A. Sangivanni & Sons v. F. M. Floryan & Co.

262 A.2d 159, 158 Conn. 467, 1969 Conn. LEXIS 622
Supreme Court of Connecticut·Decided November 13, 1969·Published·Cited by 67 cases

Opinion

Cotter, J.

In this action returnable on tbe first Tuesday of May, 1960, the plaintiff, a sole proprietorship, sought an order directing the defendants to proceed with arbitration. Tbe defendants formed a joint venture and entered into a construction contract with Wallingford Shopping Plaza, Inc., on March 26, 1959, in which they agreed to *469 construct a shopping center. On March 31, 1959, the defendants and the plaintiff: entered into a subcontract in which the plaintiff agreed to perforin the excavation, site work and paving in accordance with the plans and specifications and the provisions of the general contract. The subcontract between the parties contained an arbitration clause. In the course of the performance of the subcontract, two principal disputes arose between the parties regarding the plaintiff’s claim for extra compensation for rock excavation and the failure of the plaintiff to resume paving operations in the spring of 1960. By reason of the latter dispute, the defendants terminated the subcontract on or about April 5, 1960. The plaintiff instituted a separate mechanic’s lien foreclosure action against Wallingford Shopping Plaza, Inc., the owner of the property which was the subject of the subcontract, returnable to the Court of Common Pleas for New Haven County on the first Tuesday of October, 1960, in which action the defendants were subsequently joined. The plaintiff closed the pleadings in the present action with an amended reply filed September 7, 1967. The case was discontinued on May 13, 1968, pursuant to an order of the court. Upon motion of the plaintiff, the case was restored by the court to the docket on June 17, 1968, after a hearing. Thereafter, a judgment of nonsuit was rendered on September 12, 1968, for failure of the plaintiff to appear to prosecute its complaint. On September 16, 1968, the plaintiff’s attorneys, the firm of Marsh, Day and Calhoun, filed a motion to open the nonsuit on the ground that the firm’s appearance had not been printed on the. September 12, 1968, list of assignments of court cases and that it did not therefore receive notice that the. case was on the trial list. The defendants claim that *470 failure to include the firm name of Marsh, Day and Calhoun on the printed assignment list did not excuse the failure of other attorneys who had represented the plaintiff from appearing on the day the case was assigned or from notifying Marsh, Day and Calhoun of the assignment. The court, nevertheless, granted the plaintiff’s motion to open the nonsuit on September 20,1968.

The trial court, after a trial, rendered judgment on November 18, 1968, directing the parties to proceed with arbitration of such disputes as exist between them pertaining to the contract. The defendants have appealed.

The defendants, in their answer, denied the allegations in the complaint, admitting, however, that the parties “entered into a written agreement on or about March 31, 1959, providing for arbitration under certain conditions and circumstances, but the plaintiff’s demands and the matters in controversy are clearly outside of the orbit” of the arbitration agreement. In addition, the defendants, at various times, filed nine special defenses raising issues that (1) the plaintiff will claim upon arbitration that it was induced to enter into the agreement through misrepresentation and fraud concerning the quantity of rock to be encountered under the subcontract, and that such a “claim for fraud can only be asserted and determined in an action at law” and not in arbitration ; and that no bona fide arbitrable issue exists because (2) the plaintiff abandoned the contract, (3) the plain language of the contract precludes extras for rock excavation, demolition or rock conditions encountered by the contractor at the construction site, (4) the plaintiff failed to advise the defendants in writing upon encountering rock before proceeding to blast and remove it, (5) institution of *471 the present action was premature because the work which the plaintiff was obligated to perform was not entirely finished, (6) the plaintiff, contrary to a provision in the contract, did not obtain an interpretation from the architect as to whether or not work allegedly performed, for which the plaintiff claims or will claim extra compensation, was covered in the plans and specifications, and (7) the plaintiff failed to obtain written authorization for the performance of extra work, payment for which the defendants believe the plaintiff will make a claim upon arbitration. The defendants concluded the list of special defenses by alleging that (8) commencement of the action to foreclose the mechanic’s lien constituted a waiver of whatever right the plaintiff may have had to compel arbitration and (9) the plaintiff was guilty of laches in not diligently prosecuting this action to compel arbitration.

