Boston Edison Company v. Federal Energy Regulatory Commission, City of Holyoke Gas and Electric Department, Intervenors

856 F.2d 361, 1988 U.S. App. LEXIS 12155
CourtCourt of Appeals for the First Circuit
DecidedSeptember 6, 1988
Docket87-1935
StatusPublished
Cited by78 cases

This text of 856 F.2d 361 (Boston Edison Company v. Federal Energy Regulatory Commission, City of Holyoke Gas and Electric Department, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Company v. Federal Energy Regulatory Commission, City of Holyoke Gas and Electric Department, Intervenors, 856 F.2d 361, 1988 U.S. App. LEXIS 12155 (1st Cir. 1988).

Opinion

SELYA, Circuit Judge.

Boston Edison Company (“BECO”) petitions for review of certain orders of the Federal Energy Regulatory Commission (“FERC” or the “Commission”) refunding plant addition interest costs (“PAI”) to some thirteen municipal agencies (the “in-tervenors”). We recount the history of the proceeding and then address the principal questions presented.

I. BACKGROUND

Between 1974 and 1975, BECO entered into long-term energy contracts with the municipal agencies for the sale of fixed percentages of the electricity produced at “Pilgrim I,” a nuclear power plant in Plymouth, Massachusetts. The contracts were filed with FERC pursuant to the Federal Power Act (“Act”), 16 U.S.C. §§ 824 et seq. (1982). Each contract ran between BECO and a single municipal agency. They were, however, similar in style and content. Each comprised a “basic agreement” and four appendices. The basic agreement was a standard form which varied only as to dates, customers’ identities, ratable amounts of energy to be purchased, entitlement percentages, and the like. The appendices were uniform. 1 Because the several unit power contracts are, for our pur *363 poses, functionally identical, we treat the arrangement as if only a single contract (“Contract”) existed between petitioner and the thirteen intervenors.

As we have mentioned, see supra note 1, Appendix “C” of the Contract governed the purchasers’ payment obligations. It contained a financing formula for use in calculating billing rates. In 1980, BECO for the first time began invoicing the intervenors for PAI. On February 3, 1987, the inter-venors filed a joint complaint with FERC, asserting that the PAI surcharges were impermissible and subjected them to a higher incremental debt cost than permitted by the financing formula. FERC granted summary judgment in the inter-venors’ favor, and issued an order requiring BECO to refund all PAI charges collected since 1980, with interest thereon, notwithstanding a claims limitation provision in the Contract. City of Holyoke Gas and Electric Dep’t v. Boston Edison Co., No. EL87-13-000, 40 F.E.R.C. ¶ 61,007 (July 2, 1987). Thereafter, FERC denied BECO’s request for rehearing. City of Holyoke Gas and Electric Dep’t v. Boston Edison Co. Nos. EL87-13-001, 002, 40 F.E.R.C. ¶ 61,303 (September 17, 1987). We have jurisdiction of BECO’s ensuing review petition under 16 U.S.C. § 825i (b) (1982).

II. PROPRIETY OF PLANT ADDITION INTEREST CHARGES

Petitioner contends that FERC erred in granting summary judgment in favor of the municipal agencies and in rejecting the proffer of extrinsic evidence. We are not convinced.

