Northern Natural Gas Company, Division of Internorth, Inc. v. Federal Energy Regulatory Commission, Panhandle Eastern Pipe Line Company, Intervenors

785 F.2d 338, 251 U.S. App. D.C. 340, 1986 U.S. App. LEXIS 22654
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 11, 1986
Docket85-1044
StatusPublished
Cited by8 cases

This text of 785 F.2d 338 (Northern Natural Gas Company, Division of Internorth, Inc. v. Federal Energy Regulatory Commission, Panhandle Eastern Pipe Line Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Natural Gas Company, Division of Internorth, Inc. v. Federal Energy Regulatory Commission, Panhandle Eastern Pipe Line Company, Intervenors, 785 F.2d 338, 251 U.S. App. D.C. 340, 1986 U.S. App. LEXIS 22654 (D.C. Cir. 1986).

Opinion

GINSBURG, Circuit Judge:

Northern Natural Gas Company (Northern) petitions this court for review of two Federal Energy Regulatory Commission (FERC or Commission) orders remarkable for their incoherence. The first order authorized an amendment to a contract between Northern and Panhandle Eastern Pipe Line Company (Panhandle) and Trunk-line Gas Company (Trunkline), so as to allow Northern to purchase less gas transportation from Panhandle and Trunkline. Generating the controversy at hand, the Commission, both initially and on rehearing, declined to grant the authorization retroactively. FERC issued the initial order more than two years after Northern had first invoked its contractual right to ask Panhandle to reduce the transportation purchase quantity; the delay, Northern estimates, cost it about 1.3 million dollars. Northern and Panhandle now each charges the other with responsibility for the delay. In the orders Northern asks us to review, FERC raises questions about its statutory authority to grant retroactive authorizations, and blames both parties for the delay but leaves the entire cost on Northern. We vacate the two orders and remand this matter to the Commission so that it may issue an order reasoned with sufficient clarity to enable us to engage in meaningful review.

I. Background

Northern buys natural gas produced offshore Louisiana in the areas called “West Cameron Blocks 480, 543, and 616” (Blocks I, II, and III, respectively). Under three separate FERC authorizations and three separate contracts dated September 26, 1976, October 27, 1976, and May 24, 1977, for Blocks I, II, and III, respectively, Panhandle and Trunkline transport the gas for Northern to onshore facilities. Northern *340 pays Panhandle and Trunkline a monthly demand charge based on the daily amount of transportation that Northern, by contract specification, is entitled to demand.

The contracts and Commission certificates specified an initial daily contract-demand quantity but provided that Northern could unilaterally reduce this quantity after five years of service, upon six months notice to Panhandle and Trunkline. Northern gave such notice for Blocks I and II by letters dated, respectively, May 26, 1981 and June 24, 1981. Over Northern’s disagreement, Panhandle insisted that the reduction would require a formal contract amendment and sent Northern two proposed amendments, which Northern received on September 14, 1981. These amendments did reduce the daily contract-demand quantity, but for reasons apparently unrelated to the reduction, they also increased the unit charge that Northern would pay for transportation. Northern and Panhandle then negotiated for several months about the increase; eventually, in March 1982, Northern’s General Manager signed the amendments. Panhandle, however, next requested verification that the General Manager was authorized to sign the amendments; Northern provided documentation to that effect; Panhandle still refused to accept the signature. In May 1982, a Northern Vice President finally signed the amendments.

On August 9, 1982, Panhandle attempted to implement the contract amendments through a tariff filing with FERC. On September 8, FERC rejected the filing; the Commission explained that, because authorization of an abandonment of service was at stake, the amendments had to be presented through a filing made under Section 7(b) of the Natural Gas Act (NGA), 15 U.S.C. § 717f(b).

Meanwhile, on March 15, 1982, Northern had sent Panhandle notice of a 50% reduction in the daily contract-demand quantity for Block III. Panhandle then sent Northern a proposed amendment, identical to the first two except for information specific to the block. Northern received the amendment on August 19 and executed it on October 6.

Finally, on February 9, 1983, Panhandle filed under Section 7(b) for abandonments in all three blocks, requesting a retroactive effective date of February 1, 1982, for Blocks I and II and October 1, 1982, for Block III. Northern intervened in support of Panhandle and Trunkline. On September 23, FERC authorized the reductions effective as of the 1983 date of the order, not the requested 1982 dates. In rejecting the request for retroactivity, FERC noted that Panhandle and Trunkline had not even filed under Section 7(b) for the reductions as of the effective dates requested. The order also observed that Northern was contractually required to give Panhandle six months’ notice (in fact, Northern gave more generous notice), and if the parties had any questions about the volume reductions, “then Panhandle and Trunkline should have made more timely filings.” Panhandle Eastern Pipe Line Company, 24 F.E.R.C. 1161,337 at 61,716 (Sept. 23, 1983) (Order).

Northern and Panhandle both requested rehearing on the denial of retroactivity. On November 20, 1984, FERC denied these requests. It noted: “Section 7(b) does not provide for retroactive abandonment authorizations.” FERC further observed: “The untimely filings for appropriate Commission authorization appear to have resulted in good part from the failure of the parties to resolve their differences expeditiously. In light of this and of the prospective nature of Section 7 authorization, we shall not make the authorizations retroactive.” Panhandle Eastern Pipe Line Company, 29 F.E.R.C. 1161,236 at 61,489 (Nov. 20, 1984) (Order on Rehearing). Northern then petitioned this court for review.

II. FERC’s Statutory Authority

We first consider whether the Commission had statutory authority to grant the relief here requested — a retroactive abandonment authorization. We hold that Section 16 of the NGA, 15 U.S.C. § 717o, does grant FERC such authority, and that Section 7(b) does not bar such relief.

*341 Section 16 provides in pertinent part: “The Commission shall have power to perform any and all acts, and to ... make ... such orders ... as it may find necessary or appropriate to carry out the provisions of this [Act].” This provision gives the Commission “broad authority so as to do equity consistent with the public interest,” Columbia Gas Transmission Corp. v. FERC, 750 F.2d 105, 109 (D.C.Cir.1984), and “to use means of regulation not spelled out in detail, provided the agency’s action conforms with the purposes and policies of Congress and does not contravene any terms of the Act.” Niagara Mohawk Power Corp. v. FPC, 379 F.2d 153, 158 (D.C.Cir.1967).

Section 16 unquestionably gives FERC the authority, in fashioning remedies, to consider equitable principles, one of which is to regard as being done that which should have been done. See id. at 160. We therefore hold that in appropriate circumstances, the Commission’s authority under Section 16 extends to the granting of retroactive abandonment authorizations so as to carry out the provisions of the NGA. Cf Consolidated Gas Transmission Corp. v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
785 F.2d 338, 251 U.S. App. D.C. 340, 1986 U.S. App. LEXIS 22654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-natural-gas-company-division-of-internorth-inc-v-federal-cadc-1986.