Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000)

2000 Conn. Super. Ct. 2393
CourtConnecticut Superior Court
DecidedFebruary 22, 2000
DocketNo. CV 99-00551690
StatusUnpublished

This text of 2000 Conn. Super. Ct. 2393 (Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000), 2000 Conn. Super. Ct. 2393 (Colo. Ct. App. 2000).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION
The parties contest an arbitrators' award. The plaintiff, Carlin Contracting Co., Inc. (Carlin), brought this action to vacate the award. The defendant, Blakeslee Arpaia Chapman, Inc. (B-A-C), has moved for confirmation of the award. Both parties rely on statutes each deems applicable. C.G.S. §§ 52-418 and52-420 (Carlin) and C.G.S. § 52-417 (B-A-C).

Carlin contracted with the Water Pollution Control Authority of the City of Bridgeport to do certain rehabilitation work on the East Side Wastewater Treatment Plant. As general contractor, Carlin subcontracted B-A-C to do certain of the work called for in the Bridgeport-Carlin general contract. This Carlin — B-A-C subcontract is dated March 10, 1997. According to the subcontract, B-A-C was to do certain excavation and piling work.

Regarding arbitration, the subcontract provided:

"Disputes arising out of Owner acts, omissions or responsibilities shall be resolved in accordance with the disputes procedures in the Prime Contract. Subcontractor shall have the right to exercise those rights at its sole cost and shall be bound thereby. Contractor shall have not direct liability except to give Subcontractor opportunity to exercise its rights under the Prime Contract. Where the claim in dispute includes more than just this Subcontractor's work, Contractor shall reasonably pursue the claim including Subcontractor's portion and subcontractor shall have full responsibility for preparation and presentation of its elements of the claim and shall bear all expenses thereof including attorneys' fees allocable to its portion of the claim. Subcontractor shall not be entitled to receive any greater amount from Contractor than contractor receives from the Owner on account of Subcontractor's work, less costs and/or legal fees incurred by Contractor in pursuing the claim and markups to which Contractor is entitled; and, CT Page 2395 Subcontractor shall accept such amount, if any, received by Contractor from Owner as full satisfaction and discharge of its elements of claim. Disputes solely with Contractor shall be resolved by arbitration in Waterford, Connecticut in accordance with the rules of the American Arbitration Association. Disputes shall not interfere with the progress of the job. Work shall proceed as ordered, subject to claim." [Italics added.]

On January 20, 1998, B-A-C filed a demand for arbitration as "A PARTY TO A WRITTEN AGREEMENT DATED ___3/10/97___ PROVIDING FOR ARBITRATION . . . . B-A-C described the nature of the dispute as "Non-payment under terms of construction contract." B-A-C stated the amount of its claim was $250,000.00. B-A-C informed it estimated the time needed overall for hearings was 4 days.

Arbitrators were selected. Ten days of hearing were held over the period October 5, 1998 to March 4, 1999. On June 18, 1999, the arbitrators rendered an award. The key provision states:

"On the claim of Blakelee Arpaia Chapman, Inc. (Claimant) against Carlin Contractors, Inc. (Respondent), We award Claimant the sum of $407,006.00 plus interest of $62,489.34, plus attorneys fees of $68,900 to be paid by Respondent." Award of Arbitrators, Exhibit I to Complaint (Application To Vacate Arbitration Award And For Order To Show Cause, July 20, 1999.[101]

The threshold, and practically speaking dispositive, issue is the authority for the arbitration and the resulting award. Further facts are necessary to make this determination.

There is no question the parties had agreed to arbitrate. Carlin claims the arbitration clause's "[d]isputes solely with Contractor [Carlin]" restricted arbitration to disputes between B-A-C and Carlin regarding work B-A-C was required to perform under the subcontract. According to Carlin, "[d]isputes arising out of Owner acts, omissions or responsibilities" were not to be resolved by arbitration between Carlin and B-A-C, rather the latter were to be resolved under the provisions of the Prime Contract, the contract between Carlin and the City of Bridgeport. As stated, B-A-C filed its demand for arbitration on January 20, 1998. Its demand then was for $250,000.