A. Standard of Review.

Generally speaking, we have accorded deference to agency expertise in contract interpretation cases where the agency’s interpretation “has a reasonable basis in the contract terms, the [relevant] Act’s policies and the Board’s expertise....” NLRB v. C.K. Smith & Co., 569 F.2d 162, 167 (1st Cir.1977), cert. denied, 436 U.S. 957, 98 S.Ct. 3070, 57 L.Ed.2d 1122 (1978). Nevertheless, the traditional rule has been that agency decisions based on pure questions of law may be reviewed de novo. See Texas Gas Transmission Corp. v. Shell Oil Co., 363 U.S. 263, 268-70, 80 S.Ct. 1122, 1125-27, 4 L.Ed.2d 1208 (1960) (meaning of contract subject to de novo review where Commission “professed to dispose of the case solely upon its view of the result called for by the application of canons of contract construction employed by the courts, and did not in any wise rely on matters within its special competence”). Some circuits read Texas Gas expansively. See, e.g., Mid Louisiana Gas Co. v. FERC, 780 F.2d 1238, 1243 (5th Cir.1986) (when agency’s reading “relies solely on the language of the ... agreement itself, rather than on any technical or factual expertise,” no deference accorded). Others take a more isthmian view. See, e.g., Columbia Gas Transmission Corp. v. FPC, 530 F.2d 1056, 1059 (D.C.Cir.1976) (‘.‘there is room, in review of administrative agencies, for some deference to their views even on matters of law like the meaning of contracts ... where the understanding of the documents involved is enhanced by technical knowledge of industry conditions and practices”); see also National Fuel Gas Supply Corp. v. FERC, 811 F.2d 1563, 1570 (D.C.Cir.) (suggesting that, as a matter of routine, reviewing courts should defer to plausible agency interpretations of contracts within regulated industry), cert. denied, — U.S. —, 108 S.Ct. 200, 98 L.Ed.2d 151 (1987). This circuit has yet to carve its niche along this continuum.

In the present case, BECO suggests that we are bound to follow Texas Gas literally, while FERC urges that we ought not do so. FERC’s exhortation strikes a responsive chord, as there is obvious merit in the proposition that agencies always — or almost always — exercise some measure of expertise when interpreting contracts germane to their administrative fields. Then, too, the Supreme Court’s recent repudiation of the idea that courts need not exhibit any deference to an agency on “pure” questions of statutory law, see Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 842-45, 104 S.Ct. 2778, 2781-83, 81 L.Ed.2d 694 (1984), may well adumbrate a similar result as to *364 “pure” questions of contract interpretation. Be that as it may, we leave definitive resolution of our place on the continuum for another day. Here, all roads lead to Rome. When we scrutinize these agreements in light of the relevant principles of contract law, without ceding special deference to the agency’s interpretation, our reading of them vis-a-vis the PAI point comports exactly with FERC’s. For that reason, we need not decide today how much, if any, deference should be accorded to an agency’s resolution of a “pure” question of contract law under less certain circumstances.

B. Relevant Contract Provisions.

The Contract, which purports to “constitute- the entire understanding” between the parties “superseding any and all previous understandings,” Contract ¶ D-5.6, provides that each intervenor will pay a fixed percentage “of the sum of all of the costs incurred by [BECO] by virtue of: (1) the construction of, or any modifications or additions to the Unit ... and (2) the operation and maintenance of the Unit_” Id. at ¶ C-1.0, reprinted in AppC at 1. The contractual payment equation, see id. at If C-2.0, reprinted in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oklahoma Gas and Electric Company v. FERC
11 F.4th 821 (D.C. Circuit, 2021)
Goethel et al v Penny Pritzker et al
2016 DNH 127 (D. New Hampshire, 2016)
Financial Resources Network, Inc. v. Brown & Brown, Inc.
867 F. Supp. 2d 153 (D. Massachusetts, 2012)
In Re the Educ. Resources Institute, Inc.
442 B.R. 20 (D. Massachusetts, 2010)
Noonan v. Wonderland Greyhound Park Realty LLC
723 F. Supp. 2d 298 (D. Massachusetts, 2010)
Centerpoint Energy Entex v. Railroad Commission
208 S.W.3d 608 (Court of Appeals of Texas, 2006)
Pride Hyundai, Inc. v. Chrysler Financial Co.
369 F.3d 603 (First Circuit, 2004)
Thames Shipyard v. United States
350 F.3d 247 (First Circuit, 2003)
Thames Shipyard & Repair Co. v. United States
350 F.3d 247 (First Circuit, 2003)
Filiatrault v. Comverse Technology, Inc.
275 F.3d 131 (First Circuit, 2001)
Markovits v. Venture Info Capital, Inc.
129 F. Supp. 2d 647 (S.D. New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
856 F.2d 361, 1988 U.S. App. LEXIS 12155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-company-v-federal-energy-regulatory-commission-city-of-ca1-1988.