Consolidated Gas Transmission Corporation v. Federal Energy Regulatory Commission

771 F.2d 1536, 248 U.S. App. D.C. 396, 1985 U.S. App. LEXIS 21665
CourtCourt of Appeals for the D.C. Circuit
DecidedSeptember 17, 1985
Docket84-1240, 84-1256, 84-1323, 84-1324, 84-1328 and 84-1342
StatusPublished
Cited by40 cases

This text of 771 F.2d 1536 (Consolidated Gas Transmission Corporation v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Consolidated Gas Transmission Corporation v. Federal Energy Regulatory Commission, 771 F.2d 1536, 248 U.S. App. D.C. 396, 1985 U.S. App. LEXIS 21665 (D.C. Cir. 1985).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

Petitioners and intervenors in these consolidated cases challenge various aspects of an opinion by the Federal Energy Regulatory Commission (“FERC” or “Commission”) interpreting the minimum bill provision of a tariff for resale of liquefied natural gas (“LNG”) imported from Algeria and regasified at a facility in Cove Point, Maryland. The minimum bill provision in each of the tariffs provides that the LNG company can recover certain operating expenses, but not a return on equity, if it is “unable to deliver gas” to the transmission company. LNG supplies from Algeria to the Cove Point facility were cut off in March, 1980, but the two companies who jointly own the plant (“the LNG companies”) did not invoke the minimum bill provisions of their tariffs with their affiliated pipeline companies until December, 1980. The Commission, in a series of three opinions, eventually concluded that the LNG companies should have invoked the minimum bill as of May 31, 1980, and ordered the LNG companies and their affiliated pipelines to refund amounts above the minimum bill charged after that date. Columbia Gas Transmission Corp., 25 F.E.R.C. ¶ 61,460 (1983) [hereinafter cited as Op. 202], vacated, 27 F.E.R.C. ¶ 61,089 [hereinafter cited as Op. 202-A], modified, 28 F.E.R.C. ¶ 61,053 (1984) [hereinafter cited as Op. 202-B]. We find the Commission’s order to be based on substantial evidence and to be a rational exercise of its broad powers to fashion discretionary relief. We therefore deny the petitions for review.

I. The Background

A. The Minimum Bill Provision

Petitioners 1 Consolidated System LNG Company (“Consolidated LNG”) and Columbia LNG Corporation (“Columbia LNG”) jointly own a regasification terminal for LNG at Cove Point, Maryland and a pipeline from the terminal to Loudoun County, Virginia. In 1972, the Federal Power Commission (“FPC” or “Commission”) authorized each of the companies to import LNG from Algeria and to revaporize it at Cove Point for transportation and sale to its pipeline affiliate, Columbia Gas Transmission Corporation (“Columbia Transmission”) and Consolidated Gas Transmission Corporation (“Consolidated Transmission”), respectively. Columbia LNG Corp., 47 F.P.C. 1624 [hereinafter cited as Op. 622], modified, 48 F.P.C. 723 (1972) [hereinafter cited as Op. 622-A]. 2 The facility began operating in 1978 with Columbia LNG as the operator.

The Commission certificated the Cove Point facilities pursuant to § 7 of the Natural Gas Act, 15 U.S.C. § 717f (1982), large *1541 ly in response to a shortage of natural gas in the United States and on the systems involved. Op. 622 at 1636-37. The import and certificate authorizations provided that El Paso Algeria Corporation would “deliver the equivalent of 650,000 Mcf per day of LNG at Cove Point, 300,000 Mcf for Columbia LNG and 350,000 Mcf for Consolidated LNG.” Id. at 1637. 3 The regasified LNG would provide base load supplies of gas to the transmission companies estimated at 9.1% of Columbia’s and 14.3% of Consolidated’s 1977 gas supplies. Initial Decision, 47 F.P.C. 1656, 1696-97 (1972) [hereinafter cited as Initial Dec.]. The Commission authorized the imports of LNG pursuant to § 3 of the Natural Gas Act, 15 U.S.C. § 717b (1982), finding the LNG supplies from Algeria to be adequately reliable but recognizing “that there can be no absolute guarantee that there will be no interruption of supply.” Op. 622 at 1633.

