 A. 369 (Valente v. Weinberg) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valente v. Weinberg, 67 A. 369, 80 Conn. 134, 1907 Conn. LEXIS 22 (Colo. 1907).

Opinion

Thayer, J.

The plaintiff and defendant entered into two contracts for the erection of a brick apartment house by the former upon the land of the latter. The second contract provided merely for additions to and changes in the earlier one, and we may refer to them as one contract. The plaintiff claims that after he had nearly completed the building the defendant unlawfully ejected him from the premises and prevented his completion of the contract. He sues to recover the value of the labor and materials) which he had furnished before he was ejected. The de- ' fendant admits that he ejected the plaintiff and terminated his employment under the contract, but claims to have done so pursuant to article five of the contract, and by his answer and counterclaim seeks to recover from the plaintiff the amount which the defendant has paid to another person to complete the building.

If the plaintiff, without fault on his part, was prevented by the defendant from completing the contract, he could treat it as rescinded and recover, quantum meruit, for the work and labor performed under it, or he could bring his action for damages against the defendant for breaking the contract and preventing the plaintiff’s performance of it. Derby v. Johnson, 21 Vt. 17, 21; Wright v. Haskell, 45 Me. 489, 492; United States v. Behan, 110 U. S. 338, 344, 4 Sup. Ct. Rep. 81; Chicago v. Tilley, 103 U. S. 146, 154; Connelly v. Devoe, 37 Conn. 570, 576. If, on the other hand, the plaintiff failed to perform his contract and the defendant rightfully entered and completed it, acting under the terms of the contract, the plaintiff cannot recover. The case turns, therefore, upon the question whether the defendant rightfully entered and ejected the plaintiff.

*136 Article V of the contract reads as follows : “ Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect, or failure being certified by the architects, the owner shall be at liberty after three days’ written notice to the contractor to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architects shall certify that such refusal, neglect, or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work, and to enter upon the premises and take possession, for the ptirpose of completing the work included under this contract, of all materials, tools, and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor, he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the wnpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor; but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner, as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architects, whose certificate thereof shall be conclusive upon the parties.”

This article contemplates that there may be a neglect or failure on the part of the plaintiff of such a character as not to constitute a sufficient ground for terminating his employment, and it also contemplates that there may *137 Tbe such negligence or failure on his part as to constitute such ground and to warrant such procedure. In the former case one form of certificate by the architects and one course of proceeding by the defendant is provided for, while a different certificate and a different proceeding is provided for in the latter case. The plaintiff’s negligence or failure might be of such a character as not to warrant either proceeding. Of this the architects were to be the judges, and to justify the defendant in taking either proceeding, and especially the harsh one of terminating the plaintiff’s employment, taking his tools and materials and turning the completion of the contract over to a third party beyond the plaintiff’s control but at his expense, the provisions of article five, strictly construed, should he strictly pursued. Wilson v. Borden, 68 N. J. L. 627, 629, 54 Atl. 815; Champlain Const. Co. v. O'Brien, 104 Fed. Rep. 930, 933; Spencer v. Duplan Silk Co., 112 Fed. Rep. 638, 641. The article provides, as a condition precedent to the defendant’s right to terminate the plaintiff’s employment, that the architects shall certify not only that there has been a refusal, neglect, or failure on the part of the plaintiff of the kind mentioned, but also that such refusal, neglect, or failure is a sufficient ground for such action. On two occasions the architects, at the defendant’s urgent solicitation, wrote him as follows : “We hereby certify that in our opinion Pasquale Valente, contractor on your new building on College Street, neglects to supply a sufficiency of properly skilled workmen and materials, and fails in every respect to prosecute the work with promptness and diligence, and we hereby certify that you have sufficient cause to proceed as provided in Article V of his contract.” The two certificates were alike, except that the first, dated March 7th, 1905, was accompanied by a list of materials necessary to be put in to complete the work, and an enumeration of' some defective work. The defendant notified the plaintiff of this certificate and the latter began to remedy the defects. On the 28th of March the defendant procured the second certificate, and at once notified the *138 plaintiff to vacate the building and premises. The certificates do not state that the architects are of opinion that the defendant has cause to proceed, under the second part of article fifth of the contract, to terminate the plaintiff’s employment, nor do they state that the neglect and failure of the plaintiff constitute a sufficient ground for terminating it. We think, as already indicated, that such a certificate, in strict compliance with the terms of article five, was essential, and that the defendant in proceeding to eject the plaintiff and prevent his performance of his contract without such certificate acted wrongfully. The plaintiff, therefore, is entitled to recover for the services and materials furnished in the construction of the building.

The court correctly overruled the defendant’s claim that, if the plaintiff was entitled to recover, “ the measure of damages is that adopted in Pinches v. Church, 55 Conn. 183, 10 Atl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Department of Transportation v. White Oak Corp.
946 A.2d 1219 (Supreme Court of Connecticut, 2008)
Butera v. Boucher
798 A.2d 340 (Supreme Court of Rhode Island, 2002)
Phil Lodovico v. Tabacco Sons Builders, No. Cv98-0491995s (May 17, 2000)
2000 Conn. Super. Ct. 6584 (Connecticut Superior Court, 2000)
Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000)
2000 Conn. Super. Ct. 2393 (Connecticut Superior Court, 2000)
Brewer Construction v. Fg Assoc., No. Cv92 050 78 85 (Jun. 21, 1993)
1993 Conn. Super. Ct. 6077 (Connecticut Superior Court, 1993)
Piccolo v. Kapetan, No. Cv88 24 99 09 (Aug. 1, 1991)
1991 Conn. Super. Ct. 7371 (Connecticut Superior Court, 1991)
Donofrio v. Foley, No. Cv87 004 67 74 (Aug. 28, 1990)
1990 Conn. Super. Ct. 1214 (Connecticut Superior Court, 1990)
Metcalfe v. Talarski
567 A.2d 1148 (Supreme Court of Connecticut, 1989)
Duksa v. City of Middletown
472 A.2d 1 (Supreme Court of Connecticut, 1984)
Paul Hardeman, Inc. v. Arkansas Power & Light Company
380 F. Supp. 298 (E.D. Arkansas, 1974)
Martin v. Kavanewsky
255 A.2d 619 (Supreme Court of Connecticut, 1969)
Acme Process Equipment Co. v. United States
171 Ct. Cl. 324 (Court of Claims, 1965)
Acme Process Equipment Co. v. United States
347 F.2d 509 (First Circuit, 1965)
Thornton v. Arlington Independent School District
332 S.W.2d 395 (Court of Appeals of Texas, 1960)
Greco v. Morcaldi
146 A.2d 589 (Supreme Court of Connecticut, 1958)
Oden Const. Co. v. HELTON
65 So. 2d 442 (Mississippi Supreme Court, 1953)
Morici v. Jarvie
75 A.2d 47 (Supreme Court of Connecticut, 1950)
Cone v. Pedersen
40 A.2d 274 (Supreme Court of Connecticut, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
67 A. 369, 80 Conn. 134, 1907 Conn. LEXIS 22, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valente-v-weinberg-conn-1907.