Seminole Electric Cooperative, Inc. v. Federal Energy Regulatory Commission

861 F.3d 230, 2017 WL 2818640, 2017 U.S. App. LEXIS 11665
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 30, 2017
Docket15-1450
StatusPublished
Cited by6 cases

This text of 861 F.3d 230 (Seminole Electric Cooperative, Inc. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Seminole Electric Cooperative, Inc. v. Federal Energy Regulatory Commission, 861 F.3d 230, 2017 WL 2818640, 2017 U.S. App. LEXIS 11665 (D.C. Cir. 2017).

Opinion

GRIFFITH, Circuit Judge:

The Federal Energy Regulatory Commission determined that Florida Power <⅞ Light Company overcharged Seminole Electric Cooperative, Inc. for electricity and ordered a refund. Seminole claims that it was entitled to a larger refund and petitions for review. We deny the petition.

I

Seminole transmits electricity to its electrical-cooperative customers by. purchasing transmission services from Florida Power. For every hour of the day, Seminole tells Florida Power the amount of electricity it expects its customers to use. When Seminole’s customers take more electricity from the transmission system than expected, Florida Power must make up the difference with extra generation. By the same token, when Seminole’s customers take less electricity than expected, Florida Power must find ways to deal with the excess generation. Either way, Florida Power incurs extra costs to provide this so-called “energy imbalance service,” which are passed along to Seminole according to a formula set forth in Schedule 4 of the tariff that governs the rates Florida Power may charge.

Schedule 4, summarized in the following *232 table and reproduced in relevant part below, 1 divides up charges for energy imbalance service into three tiers or “deviation bands:” a tier with a low rate that applies to deviations of up to 1.5% (with a minimum deviation of 2 megawatts); one with a medium rate that applies to deviations greater than 1.5% up to 7.5% (or greater than 2 megawatts up to 10 megawatts); and one with a high rate that applies to deviations above 7.5% (or above 10 megawatts).

Deviation Band

Between 0% and 1.5%, with a minimum of 2 megawatts

Greater than 1.5% up to 7.5%, or greater than 2 megawatts up to 10 megawatts

Above 7.5%, or above 10 megawatts

Charge for Electricity

100% of incremental cost

110% of incremental cost

125% of incremental cost

Seminole filed a complaint with FERC alleging that Florida Power was violating Schedule 4 in two respects. First, Seminole claimed that Florida Power had been using the wrong measure for four and a half years to determine which tier’s rate applies. Specifically, Florida Power would charge Seminole at a certain tier’s rate if Seminole’s usage crossed either the percentage or the megawatt threshold for that tier, rather than wait for the usage to cross both thresholds before imposing that rate. A simple example illustrates the problem: Suppose usage by Seminole’s customers deviated by 2.5% from what was scheduled, but that — in absolute terms— the deviation amounted only to 1.9 megawatts. Florida Power would charge Seminole at the second tier’s rate, rather than the first tier’s rate, simply because the deviation (i.e, the imbalance) exceeded 1.5%. According to Seminole, that was impermissible because the tariff allowed charges at the second tier’s rate only when usage had deviated by more than 1.5% (in relative terms) and more than 2 megawatts (in absolute terms). FERC ultimately agreed with Seminole that Florida Power’s practice violated the tariff and that the co-op had been overcharged about $3.18 *233 million — a finding that is not disputed by any party and is not at issue in this case. However, the remedy for that violation is.

FERC ordered Florida Power to refund the overcharges for a period going back 24 months from when Seminole first complained about them. FERC based its decision to restrict the refund period in this way on a provision of the companies’ service agreement, reproduced below, 2 that establishes the process for challenging bills issued pursuant to the tariff. As FERC understood that provision, Seminole was barred from challenging any bill that it waited longer than 24 months to contest. Quite apart from its reading of how the time bar works, FERC argues that it would have exercised its discretion to restrict Seminole’s refund anyway on the ground that the co-op should have discovered the overcharges earlier. Seminole challenges FERC’s decision to limit the refund period.

Seminole’s complaint to FERC alleged a second way that Florida Power was violating the tariff: Florida Power applied the rate of the highest applicable tier to the entirety of Seminole’s imbalance, rather than apply each tier’s rate to the portion of the imbalance that fell within each tier. To simplify what may seem at- first blush a complicated matter, imagine that Seminole scheduled 100 megawatts of electricity to be delivered, but ended up using 111 megawatts, meaning that its customers used il% more electricity than it had scheduled on their behalf. In that scenario, Florida Power would charge the highest tier’s rate (125% of marginal cost) on all of Seminole’s 11% deviation — a practice FERC refers to as non-apportionment.

Non-apportionment is not allowed under Seminole’s reading of the tariff. According to Seminole, in this example Florida Power must charge the first tier’s rate (100% of marginal cost) on the first 1.5 percentage points of Seminole’s deviation; the second tier’s rate (110% of marginal cost) on the portion of Seminole’s deviation that is greater than 1.5% up to 7.5%; and the third tier’s rate (125% of marginal cost) only on the very last portion of Seminole’s deviation, above 7.5% up to 11%. In Seminole’s view, charges for energy imbalance service work like the tax code: you pay the highest rate only on that portion of your income that falls into the highest tax bracket, not on all of your income. FERC refers to this approach as apportionment. As a result of Florida Power’s use of non-apportionment rather than apportionment, Seminole paid Florida Power about $1.27 million more than it otherwise would have.

Seminole lost on this issue before FERC, initially and then again on reconsideration. In FERC’s reading, the tariff requires neither apportionment nor non-apportionment, but leaves to the transmission provider the discretion which to use, given the different electricity needs around the country. FERC denied Seminole’s complaint on the question. Florida Power has intervened to defend FERC’s orders.

II

We have jurisdiction to hear Seminole’s challenges under section 813(b) *234 of the Federal Power Act, which allows aggrieved parties to petition for review of FERC orders in our court. See 16 U.S.C. § 825Z(b). We review those “orders under the Administrative Procedure Act’s ‘arbitrary and capricious’ standard.” Entergy Servs., Inc. v. FERC, 568 F.3d 978, 981 (D.C. Cir. 2009) (quoting 5 U.S.C. § 706(2)(A)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tenaska Clear Creek Wind, LLC v. FERC
108 F.4th 858 (D.C. Circuit, 2024)
East Texas Electric Cooperative, Inc. v. FERC
90 F.4th 579 (D.C. Circuit, 2024)
American Municipal Power, Inc. v. FERC
86 F.4th 922 (D.C. Circuit, 2023)
Wabash Valley Power Association, Inc. v. FERC
45 F.4th 115 (D.C. Circuit, 2022)
Veterans Technology, LLC v. United States
133 Fed. Cl. 146 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
861 F.3d 230, 2017 WL 2818640, 2017 U.S. App. LEXIS 11665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/seminole-electric-cooperative-inc-v-federal-energy-regulatory-commission-cadc-2017.