Carlin began its work on April 27, 1997. "As of February 10, CT Page 2396 1998, BAC completed all of its obligations under the Subcontract, except those obligations that Carlin directed BAC not to perform until further notice. As of February 10, 1998, BAC had submitted 10 invoices to Carlin in the total amount of $559,565.08 . . . ." Memorandum of Blakeslee Arpaia Chapman, Inc. In opposition To Motion of Carlin Contracting Co., Inc. To Vacate Arbitration Award, August 18, 1999, p. 3. [103] "As of February 23, 1998, Carlin had been paid $400,114.15 for work performed by BAG, but had paid BAC only $236,068.78, leaving a shortfall of $164,045.37." Id., p. 4.

On March 5, 1998, B-A-C wrote to Carlin as follows:

"This firm represents Blakeslee Arpaia Chapman, Inc. ("BAC"). This letter is to advise you that BAC is exercising its right to terminate further performance on the above referenced project. The basis for BAC's termination is fully set forth in the attached letter to your surety, Safeco Insurance Company of America, which is incorporated herein and made a part hereof. This letter is also to advise you that BAC is making a claim pursuant to § 49-41a of the Connecticut General Statutes and is making a claim against your payment bond pursuant to § 49-42 of the Connecticut General Statutes, as is fully set forth in the attached letter to your surety." Letter from Attorney William J. Egan to Carlin Contracting Co., Inc., March 5, 1998.

On March 5, 1998, Attorney Egan wrote to Carlin's surety, Safeco Insurance Company. That letter stated in part:

"Notice of Termination

"Carlin's continuing failure to make progress payments when due is a material breach of the subcontract which excuses BAG from further performance and entitles BAG, at its election, to recover in quantum merit for the reasonable value of the labor and materials it furnished to the date of this letter. This letter is notice that BAG is exercising its right to terminate further performance under the subcontract and that it elects to proceed in quantum merit to recover the reasonable value of the labor and materials it has already furnished." Letter from Attorney William J. Egan to Safeco Insurance Company, March 5, 1998.

B-A-C informed Carlin by these letters that it was invoking CT Page 2397 the provisions of C.G.S. § 49-41a and was making a claim against Carlin's payment bond pursuant to C.G.S. § 49-42. Simply stated, this required Carlin to place funds in an interest bearing escrow account for the benefit of B-A-C in an amount equal to what Carlin had been paid by the City for work B-A-C had done but which Carlin had not paid B-A-C. B-A-C claimed this amount was in the order of $147,000.

Carlin characterizes B-A-C's action as a "rescission." According to Carlin, B-A-C's "rescission" renders the contract non-existent and therefore the arbitration provision is wiped out along with the entire contract. B-A-C counters relying on BatterBuilding Materials Co. v. Kirschner, 142 Conn. 1 (1954), andInternational Brotherhood v. Trudor Platt Motor Lines, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. Sangivanni & Sons v. F. M. Floryan & Co.
262 A.2d 159 (Supreme Court of Connecticut, 1969)
Batter Building Materials Co. v. Kirschner
110 A.2d 464 (Supreme Court of Connecticut, 1954)
Haaser v. A. C. Lehmann Co.
33 A.2d 135 (Supreme Court of Connecticut, 1943)
Valente v. Weinberg
67 A. 369 (Supreme Court of Connecticut, 1907)
Janulewycz v. Quagliano
89 A. 897 (Supreme Court of Connecticut, 1914)
Jones v. . Brinsmade
76 N.E. 22 (New York Court of Appeals, 1905)
Gordon v. Indusco Management Corp.
320 A.2d 811 (Supreme Court of Connecticut, 1973)
Metcalfe v. Talarski
567 A.2d 1148 (Supreme Court of Connecticut, 1989)
John T. Brady & Co. v. City of Stamford
599 A.2d 370 (Supreme Court of Connecticut, 1991)
Saturn Construction Co. v. Premier Roofing Co.
680 A.2d 1274 (Supreme Court of Connecticut, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
2000 Conn. Super. Ct. 2393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlin-cont-v-blakeslee-arpaia-chapman-no-cv-99-00551690-feb-22-connsuperct-2000.