Lummus Company v. Commonwealth Oil Refining Company, Inc., (Three Cases)

280 F.2d 915
CourtCourt of Appeals for the First Circuit
DecidedAugust 10, 1960
Docket5552-5554
StatusPublished
Cited by69 cases

This text of 280 F.2d 915 (Lummus Company v. Commonwealth Oil Refining Company, Inc., (Three Cases)) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lummus Company v. Commonwealth Oil Refining Company, Inc., (Three Cases), 280 F.2d 915 (1st Cir. 1960).

Opinions

ALDRICH, Circuit Judge.

This is an appeal under 28 U.S.C. § 1292(a) (1) from an interlocutory order, dated July 20, 1959, of the United States District Court for the District of Puerto Rico entering a preliminary stay of arbitration and granting a preliminary injunction enjoining defendant-appellant from taking any further action in a case pending in the United States District Court for the Southern District of New York, or any other steps in furtherance of the arbitration. Defendant-appellant, The Lummus Company, a Delaware corporation with its principal office in New York, N. Y., is engaged, inter alia, in designing and constructing oil refineries. Plaintiff-appellee, Commonwealth Oil Refining Co., Inc., is a Puerto Rican corporation, which describes itself as the owner of an oil refinery in Puerto Rico built for it by the defendant. The controversy between the parties arises out of two contracts entered into in New York in July 1954, and March 1956, under which [918]*918Lummus undertook to design, build, initially supervise, and guarantee the performance of, first, the original refinery, and then later its expansion facilities, for a guaranteed maximum cost of some $35,000,000. Both contracts contain the following clause:

“Any controversy or claim arising out of or relating to this Agreement shall be settled by arbitration * * *. The arbitration shall be held in New York, U.S.A.”1

The refinery has been built, and Lum-mus has received some $32,500,000 therefor. The original plant commenced operation on December 31, 1955, and the expansion facilities on September 30, 1957. Operation, however, has been at a marked loss, rather than at the substantial profit anticipated. Since at least 1957 Commonwealth has expressed dissatisfaction with Lummus’ performance, and Lum-mus, inter alia, with Commonwealth’s refusal to pay sums claimed to be due for work and materials.

On April 29,1959, Lummus mailed, and on April 30 Commonwealth received, a demand for arbitration of its claim to recover some $4,700,000 from Commonwealth, and of “any set-offs or counterclaims * * * which Commonwealth may assert.” On May 4, Commonwealth instituted an action in the District of Puerto Rico, in which it alleged, in substance, that Lummus had prepared “oil refinery economic and capability studies and earnings projections based thereon (herein called, collectively, ‘studies and projections’)” relating to the refinery; that the “ ‘studies and projections’ were false and misleading,” and that LummuS' either knew this to be so or made the representations “with reckless indifference as to the truth or falsity thereof”; that Commonwealth relied on the “studies and projections” and was induced by the representations contained therein to' execute the two contracts, “which plaintiff would not have executed but for such false and misleading ‘studies and projections’ * * * ”; and that, “by reason of the facts set forth in this complaint, plaintiff has suffered financial losses and damages in an amount exceeding $60,-000,000 * * As relief, the complaint sought:

“(a) judgment * * * in the sum of $60,000,000, plus other sums as yet undetermined * * *; and

