Advanced Energy Management Alliance v. Federal Energy Regulatory Commission

860 F.3d 656, 2017 WL 2636455, 2017 U.S. App. LEXIS 10815
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 20, 2017
Docket16-1234 Consolidated with 16-1235, 16-1236, 16-1239
StatusPublished
Cited by14 cases

This text of 860 F.3d 656 (Advanced Energy Management Alliance v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Advanced Energy Management Alliance v. Federal Energy Regulatory Commission, 860 F.3d 656, 2017 WL 2636455, 2017 U.S. App. LEXIS 10815 (D.C. Cir. 2017).

Opinion

Opinion for the Court filed

PER CURIAM 1 :

The Federal Energy Regulatory Commission approved new rules governing the buying and selling of “capacity.” “Capacity” is the ability to produce electricity. Purchasers of capacity acquire the right to buy electricity in the future. Petitioners object to the Commission’s approval of revisions to the rules for capacity markets operated by PJM Interconnection.

I.

PJM Interconnection is a regional transmission organization that oversees the electric grid covering all or parts of thirteen Mid-Atlantic and Midwestern states and the District of Columbia. Regional transmission organizations are independent organizations that manage the transmission of electricity over the electric grid and ensure electricity is reliably available for consumers. See generally 18 C.F.R. § 35.34. In the PJM region, independent generation resources—such as nuclear power plants, renewable energy resources, and oil-, coal-, and natural-gas-fired plants—produce electricity. The resource owners sell electricity at wholesale to traditional utilities, or “load serving entities,” which deliver it to consumers. PJM operates competitive “markets” for the wholesale sale of electricity and other related products. One of these markets is a capacity market.

Capacity is not actual electricity. It is a commitment to produce electricity or forgo the consumption of electricity when required. Generation resource owners sell capacity to utilities, which need sufficient capacity to provide electricity to their customers reliably. This creates a kind of options contract. When a utility experiences a high demand for electricity, it can call on the capacity resource to produce that electricity. See Conn. Dep’t of Pub. Util. Control v. FERC, 569 F.3d 477, 479 (D.C. Cir. 2009).

PJM procures capacity for the entire system. It is more efficient if utilities share capacity. Each utility needs enough capacity to be able to meet its expected peak demand. Individual utilities will experience peak demand at different times, and PJM can transmit electricity to where it is needed. See generally Gainesville Utils. Dep’t v. Fla. Power Corp., 402 U.S. 515, 518-20 & n.3, 91 S.Ct. 1592, 29 L.Ed.2d 74 (1971). PJM uses a capacity market to determine what resources will provide capacity and at what price.

PJM’s capacity market involves a yearly auction. The auction works as follows. Resource owners offer to sell a set amount of capacity at a specific rate. PJM accepts offers, beginning with the offer at the lowest rate, until the system has sufficient capacity to meet projected demand. Re *660 gardless of the resource owner’s offer price, PJM purchases all capacity at the rate of the highest accepted bid—the market-clearing price. The utilities then pay for their assigned share of capacity. When the utilities within PJM’s system need more electricity in order to meet consumer demand, PJM calls on resources with a capacity commitment. Capacity resources must provide their committed share of the needed electricity. See Hughes v. Talen Energy Mktg., L.L.C., — U.S.-, 136 S.Ct. 1288, 1293, 194 L.Ed.2d 414 (2016).

PJM has operated this capacity market since 2006. See generally PJM Interconnection, L.L.C., 117 FERC ¶ 61,331 (2006). It had market rules in place to enforce capacity commitments. According to PJM, the rules were not working. Resource owners were making capacity commitments but not providing electricity when it was needed. The penalties for a capacity resource that did not provide electricity were slight and easily avoided.

PJM wanted to establish new enforcement mechanisms to ensure resources thát made a capacity commitment provided electricity when called upon. In December 2014, PJM submitted revised capacity market rules to the Federal Energy Regulatory Commission for its approval under section 205 of the Federal Power Act, 16 U.S.C. § 824d. PJM concurrently submitted a separate filing under section 206 of the Federal Power Act, 16 U.S.C. § 824e, which suggested that some of PJM’s energy market rules would become unjust and unreasonable if the Commission approved the new capacity market rules. We will more thoroughly discuss the relevant details of the revised rules when addressing each of petitioners’ various challenges. Generally, PJM’s revised rules would require resources participating in the capacity market to be able to deliver the committed level of electricity at any time for the entire delivery ye.ar. PJM proposed various market mechanisms to ensure the resources would actually deliver the electricity when it is needed. These included the ability to offer capacity at a higher price in the auctions; bonuses for producing additional electricity; and steep penalties for resources that did not meet their capacity commitment, with very limited exemptions.

In June 2015, the Commission approved PJM’s proposed changes. PJM Interconnection, L.L.C., Order on Proposed Tariff Revisions, 151 FERC ¶ 61,208 (2015) (“Tariff Order”). The Commission denied rehearing. PJM Interconnection, L.L.C., Order on Rehearing and Compliance, 155 FERC ¶ 61,157 (2016) (“Rehearing Order”). Nine organizations 2 petitioned this court for review. The petitioners, together and separately, raise eight challenges.

II.

Seven of the petitioners argue that the Commission did not adequately consider the costs and benefits of PJM’s proposal. The Commission balanced the benefits of the revised rules against the increased costs and reached a reasoned judgment. See, e.g., Blumenthal v. FERC, 552 F.3d 875, 885 (D.C. Cir. 2009). The Commis *661 sion’s decision was not arbitrary or capricious. See, e.g., Pub. Utilities Comm’n of State of Cal. v. FERC, 254 F.3d 250, 253 (D.C. Cir. 2001).

PJM presented significant evidence that the old capacity market was not ensuring reliable electricity. PJM explained that the system obtained sufficient capacity during auctions. But resources frequently did not perform when called upon. PJM faced particular problems in January 2014. The PJM service region experienced unusually cold weather that resulted in very high demand for electricity. Twenty-two percent of PJM’s resources experienced an outage and could not provide any power. In addition, PJM demonstrated increasing levels of resource outages. And those outages were likely to continue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Harbor, LLC v. FERC
D.C. Circuit, 2025
Hecate Energy LLC v. FERC
126 F.4th 660 (D.C. Circuit, 2025)
Tenaska Clear Creek Wind, LLC v. FERC
108 F.4th 858 (D.C. Circuit, 2024)
New York State Public Service Commission v. FERC
104 F.4th 886 (D.C. Circuit, 2024)
American Municipal Power, Inc. v. FERC
86 F.4th 922 (D.C. Circuit, 2023)
Vistra Corp. v. FERC
80 F.4th 302 (D.C. Circuit, 2023)
Citadel FNGE Ltd. v. FERC
77 F.4th 842 (D.C. Circuit, 2023)
California Public Utilities Commission v. FERC
20 F.4th 795 (D.C. Circuit, 2021)
Public Citizen, Inc. v. FERC
7 F.4th 1177 (D.C. Circuit, 2021)
Delaware Division of the Public Advocate v. FERC
3 F.4th 461 (D.C. Circuit, 2021)
Nebraska Public Power District v. FERC
957 F.3d 932 (Eighth Circuit, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
860 F.3d 656, 2017 WL 2636455, 2017 U.S. App. LEXIS 10815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/advanced-energy-management-alliance-v-federal-energy-regulatory-commission-cadc-2017.