Illinois Commerce Commission v. Federal Energy Regulatory Commission

756 F.3d 556, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2014 WL 2873936, 2014 U.S. App. LEXIS 11961
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 25, 2014
Docket13-1674, 13-1676, 13-2052, 13-2262
StatusPublished
Cited by5 cases

This text of 756 F.3d 556 (Illinois Commerce Commission v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Illinois Commerce Commission v. Federal Energy Regulatory Commission, 756 F.3d 556, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2014 WL 2873936, 2014 U.S. App. LEXIS 11961 (7th Cir. 2014).

Opinions

POSNER, Circuit Judge.

It’s been almost five years since we remanded this case to the Federal Energy Regulatory Commission. Illinois Commerce Commission v. FERC, 576 F.3d 470 (7th Cir.2009). The petitioners who persuaded us to remand the Commission’s order, which allocated costs for certain new high-voltage network transmission lines (consisting of the transmission lines themselves plus transformers, capacitors, and other ancillary equipment — for simplicity we’ll generally refer to the entire facility as a “transmission line”), are not satisfied with the order that the Commission issued on remand. For that order [557]*557reinstated without change the order that we had vacated.

The petitioners are primarily the mid-western members of a Regional Transmission Organization (plus the Illinois Commerce Commission, which essentially is appearing on behalf of Commonwealth Edison, the largest electrical utility in Illinois) called PJM Interconnection. A Regional Transmission Organization is a voluntary association primarily of utilities that either own electrical transmission lines that comprise a regional electrical grid or generate electricity that is transmitted to the customers in the region. The association operates the grid on behalf of the members.

PJM has the largest peak load (the amount of electrical power expected to be provided for a sustained period of above-average demand) of any Regional Transmission Organization — also the largest population and the most transmission mileage. Its region stretches east and south from the Chicago area (northeastern Uli-nois) to western Michigan, eastern Indiana, Ohio, Kentucky, Tennessee, West Virginia, Pennsylvania, New Jersey, Delaware, Maryland, the District of Columbia, North Carolina, and Virginia. Most mid-western utilities, however, belong not to PJM but to an Independent System Operator (which is similar to a Regional Transmission Organization, however) called Mid-continent Independent System Operator, Inc. (MISO). As shown on the map (prepared by the ISO/RTO Council, www. isorto.org/about/default, visited June 23, 2014, as were the other websites cited in this opinion), MISO operates in the Midwest, South, and some of the Great Plains states, in contrast to PJM, which operates mainly in the mid-Atlantic region but also, though to a considerably lesser extent, in the Midwest. The Federal Energy Regulatory Commission’s order is addressed only to PJM, but MISO will play a bit role our analysis.

Regional Transmission Organizations

[[Image here]]

[558]*558What we’ll refer to as the western region of PJM consists of the parts of Michigan, Illinois, and Indiana shown on the map as being in PJM’s domain, along with all of Ohio. Electrical generating plants in the western region usually are close to the customers — Chicago, for example, a major electricity market, is ringed by power plants — and so in that region relatively low-voltage transmission lines (typically 345-kilovolts) are adequate for serving most customers, although the region also has a number of high-voltage — 765-kV— lines for transmitting electricity with greater efficiency, mainly from Indiana to customers in Chicago. The cities in the eastern region use even lower voltage (230-kV lines) than the cities in the western region, but most of the power plants are farther away from the customers than in PJM’s western region and therefore 500-kV lines are preferred even though more expensive; the reason is that higher voltage reduces the amount of electricity that is lost as a function of the distance over which it is transmitted.

The question presented by the petition for review is the extent to which the members of PJM in its western region (we’ll call these the “western utilities”) can be required to contribute to the costs of newly built or to-be-built 500-kV lines (we’ll call these the “new transmission lines”) even though the lines are primarily in the eastern part of PJM. Originally at issue were 18 such lines and related projects, expected to cost $6.6 billion in toto. The number of new lines has dwindled to 12 (11 already built, the other under construction; but 3 more are under study). The current estimate of the total cost of the projects that have been or will be completed is $2.7 billion.

PJM’s western utilities are unlikely to obtain a significant additional supply of electricity from the new transmission lines. The capacity of the western utilities to generate electricity is already ample — so ample that they transmit a great deal of their electricity to the eastern members of PJM to help them meet the heavy eastern demand for electricity. Because the demand for electricity is so much greater in PJM’s eastern subregion, it’s unlikely that much electricity will be transmitted from the eastern to the western utilities via the new transmission lines.

Still, the western utilities may benefit from the new high-voltage transmission lines in PJM’s eastern region, and to the extent they do they can be required to contribute to the cost of building the new lines. The Commission’s order that we set aside five years ago made no effort to quantify those benefits, however; instead it allocated the costs of the new transmission lines among all the members of PJM in proportion to each utility’s electricity sales, a pricing method analogous to a uniform sales tax. The Commission acknowledged that this was a crude method of cost allocation — which is to put it mildly, because without quantifying the benefits of the eastern projects to the western utilities it is impossible to determine what those utilities should be charged: charging costs greater than the benefits would overcharge the utilities, and charging costs less than the benefits would undercharge them. The Commission defended its approach by appealing to the difficulty of measuring the benefits that the western utilities would derive from the new lines. We considered that a feeble defense. We said that “FERC is not authorized to approve a pricing scheme that requires a group of utilities to pay for facilities from which its members derive no benefits, or benefits that are trivial in relation to the costs sought to be shifted to its members.” 576 F.3d at 476. We acknowledged that “if [the Commission] cannot quantify the benefits to the midwestern utilities from new [559]*559500 kV lines in the East, ... but it has an articulable and plausible reason to believe that the benefits are at least roughly commensurate with those utilities’ share of total electricity sales in PJM’s region, then fine; the Commission can approve PJM’s proposed pricing scheme on that basis.” Id. at 477. But the Commission hadn’t met that standard either. So we remanded.

Almost three years elapsed before the Commission issued its order on remand. PJM Interconnection, L.L.C., 138 FERC P 61230 (March 30, 2012). A year later the Commission supplemented the order on rehearing, PJM Interconnection, L.L.C., 142 FERC P 61216 (March 22, 2013), and now, a year farther on, the western utilities are back before us, challenging the order on remand — which like the order we set aside prescribes “a region-wide postage-stamp allocation of the costs of new transmission facilities that operate at and above 500 kV.” PJM Interconnection, L.L.C., supra, 138 FERC P 61230, ¶ 49. This is FERC-speak for allocating the costs of the high-voltage lines across all the PJM utilities, east or west, in proportion to each utility’s respective sales.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Long Island Power Authority v. FERC
27 F.4th 705 (D.C. Circuit, 2022)
Nebraska Public Power District v. FERC
957 F.3d 932 (Eighth Circuit, 2020)
Bennett v. Islamic Republic of Iran
817 F.3d 1131 (Ninth Circuit, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
756 F.3d 556, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20137, 2014 WL 2873936, 2014 U.S. App. LEXIS 11961, Counsel Stack Legal Research, https://law.counselstack.com/opinion/illinois-commerce-commission-v-federal-energy-regulatory-commission-ca7-2014.