“(b) such rescission under the laws of the State of New York of the two contracts * * * as may be just and equitable * * * or a declaration as to their inexistence under the laws of the Commonwealth of Puerto Rico * * * 2 At the same time Commonwealth served a motion in the district court, “pursuant to 32 L.P.R.A. § 3204(4) (a),”3 to stay the New York arbitration on the ground that the arbitration clauses were invalid by reason of fraudulent inducement of the contracts. On May 20 Lummus served a motion in the New York County Supreme Court to compel arbitration. On May 25 Commonwealth filed a petition to remove that proceeding to the United [919]*919States District Court for the Southern District of New York, hereinafter called the Southern District. On May 29 Lummus obtained from that court an order for Commonwealth to show cause, returnable June 2, why the present proceedings should not be enjoined. No further steps were taken in the Southern District because on the same day Commonwealth obtained from the court below, ex parte, a temporary order restraining further proceedings in the Southern District. On June 1, Commonwealth moved for a preliminary injunction restraining Lummus from taking any further action in the Southern District or elsewhere in furtherance of arbitration until final determination of the motion of May 4 for a stay of arbitration. Decision was reserved on this motion, but the temporary restraining order was continued in force to June 18. On that date, Judge RuizNazario being out of the district, a hearing was held before Senior Judge Magruder, sitting in the district court by special assignment, on the matter of continuing the temporary restraining order pending determination by Judge RuizNazario of the original motion to stay arbitration, and of the motion for a preliminary injunction. On June 19 Judge Magruder entered a preliminary injunction, to expire July 20, stating that he was doing so in order to give Judge RuizNazario opportunity to make the final decision on the questions before him. See 174 F.Supp. 485. On July 6 Lummus moved for a modification of Judge Magruder’s order to permit it to move in the Southern District to remand that action to the state court. This motion was denied on July 17. See 175 F.Supp. 873.4 On July 20 Judge Ruiz-Nazario entered an order preliminarily staying the arbitration “until this Court enters its order finally determining whether there are valid and existing arbitration agreements * * *,” and granted the preliminary injunction enjoining Lummus from taking any steps in furtherance of the arbitration, in the Southern District or otherwise.

Admittedly Lummus’ appeal from the decree of July 20 presents all pertinent matters. It raises a substantial number of difficult questions. They can be divided into three major groupings. First, Lummus contends that the district court, as a matter of equitable jurisdiction, should not have enjoined the New York proceedings, but should rather have stayed its own. It bases this contention, first, on the priority of the New York proceedings, arguing that they commenced with the service of the arbitration demand, and second, on the contention that New York is a more proper forum because New York law is controlling, because New York is more convenient for the parties and witnesses, and because jurisdiction over Lummus in Puerto Rico is doubtful.5 We do not stop to consider these contentions at any length. What we presently have here is simply a question of two pending actions, i. e., the motion to stay arbitration and the action to compel arbitration, in two federal courts of concurrent jurisdiction, each of which is being asked to consider what is basically a different side of the same coin. There is no reason why both suits should continue at the same time. This would be detrimental to both the parties and the federal judicial system. Although priority of suit is often taken as a basic factor in determining which should give way, see Martin v. Graybar Elec. Co., 7 Cir., 1959, 266 F.2d 202

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feliciano-Munoz v. Rebarber-Ocasio
970 F.3d 53 (First Circuit, 2020)
Portugues-Santana v. Rekomdiv International
657 F.3d 56 (First Circuit, 2011)
Huongsten Production Import & Export Co. v. Sanco Metals LLC
810 F. Supp. 2d 418 (D. Puerto Rico, 2011)
Dialysis Access Center, LLC v. RMS Lifeline, Inc.
638 F.3d 367 (First Circuit, 2011)
Beazer Homes Corp. v. Bailey
940 So. 2d 453 (District Court of Appeal of Florida, 2006)
Griggs v. E. I. DuPont
Fourth Circuit, 2004
Joseph D. Griggs v. E.I. Dupont De Nemours & Company
385 F.3d 440 (Fourth Circuit, 2004)
In re Tyco Int’l Ltd. MDL (03-1342)
2003 DNH 228 (D. New Hampshire, 2003)
Arrieta Gimenez v. Arrieta Negron
672 F. Supp. 46 (D. Puerto Rico, 1987)
Cancanon v. Smith Barney, Harris, Upham & Co.
805 F.2d 998 (Eleventh Circuit, 1986)
Rojas Cancanon v. Smith Barney
805 F.2d 998 (Eleventh Circuit, 1986)
Borck v. Holewinski
459 So. 2d 405 (District Court of Appeal of Florida, 1984)
Alascom, Inc. v. ITT North Electric Co.
727 F.2d 1419 (Ninth Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
280 F.2d 915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lummus-company-v-commonwealth-oil-refining-company-inc-three-cases-ca1-1960.