While the Commission was convinced that the LNG was badly needed by the companies, it warned “that it is [not] in the best interest of gas consumers in the United States that any project which promises new supplies of gas be approved regardless of the associated price and other conditions.” Op. 622-A at 727. The Commission acted instead to balance the need to make the project economically viable with its duty to protect gas consumers. Id. at 726. It chose the minimum bill as the tariff mechanism by which to create “an equitable apportionment of the risk between customers and stockholders and ... to assure the financing of the project on reasonable terms to the consumer.” Id. at 730.

A minimum bill provision similar to that adopted by the FPC to apportion the project’s risk had initially been proposed by Consolidated LNG. Consolidated LNG’s proposed tariff provided that the company would not pass on to customers return on equity costs in the event of a service interruption in excess of one day. In return for this assumption of some of the risk of interruption, Consolidated LNG sought a greater return on equity than that granted its pipeline affiliate. Initial Dec. at 1694-95. Columbia LNG, on the other hand, had proposed a tariff providing for the payment of all costs, including a return on equity, “ ‘regardless of: (i) the amount of gas delivered, and (ii) the non-delivery of gas for any reason, including force majeure,’ ” and was willing to accept the same return on equity as its pipeline affiliate in return for being allowed to pass the entire risk of interruption on to its customers. Id. at 1694. The Commission approved the certificates and most of the proposed tariffs for sales by the LNG companies to their affiliated pipelines but rejected the portions of both tariffs requiring payment whether or not LNG was delivered, finding the provisions contrary to the public interest. Op. 622 at 1639. On rehearing, however, the Commission found that “although full ‘cost-of-service’ tariffs are not in the public interest, the type of minimum bill proposed by Consolidated LNG is acceptable for this project, and that, in the event of non-delivery, certain fixed costs should be recovered by the LNG companies.” Op. 622-A at 730. The Commission therefore ordered that the tariffs filed by both LNG companies include a minimum bill provision specifying the expenses to be paid “[i]n the event that Seller is unable to deliver gas to Buyer during any period exceeding one day.” Id. at 731. 4

*1542 B. The Algerian Cut-Off and the FERC Proceedings

Deliveries of imported LNG to the Cove Point terminal began in 1978. Sonatrach, the Algerian company exporting the LNG, suspended deliveries effective March 31, 1980, after it was unable to secure the Algerian government’s approval of an amendment increasing the price paid by El Paso Algeria to Sonatrach. The last shipment of LNG from Algeria was unloaded at Cove Point on April 11, 1980, leaving the storage tanks nearly full with over 5 million dt of gas. Negotiations between representatives of the U.S. and Algerian governments were held in an attempt to resolve the pricing dispute; the negotiations began on April 21,1980 and continued into 1982, but to no avail.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Association of Realtors v. United States
97 F.4th 951 (D.C. Circuit, 2024)
LG Electronics U.S.A., Inc. v. United States Department of Energy
679 F. Supp. 2d 18 (District of Columbia, 2010)
In Re Western States Wholesale Natural Gas
633 F. Supp. 2d 1151 (D. Nevada, 2007)
Learjet, Inc. v. Oneok, Inc.
633 F. Supp. 2d 1151 (D. Nevada, 2007)
Brubaker, Robert L. v. Metro Life Ins Co
482 F.3d 586 (D.C. Circuit, 2007)
J.P. Morgan Trust Co. v. Williams Companies, Inc.
471 F. Supp. 2d 1076 (D. Nevada, 2006)
Mittal Steel USA ISG, Inc. v. Bodman
435 F. Supp. 2d 106 (District of Columbia, 2006)
Flynn v. Tiede-Zoeller, Inc.
412 F. Supp. 2d 46 (District of Columbia, 2006)
SW Elec Coop Inc v. FERC
347 F.3d 975 (D.C. Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
771 F.2d 1536, 248 U.S. App. D.C. 396, 1985 U.S. App. LEXIS 21665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/consolidated-gas-transmission-corporation-v-federal-energy-regulatory-cadc-1985.