Nebraska Public Power District v. FERC

957 F.3d 932
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 30, 2020
Docket19-1553
StatusPublished
Cited by2 cases

This text of 957 F.3d 932 (Nebraska Public Power District v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nebraska Public Power District v. FERC, 957 F.3d 932 (8th Cir. 2020).

Opinion

United States Court of Appeals For the Eighth Circuit ___________________________

No. 19-1553 ___________________________

Nebraska Public Power District

lllllllllllllllllllllPetitioner

v.

Federal Energy Regulatory Commission

lllllllllllllllllllllRespondent

GridLiance High Plains LLC; Southwest Power Pool; Tri-State Generation & Transmission Assn.

lllllllllllllllllllllIntervenors

------------------------------

Edison Electric Institute

lllllllllllllllllllllAmicus on Behalf of Petitioner ____________

Petition for Review of an Order of the Federal Energy Regulatory Commission ____________

Submitted: January 15, 2020 Filed: April 30, 2020 ____________ Before SMITH, Chief Judge, LOKEN and GRUENDER, Circuit Judges. ____________

SMITH, Chief Judge.

Southwest Power Pool (SPP) is a Regional Transmission Organization (RTO) authorized by the Federal Energy Regulatory Commission (FERC) to provide electric transmission services across a multi-state region. Under SPP’s license-plate rate design,1 SPP is divided into different zones, and customers in each zone pay rates based on the cost of transmission facilities in that zone.

In 2018, FERC approved SPP’s placement of Tri-State Generation & Transmission Association (“Tri-State”) into Zone 17. Nebraska Public Power District (NPPD), as a member of Zone 17, challenges FERC’s decision, arguing that FERC erred in concluding that the proposed placement was just and reasonable. Specifically, NPPD alleges that FERC failed to conclude, based on substantial evidence, that the benefits that NPPD and other Zone 17 facilities receive from Tri-State’s transmission facilities are at least roughly commensurate with the costs allocated to Zone 17 as a result of Tri-State’s placement in Zone 17. We deny the petition and affirm FERC’s decision.

I. Background A. Statutory and Regulatory Framework This case arises out of Section 205 of the Federal Power Act (FPA). Under Section 205 of the FPA, “[a]ll rates and charges made, demanded, or received by any

1 In a license-plate rate design, transmission service in the RTO is “priced according to the power’s destination.” Ala. Mun. Elec. Auth. v. FERC, 662 F.3d 571, 573–74 (D.C. Cir. 2011). Explained another way, every transmission owner in that particular area, or zone, is charged the same rate. Id. at 574.

-2- public utility for or in connection with the transmission or sale of electric energy subject to the jurisdiction of [FERC], . . . shall be just and reasonable.” 16 U.S.C. § 824d(a). “Section 205(d) provides that unless [FERC] otherwise orders, ‘no change shall be made by any public utility in any such rate, charge, classification, or service, or in any rule, regulation, or contract relating thereto, except after sixty days’ notice to [FERC] and to the public.’” Xcel Energy Servs. Inc. v. FERC, 815 F.3d 947, 949 (D.C. Cir. 2016) (quoting id. § 824d(d)).

To eliminate free market barriers in wholesale electricity and to reduce technical inefficiency, FERC promulgated regulations to encourage transmission providers to establish RTOs. See Morgan Stanley Capital Grp. v. Pub. Util. Dist. No. 1 of Snohomish Cty., 554 U.S. 527, 536–37 (2008); see also Order No. 2000, 65 Fed. Reg. 810, 810–12 (Jan. 6, 2000) (codified at 18 C.F.R. § 35.34). RTOs are entities, independent of any market participant, that exercise operational control over transmission facilities owned by the RTO’s members. Morgan Stanley, 554 U.S. at 536. To that end, FERC encouraged Independent System Operators (ISOs), “not-for- profit entities that operate transmission facilities in a nondiscriminatory manner,” to manage the RTOs. Id. at 536–37.

In 2004, FERC authorized SPP to form a RTO to provide electric transmission services across a multi-state region using the transmission facilities of 15 different utilities placed in 15 different zones. Under SPP’s license-plate (or zonal) rate design, customers located in each zone pay rates based on the cost of the transmission facilities located in that zone. Since 2004, SPP has expanded its geographical footprint by establishing new rate zones for larger transmission providers and by placing smaller transmission providers into existing zones. When a new transmission owner (TO) joins SPP and is placed into an existing zone, the cost of that new TO’s transmission facilities is added to the rates charged by SPP for transmission in that zone. Therefore, adding a new TO affects the rate for existing customers in that zone.

-3- B. Existing Relationship of NPPD and Tri-State Tri-State’s and NPPD’s history as electric transmission providers informs Tri- State’s placement into Zone 17. NPPD and Tri-State have a relationship that dates back decades before Tri-State joined Zone 17. In 1975, NPPD and Tri-State entered into a Memorandum of Agreement to establish principles for the joint operation and planning of their transmission facilities in Nebraska. Later, on June 8, 1984, the two transmission providers entered into the Western Nebraska Joint Transmission Agreement (“Agreement”) to “establish a joint transmission system for the Parties’ mutual benefit and joint use.” Pet’r’s App. at 62.

The Agreement explained that “portions of Tri-State’s electric power transmission facilities in Western Nebraska are interconnected with NPPD’s electric power transmission system and are operated in synchronism with it.” Id. at 61. Further, the Agreement provided that the facilities should use the Single-Entity Concept, which meant that the providers should operate the systems as if they were owned by one provider. And, the Agreement gave NPPD and Tri-State the right to use each other’s transmission systems to serve their own customers.

The Agreement also had a Costs and Benefits section, which provided that “[e]ach Party shall receive benefits commensurate with its actual costs. Such benefits shall be in the form of transmission use of [the Agreement] and in the form of Annual Equalization Payments from one Party to the other.” Id. at 66. The Annual Equalization Payment covered interest, an estimated amount for operations and maintenance expense, and administrative and general costs. The Agreement measured the providers’ use of the transmission facilities under the annual coincident peak method, which measured each provider’s use at the time the combined use of the facilities was at its peak for the entire year. Under this method, Tri-State paid NPPD an average of $1 million each year.

-4- However, the payments could vary depending upon the peak method employed. For example, using a month coincident peak method, Tri-State averages 41 percent of the use of the facilities and NPPD averages 59 percent. This would result in a benefit of $550,000 a year to NPPD. SPP uses the month coincident peak method to establish transmission rates.

After over 40 years of joint use, the transmission facilities of Tri-State and NPPD are now highly integrated. They share at least five points of interconnection. And, NPPD would lack a transmission path to some of its customers if it could not use Tri-State’s facilities. NPPD thus relies on its ability to use Tri-State’s facilities to serve its customers.

C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Lincoln v. FERC
89 F.4th 926 (D.C. Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
957 F.3d 932, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nebraska-public-power-district-v-ferc-ca8-2020.