Tenaska Clear Creek Wind, LLC v. FERC

108 F.4th 858
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 19, 2024
Docket22-1059
StatusPublished

This text of 108 F.4th 858 (Tenaska Clear Creek Wind, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tenaska Clear Creek Wind, LLC v. FERC, 108 F.4th 858 (D.C. Cir. 2024).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued April 9, 2024 Decided July 19, 2024

No. 22-1059

TENASKA CLEAR CREEK WIND, LLC, PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENT

BRIGHT CANYON ENERGY CORPORATION, ET AL., INTERVENORS

Consolidated with 22-1336, 23-1076

On Petitions for Review of Orders of the Federal Energy Regulatory Commission

David A. Super argued the cause for petitioner. With him on the briefs were Tyler S. Johnson and Stephen J. Hug.

Beth G. Pacella, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were Matthew R. Christiansen, General Counsel, and Robert H. Solomon, Solicitor. Matthew W. Estes, Attorney, entered an appearance. 2 Matthew J. Binette argued the cause for respondent- intervenors. With him on the brief were Marnie A. McCormick, Mark Strain, Peter K. Matt, Jecoliah R. Williams, Elizabeth P. Trinkle, William R. Hollaway, Ph.D., Lucas C. Townsend, and Max E. Schulman.

Before: CHILDS and GARCIA, Circuit Judges, and GINSBURG, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge CHILDS.

CHILDS, Circuit Judge: Petitioner Tenaska Clear Creek Wind, LLC (“Clear Creek”) wants to generate energy by wind turbine for sale to parts of Missouri, southeast Iowa, and northeast Oklahoma. In these consolidated petitions for review of orders of the Federal Energy Regulatory Commission (“Commission”), Clear Creek maintains that the Commission acted arbitrarily, capriciously, and contrary to precedent when it allowed Southwest Power Pool, Inc. (“SPP”), a regional transmission organization (“RTO”), to assign costs of more than $100 million to Clear Creek to pay for upgrades required on SPP’s system to accommodate the interconnection of Clear Creek’s wind turbine-powered electrical generation project (the “Project”). For the reasons set forth below, the court denies Clear Creek’s petitions for review.

I.

A.

The Federal Power Act of 1920, 16 U.S.C. §§ 791a–828c (the “Act”), vests the Commission with regulatory authority over the “transmission of electric energy in interstate commerce and . . . the sale of electric energy at wholesale in interstate commerce,” id. § 824(b)(1), and requires all rates 3 subject to the Commission’s jurisdiction to “be just and reasonable,” id. § 824d(a). As part of the enforcement of the “just and reasonable” requirement, “section 205 [of the Act] requires that utilities file tariffs reflecting their rates and service terms with the Commission for review.” Green Dev., LLC v. FERC, 77 F.4th 997, 1000 (D.C. Cir. 2023) (citing 16 U.S.C. § 824d(c)). “A negatively affected party may challenge a Commission-approved rate by filing a complaint with the Agency, and it carries the burden of demonstrating that the rate is unjust or unreasonable.” Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. 2022).

When a power generator like Clear Creek builds a new facility, it must connect that location to the power grid. Green Dev., 77 F.4th at 1001. To create a new connection to the electric grid, the power generator asks to “interconnect” to the transmission system by submitting an interconnection request to a transmission system operator, at which point the generator is assigned a position in a queue. Standardization of Generator Interconnection Agreements & Procs. (“Order No. 2003”), 104 FERC ¶ 61,103 at P 35 (July 24, 2003). Transmission system operators review the requests in the queue in chronological order, either individually or in clusters. During the review process, the transmission system operator conducts studies to assess the impact of the new energy source on the preexisting electric grid. These studies identify any new facilities and equipment that may be needed to accommodate the new interconnection. In some instances, the interconnection has an impact beyond the local system. When this occurs, an affected system operator will conduct a study to evaluate the impact of the interconnection on its system. Throughout this entire process, a study may be revised or redone if the generator cancels its proposed project, thereby impacting the upgrades required for the other proposed projects in the queue. 4 When completing an interconnection request, power generators are required to choose the level of interconnection service they require. There are two levels for interconnection service that power generators may choose from: Network Resource Interconnection Service (“NRIS”), or “firm” service, and Energy Resource Interconnection Service (“ERIS”), or “non-firm” or “interruptible” service. As we have previously explained,

Electric utilities often distinguish between “firm” service, under which customers can demand power or transmission at any time, and “interruptible” service, which the utility is entitled to shut off at any point when there is not enough excess capacity beyond that required to guarantee the needs of the utility’s firm customers. Interruptible service is typically offered at a significant discount because the utility’s ability simply to cut off service at peak demand periods alleviates its need to plan for and finance additional capacity to offer the service.

Fort Pierce Utils. Auth. v. FERC, 730 F.2d 778, 785–86 (1984).

B.

The Project is a 242-megawatt facility in northwest Missouri and comprises 111 Vestas turbines across approximately 31,000 acres. Prior to beginning operation, Clear Creek sought to connect the Project to the electric grid. It submitted an interconnection request to transmission system operator Associated Electric Cooperative, Inc. (“AECI”), an electric generation and transmission cooperative based in Springfield, Missouri that provides wholesale power to parts of 5 Missouri, southeast Iowa, and northeast Oklahoma. The level of interconnection service Clear Creek requested was NRIS.

While conducting its interconnection study, AECI identified two RTOs,1 SPP and Midcontinent Independent System Operator, Inc. (“MISO”), that could be affected by Clear Creek’s interconnection.2 AECI directed Clear Creek to coordinate affected system studies with SPP and MISO. On August 20, 2018, Clear Creek asked SPP to conduct an affected system study of the interconnection.3 SPP informed Clear Creek that the affected system study should take between four to five weeks to complete.

SPP’s interconnection study procedures are outlined in its Tariff. See SPP, Open Access Transmission Tariff, attach. V (“Tariff”). When an interconnection request is submitted to SPP, SPP assigns an initial queue position and evaluates all valid interconnection requests submitted in the same 180- calendar-day window in a Definitive Interconnection System Impact Study (“DISIS”) cluster. Requests in the same DISIS cluster are evaluated together at equal priority for SPP to determine if upgrades are needed to fulfill the requests. To

1 RTOs “are independent organizations that manage the transmission of electricity over the electric grid and ensure electricity is reliably available for consumers.” Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 659 (D.C. Cir. 2017).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
Honig v. Doe
484 U.S. 305 (Supreme Court, 1988)
Pub Util Cmsn St CA v. FERC
236 F.3d 708 (D.C. Circuit, 2001)
Hoopa Valley Tribe v. Fed. Energy Regulatory Comm'n
913 F.3d 1099 (D.C. Circuit, 2019)
Xcel Energy Services Inc. v. FERC
41 F.4th 548 (D.C. Circuit, 2022)
Constellation Mystic Power v. FERC
45 F.4th 1028 (D.C. Circuit, 2022)
Elsa Maldonado v. DC
61 F.4th 1004 (D.C. Circuit, 2023)
Green Development, LLC v. FERC
77 F.4th 997 (D.C. Circuit, 2023)
City of Lincoln v. FERC
89 F.4th 926 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
108 F.4th 858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tenaska-clear-creek-wind-llc-v-ferc-cadc-2024.