Of the salvo of defenses interposed by the defendants relating to nonarbitrability, only one merits any extended discussion. That one has to do with the defendants’ allegation in their first special defense that the plaintiff’s claim has been, and upon arbitration will be, that the plaintiff was induced to enter into the subcontract “by the misrepresentation and/or fraud of the defendants- and/or the owner, Wallingford Shopping Plaza, Inc., regarding amounts of rock to be excavated.”

Free access — add to your briefcase to read the full text and ask questions with AI

A. Sangivanni & Sons v. F. M. Floryan & Co., 262 A.2d 159, 158 Conn. 467, 1969 Conn. LEXIS 622 (Colo. 1969).

262 A.2d 159 (A. Sangivanni & Sons v. F. M. Floryan & Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Doe v. Hartford Roman Catholic Diocesan Corp.
Supreme Court of Connecticut, 2015
Bobbin v. Sail the Sounds, LLC
Connecticut Appellate Court, 2014
Naccache v. Taylor
72 A.3d 149 (District of Columbia Court of Appeals, 2013)
DAIMLERCHRYSLER INS. CO., LLC v. Pambianchi
762 F. Supp. 2d 410 (D. Connecticut, 2011)
Harold Cohn & Co. v. Harco International, LLC
804 A.2d 218 (Connecticut Appellate Court, 2002)
Harold Cohn v. Harco International, No. Cv-99-0089169 (May 2, 2001)
2001 Conn. Super. Ct. 5760 (Connecticut Superior Court, 2001)
Leisure Resort Tech. v. Trading Cove, No. Cv-00-0091180 (Oct. 13, 2000)
2000 Conn. Super. Ct. 12564 (Connecticut Superior Court, 2000)
Carlin Cont. v. Blakeslee Arpaia Chapman, No. Cv 99-00551690 (Feb. 22, 2000)
2000 Conn. Super. Ct. 2393 (Connecticut Superior Court, 2000)
General Electric Capital Corp. v. DirecTV, Inc.
94 F. Supp. 2d 190 (D. Connecticut, 1999)
Yeong Gil Kim v. Magnotta
714 A.2d 38 (Connecticut Appellate Court, 1998)
Reed v. Comen, No. Cv 94 031 12 92 (Apr. 29, 1998)
1998 Conn. Super. Ct. 5416 (Connecticut Superior Court, 1998)
Langer v. Hoffman Fuel Co. of Stamford, No. Cv97-0157960 S (Mar. 4, 1998)
1998 Conn. Super. Ct. 2660 (Connecticut Superior Court, 1998)
Ostroske v. Lenkowski, Lonergan Co., No. Cv 97 137039 (Feb. 4, 1998)
1998 Conn. Super. Ct. 2440 (Connecticut Superior Court, 1998)
Seramonte Associates v. Smith, No. Cvnh 9706-8247 (Jan. 21, 1998)
1998 Conn. Super. Ct. 173 (Connecticut Superior Court, 1998)
Jaser v. Deicicchi, No. Cv97-038083-S (Oct. 16, 1997)
1997 Conn. Super. Ct. 11123 (Connecticut Superior Court, 1997)
Alca Construction Co. v. Housing Auth., No. Cv-97-0569696-S (Jun. 3, 1997)
1997 Conn. Super. Ct. 6346 (Connecticut Superior Court, 1997)
Grande v. Behling, No. Cv95-0250416s (Apr. 24, 1997)
1997 Conn. Super. Ct. 4768 (Connecticut Superior Court, 1997)
Gilbane Building Co. v. Stamford Towers, No. Cv91 0118788 S (Nov. 18, 1996)
1996 Conn. Super. Ct. 9029 (Connecticut Superior Court, 1996)