North Carolina v. Federal Energy Regulatory Commission

730 F.2d 790, 235 U.S. App. D.C. 28
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 20, 1984
DocketNo. 81-1225
StatusPublished
Cited by30 cases

This text of 730 F.2d 790 (North Carolina v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Carolina v. Federal Energy Regulatory Commission, 730 F.2d 790, 235 U.S. App. D.C. 28 (D.C. Cir. 1984).

Opinion

Opinion for the Court filed by Circuit Judge SCALIA.

SCALIA, Circuit Judge:

The State of North Carolina and the North Carolina Utilities Commission petition under 15 U.S.C. § 717r(b) (1982) for review of a Federal Energy Regulatory Commission order determining whether customers of the Transcontinental Gas Pipe Line Corporation are entitled to be paid compensation in conjunction with a series of curtailment plans reducing their allocations of natural gas.

I

During 1970, natural gas shortages developed on a number of pipeline systems in the United States. In April 1971, the Commission 1 ordered every federally regulated pipeline that anticipated it might have to curtail deliveries to file a curtailment plan explaining how it would allocate available gas. That plan, if approved, would define the pipeline’s obligations and supersede its contracts with its customers. Policy with Respect to Establishment of Measures, [31]*31etc., Docket No. R-418, Order No. 431, Statement of General Policy, 45 F.P.C. 570 (1971).

A. Transeo’s Curtailment Plans

Transcontinental Gas Pipe Line Corporation (“Transco”) is one of the major pipeline systems in the United States. In 1971 it experienced gas supply shortages and began curtailment of service, which lasted until May 15, 1980. During that period, Transco has had a variety of curtailment plans. This lawsuit focuses on three of them.

Until November 1973, Transco performed its curtailment on the basis of interim plans which reduced supplies on a pro rata basis according to the volume of each customer’s contractual entitlements. The pipeline and customers agreed to these plans and the Commission approved settlements implementing them. Transcontinental Gas Pipe Line Corp., Docket No. RP71-118, Order Conditionally Approving Interim Settlement Agreement, 46 F.P.C. 1212 (1971); Transcontinental Gas Pipe Line Corp., Docket No. RP72-99, Order Approving Interim Settlement Agreement, 48 F.P.C. 1060 (1972). No review of these plans was ever sought, and they are not before us in this suit.

In January 1973, Transco submitted a new plan, which differed in its basic approach. Instead of curtailing all customers on a pro rata basis, it set up priorities among the “end uses” to which the ultimate consumers put natural gas, and curtailed customers with low-priority end uses much more than those with high-priority ones. The highest priority was assigned to residential use, and successively lower priorities to large commercial and certain other uses and various categories of industrial uses.2 The Commission permitted the plan to go into effect on an interim basis in November 1973. Transcontinental Gas Pipe Line Corp., Docket No. RP72-99, Order Denying Motion for Reconsideration, etc., 50 F.P.C. 281 (1973). This court, however, stayed the Commission’s action and directed continuation of the previous interim plan until further order of the court. Consolidated Edison Co. of New York v. FPC, No. 73-1999 (D.C.Cir. Nov. 9, 1973; Dec. 14, 1973) (Orders). No issues arising out of that litigation are raised in this suit.

In 1974, Transco submitted a new interim settlement plan (“Transco I”) for the period November 1974-November 1975. That plan, the first of those directly relevant to this suit, allocated gas 50% on the basis of pro rata contractual entitlement and 50% on the basis of end use. It also required that customers curtailed the least pay compensation to those curtailed the most. As described below, that plan became embroiled in procedural and substantive challenges before the Commission, this court, and the Supreme Court.

The Commission, which was still under order to continue the 1972 pro rata plan until further word from this court, had asked us for clarification as to what action that order would permit with regard to an interim plan for the 1974-75 contract season. We ruled that the Commission could either maintain in effect the existing interim plan or implement a new one proposed by Transco. Consolidated Edison Co. v. FPC, No. 73-1999, (D.C.Cir. Oct. 4, 1974) (Order). On November 12, 1974, however, the Commission rejected the Transco I plan because, among other reasons, it believed the compensation requirement exceeded the Commission’s powers. Transcontinental Gas Pipe Line Corp., Docket No. RP72-99, Order Finding an Emergency, etc., 52 F.P.C. 1288 (1974). Transco and some of its customers petitioned this court to review the Commission’s decision. We entered an interim order pending our final [32]*32review, directing the Commission to place in effect the Transco I plan, with the exception of the compensation scheme, monies for which we instructed the potential payors to deposit in an escrow account pending judicial determination of its legality. Consolidated Edison Co. v. FPC, 511 F.2d 372 (D.C.Cir.1974).

The Commission’s order rejecting Transco I was still before this court for final review. At that juncture, we became concerned that the entire curtailment plan might be illegal because no genuine natural gas shortage existed. We therefore entered an interlocutory order directing the parties to submit information concerning Transco’s reserves. After receiving responses and noting that the Commission refused to certify the accuracy of Transco’s submissions, we ordered the Commission to conduct an investigation of the matter within thirty days, and deferred review of the Commission’s order until that was completed. The Supreme Court granted the Commission’s petition for certiorari and held that our order was a usurpation of a Commission function, and beyond the bounds of our authority. It directed us to remand to the agency if we required further information, or to proceed with our review if we did not. FPC v. Transcontinental Gas Pipe Line Corp., 423 U.S. 326, 96 S.Ct. 579, 46 L.Ed.2d 533 (1976). Accordingly, we remanded the record to the Commission for further findings of fact regarding the existence of a shortage, but retained jurisdiction over the controversy. Transcontinental Gas Pipe Line Corp. v. FPC, No. 74-2036 (D.C.Cir. Feb. 6, 1976) (Order). The Commission conducted an investigation, made further findings, and returned the record to us. We found the information inadequate and remanded the record again. Transcontinental Gas Pipe Line Corp. v. FPC, 562 F.2d 664 (D.C.Cir.1976), cert. denied, 436 U.S. 930, 98 S.Ct. 2830, 56 L.Ed.2d 775 (1978).

Following this second remand of the record, the Commission directed an Administrative Law Judge to prepare a report to the Commission on the shortage. Examination in Response to Court Ordered Remand, etc., Docket No. TC79-6, Order Providing for Investigation, Requiring Report, & Establishing Procedures, 6 FERC (CCH) ¶ 61,140 (1979).3 It also moved this court to remand the entire controversy in order that the Commission might reexamine the Transco I plan in light of our decision in Elizabethtown Gas Co. v. FERC, 575 F.2d 885 (D.C.Cir.1978), which had held that the Commission had authority to allow compensation as part of a curtailment plan. We granted the motion. Transcontinental Gas Pipe Line Corp. v. FERC, No. 74-2036 (D.C.Cir. Apr. 18, 1979) (Order).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Kerr
D. Arizona, 2023
Stewart v. Azar
313 F. Supp. 3d 237 (D.C. Circuit, 2018)
Sierra Club v. Federal Energy Regulatory Commission
867 F.3d 1357 (D.C. Circuit, 2017)
Wood v. Betlach
922 F. Supp. 2d 836 (D. Arizona, 2013)
State v. Environmental Protection Agency
531 F.3d 896 (D.C. Circuit, 2008)
National Treasury Employees Union v. Chertoff
394 F. Supp. 2d 137 (District of Columbia, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
730 F.2d 790, 235 U.S. App. D.C. 28, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-carolina-v-federal-energy-regulatory-commission-cadc-1984.